The beam line valve should remain close to isolate the beam line vacuum to the
HKS system when the later parts are not in vacuum. To establish the vacuum,
- Beam line valve should remain close (controlled by MCC).
- The target ladder should remain retrieved inside the driver and vacuum
isolation valve closed.
- Start pumping vacuum for the three parts in the HKS system until the
vacuum level reaches about
- Slowly or in small steps open the target ladder vacuum isolation valve
until vacuum recovers to
while the valve fully opened.
- Finally, call MCC to open the beam line valve. With a higher pumping
speed from beam line, the entire system may reach or better
quickly.