Schedule of the spectrometer construction and requested support

The construction of the HKS spectrometer and the new hypernuclear spectrometer system has already started in 2000. The present schedule for the construction is shown in Table 10. It is the present plan to ship the HKS spectrometer system from Japan to Jlab by the end of 2002. Detectors are under construction by the collaboration groups and will also be prepared by then.

It is planned that the spectrometer system will be assembled in the Test Lab. prior to the installation in Hall C. The collaboration sets the due date ready to accept a beam March 2003.


表 10: Present expected time line of the project
April, 2000 - March, 2001  
  Design of the spectrometer system
  Contract with a magnet manufacture
  Construction of Q1 and Q1
  Design of detectors
April, 2001 - March, 2002  
  Construction of the dipole magnet
  R&D test of detectors (TOF, AC etc.)
  Design and construction of the drift chambers
  Design and construction of TOF, LC
April, 2002 - March, 2003  
  Field mapping of the dipole magnet
  Transportation of the dipole to Jlab
  Assembly and test of the spectrometer magnet at Jlab
  Completion of the detector construction
  Assembly of the detector system at Jlab
  Installation of the spectrometer system in the Hall