1
|
2008 Jun. to Oct. Hall-C SANE installation and HHS/HES Prep.
|
Jun 9
|
Sep 23
|
|
500
|
0%
|
|
2
|
Meeting with Hall C Staff, RADCON, ALIGN, ACC, EH&S, Target group
|
Jun 9
|
Jun 9
|
|
500
|
0%
|
|
3
|
Beam line and target Radiation cool down
|
Jun 9
|
Jun 16
|
6d
|
500
|
0%
|
|
4
|
Prepare safety / work documentation for this schedule
|
Jun 9
|
Jun 16
|
6d
|
500
|
0%
|
|
5
|
GEP decommissioning June 9 to July 3
|
Jun 9
|
Jun 24
|
|
500
|
0%
|
|
6
|
Clear truck ramp, move in areal platforms, tools and equipment into Hall
|
Jun 9
|
Jun 9
|
1d
|
500
|
0%
|
|
7
|
RADCON support required
|
Jun 9
|
Jun 9
|
1d
|
500
|
0%
|
|
8
|
Crane HES dipole sections to beam left side
|
Jun 17
|
Jun 17
|
1d
|
500
|
0%
|
|
9
|
Move HMS to 45 deg.
|
Jun 17
|
Jun 17
|
1d
|
500
|
0%
|
|
10
|
Crane BIG CAL close to wall (to clear space)
|
Jun 17
|
Jun 17
|
1d
|
500
|
0%
|
|
11
|
Crane 45' JLG and 45' Groove to downstream beam line
|
Jun 20
|
Jun 20
|
1d
|
500
|
0%
|
|
12
|
Disassemble beam line from pivot to dump and store in Hall
|
Jun 25
|
Jun 26
|
2d
|
500
|
0%
|
|
13
|
RADCON support required
|
Jun 25
|
Jun 26
|
2d
|
500
|
0%
|
|
14
|
Install and commission Secondary emission monitor
|
Jul 7
|
Jul 16
|
|
500
|
0%
|
|
15
|
Disconnect and remove up stream girder
|
Aug 11
|
Aug 11
|
1d
|
500
|
0%
|
|
16
|
RADCON support required
|
Aug 11
|
Aug 11
|
1d
|
500
|
0%
|
|
17
|
Mount SEM onto new girder and bolt girder assembly into position
|
Aug 12
|
Aug 12
|
1d
|
500
|
0%
|
|
18
|
Connect girder beam line and cables
|
Aug 15
|
Aug 18
|
2d
|
500
|
0%
|
|
19
|
Align and secure girder
|
Aug 15
|
Aug 15
|
1d
|
500
|
0%
|
|
20
|
FPP removal and standard HMS detector reinstallation
|
Jun 16
|
Jul 4
|
|
500
|
0%
|
|
21
|
Move all 4 wire chamber boxes from storage Bld to Hall C HMS side
|
Jun 16
|
Jun 16
|
|
500
|
0%
|
|
22
|
Crane 45' JLG's into position
|
Jun 18
|
Jun 18
|
1d
|
500
|
0%
|
|
23
|
Crane HMS shield house wall sections down and secure to frame
|
Jun 18
|
Jun 18
|
1d
|
500
|
0%
|
|
24
|
Disconnect and remove FPP Electronic racks
|
Jun 19
|
Jun 19
|
1d
|
500
|
0%
|
|
25
|
RADCON support required
|
Jun 20
|
Jun 20
|
1d
|
500
|
0%
|
|
26
|
Disconnect and remove HMS trigger electronics
|
Jun 19
|
Jun 19
|
1d
|
500
|
0%
|
|
27
|
RADCON support required
|
Jun 19
|
Jun 19
|
1d
|
500
|
0%
|
|
28
|
Remove small scintillator assembly in front of exit window
|
Jun 20
|
Jun 20
|
1d
|
500
|
0%
|
|
29
|
Position and connect installation fixtures 67502-00019
|
Jun 23
|
Jun 24
|
2d
|
500
|
0%
|
|
30
|
Disconnect and remove wire chambers
|
Jun 23
|
Jun 24
|
2d
|
500
|
0%
|
|
31
|
Place chambers in shipping crate and cover
|
Jun 23
|
Jun 24
|
2d
|
500
|
0%
|
|
32
|
RADCON support required
|
Jun 23
|
Jun 24
|
2d
|
500
|
0%
|
|
33
|
Set up and align installation fixtures for CH2 blocks
|
Jun 25
|
Jun 26
|
2d
|
500
|
0%
|
|
34
|
RADCON support required
|
Jun 25
|
Jun 26
|
2d
|
500
|
0%
|
|
35
|
Unbolt and slide out all CH2 blocks then crane out storage
|
Jun 25
|
Jun 26
|
2d
|
500
|
0%
|
|
36
|
RADCON support required
|
Jun 25
|
Jun 26
|
2d
|
500
|
0%
|
|
37
|
Remove installation fixture
|
Jun 26
|
Jun 26
|
1d
|
500
|
0%
|
|
38
|
Unbolt and remove wire chamber ALU support frame
|
Jun 26
|
Jun 26
|
1d
|
500
|
0%
|
|
39
|
Restore position for first hodoscope plane
|
Jun 26
|
Jun 26
|
1d
|
500
|
0%
|
|
40
|
Reinstall Cerenkov detector
|
Jun 26
|
Jun 26
|
1d
|
500
|
0%
|
|
41
|
Align Cerenkov detector and secure
|
Jun 27
|
Jun 27
|
1d
|
500
|
0%
|
|
42
|
Reinstall aerogell chamber
|
Jun 30
|
Jun 30
|
1d
|
500
|
0%
|
|
43
|
Install 2nd hodoscopes plane
|
Jun 30
|
Jun 30
|
1d
|
500
|
0%
|
|
44
|
HMS detector hut light bulbs
|
Jul 1
|
Jul 1
|
1d
|
500
|
0%
|
|
45
|
BIG CAL glass anneal
|
Sep 1
|
Nov 5
|
|
500
|
0%
|
|
46
|
Uncover and prepare lead glass detector stack
|
Jun 17
|
Jun 18
|
2d
|
500
|
0%
|
|
47
|
Crane and install and connect UV lights
|
Jun 18
|
Jun 18
|
1d
|
500
|
0%
|
|
48
|
Reposition UV lights during anneal as required
|
Jun 18
|
Aug 19
|
50d
|
500
|
0%
|
|
49
|
Disconnect UV lights and crane of BIG CAL
|
Aug 26
|
Aug 26
|
1d
|
500
|
0%
|
|
50
|
Cover and seal lead glass stack
|
Sep 1
|
Sep 3
|
3d
|
500
|
0%
|
|
51
|
Cryo Target disassembly and removal (from Dave Meekins)
|
Jul 2
|
Jul 23
|
17d
|
500
|
0%
|
|
52
|
Warm up Cryo Target an vent scatting chamber
|
Jun 9
|
Jun 10
|
2d
|
500
|
0%
|
|
53
|
Target Radiation cool down period
|
Jun 17
|
Jun 23
|
5d
|
500
|
0%
|
|
54
|
Install pivot extensions and railing
|
Jun 17
|
Jun 17
|
1d
|
500
|
0%
|
|
55
|
RADCON support required
|
Jun 17
|
Jun 17
|
1d
|
500
|
0%
|
|
56
|
Remove scatting chamber windows
|
Jun 18
|
Jun 18
|
1d
|
500
|
0%
|
|
57
|
RADCON support required
|
Jun 18
|
Jun 18
|
1d
|
500
|
0%
|
|
58
|
Post run survey of target cells
|
Jun 19
|
Jun 20
|
2d
|
500
|
0%
|
|
59
|
Crane in and place Groove 45' areal platform in place (beam left)
|
Jun 23
|
Jun 23
|
1d
|
500
|
0%
|
|
60
|
Place 60' JLG (beam right)
|
Jun 23
|
Jun 23
|
1d
|
500
|
0%
|
|
61
|
With Cryo group support un-sting target valve box from distribution can
|
Jun 23
|
Jun 23
|
1d
|
500
|
0%
|
|
62
|
Disconnect plumbing and electronics from top of target
|
Jun 24
|
Jun 24
|
1d
|
500
|
0%
|
|
63
|
Disconnect the refrigeration transfer lines and store on top of cable tray
|
Jun 25
|
Jun 25
|
1d
|
500
|
0%
|
|
64
|
Tie back the plumbing and electrical lines for target
|
Jun 25
|
Jun 25
|
1d
|
500
|
0%
|
|
65
|
Use lifting fixture and crane to remove target from pivot
|
Jun 26
|
Jun 26
|
1d
|
500
|
0%
|
|
66
|
Disconnect cells and cell blocks and transfer them to the EEL Rad area.
|
Jun 27
|
Jun 27
|
1d
|
500
|
0%
|
|
67
|
RADCON support required
|
Jun 26
|
Jun 26
|
1d
|
500
|
0%
|
|
68
|
Place target on forklift and transfer it to EEL target group area
|
Jun 30
|
Jun 30
|
1d
|
500
|
0%
|
|
69
|
Polarized Target installation and commissioning
|
Jul 15
|
Sep 17
|
52d
|
500
|
0%
|
|
70
|
Transport target equipment deck, pivot and upper ALU deck to Hall C
|
Jul 8
|
Jul 9
|
2d
|
500
|
0%
|
|
71
|
Relocate signal cables between shield hut and pivot to clear platform install.
|
Jul 10
|
Jul 11
|
2d
|
500
|
0%
|
|
72
|
Layout and bolt equipment deck support legs to the floor
|
Jul 14
|
Jul 14
|
1d
|
500
|
0%
|
|
73
|
Crane in and bolt deck onto support legs
|
Jul 14
|
Jul 14
|
1d
|
500
|
0%
|
|
74
|
Weld end flanges to the pivot deck
|
Jul 15
|
Jul 15
|
1d
|
500
|
0%
|
|
75
|
RADCON support required
|
Jul 15
|
Jul 15
|
1d
|
500
|
0%
|
|
76
|
Install staircase, weld to deck then bolt to floor
|
Jul 15
|
Jul 15
|
1d
|
500
|
0%
|
|
77
|
Install scattering chamber base on pivot
|
Jul 16
|
Jul 16
|
1d
|
500
|
0%
|
|
78
|
Crane in scattering chamber and bolt to base
|
Jul 16
|
Jul 16
|
1d
|
500
|
0%
|
|
79
|
Place LHE dewer and electronics racks onto equipment deck
|
Jul 17
|
Jul 18
|
2d
|
500
|
0%
|
|
80
|
Install target control systems
|
Jul 18
|
Jul 31
|
11d
|
500
|
0%
|
|
81
|
Place target into chamber
|
Jul 21
|
Jul 21
|
1d
|
500
|
0%
|
|
82
|
Connect to vacuum system
|
Jul 22
|
Jul 24
|
3d
|
500
|
0%
|
|
83
|
Connect cryogenic system, U-tubes etc.
|
Jul 24
|
Jul 24
|
1d
|
500
|
0%
|
|
84
|
Pump out scattering chamber and leak check
|
Jul 29
|
Aug 1
|
4d
|
500
|
0%
|
|
85
|
Target test cool down
|
Oct 1
|
Oct 8
|
6d
|
500
|
0%
|
|
86
|
G-0 Magnet move from Hall C to long term storage (52 tons)
|
Jul 7
|
Aug 1
|
|
500
|
0%
|
|
87
|
Move HMS to large angle to max floor space
|
Jul 7
|
Jul 7
|
1d
|
500
|
0%
|
|
88
|
Clear floor space, move beam line and RAD parts to a secure location
|
Jul 7
|
Jul 7
|
1d
|
500
|
0%
|
|
89
|
RADCON support required
|
Jul 7
|
Jul 7
|
1d
|
500
|
0%
|
|
90
|
Move HKS magnets and FW close to the wall
|
Jul 8
|
Jul 8
|
1d
|
500
|
0%
|
|
91
|
Assure BIG CAL and cable train are safe
|
Jul 9
|
Jul 9
|
1d
|
500
|
0%
|
|
92
|
Move G-0 magnet into position and secure
|
Jul 9
|
Jul 9
|
1d
|
500
|
0%
|
|
93
|
Remove 22" lead pipe, pack into box and move to lead storage Bld.
|
Jul 9
|
Jul 9
|
1d
|
500
|
0%
|
|
94
|
RADCON support required
|
Jul 9
|
Jul 9
|
1d
|
500
|
0%
|
|
95
|
Remove downstream end cap and lay onto cribbing
|
Jul 7
|
Jul 7
|
1d
|
500
|
0%
|
|
96
|
RADCON support required
|
Jul 11
|
Jul 14
|
2d
|
500
|
0%
|
|
97
|
Remove upstream end cap and lay onto cribbing
|
Jul 9
|
Jul 9
|
1d
|
500
|
0%
|
|
98
|
RADCON support required
|
Jul 11
|
Jul 14
|
2d
|
500
|
0%
|
|
99
|
Unbolt lead, pack into containers and move lead storage Bld.
|
Jul 11
|
Jul 14
|
2d
|
500
|
0%
|
|
100
|
RADCON support required
|
Jul 10
|
Jul 10
|
1d
|
500
|
0%
|
|
101
|
Remove all 8 titanium windows and place into storage box
|
Jun 10
|
Jun 10
|
1d
|
500
|
0%
|
|
102
|
RADCON support required
|
Jul 11
|
Jul 11
|
1d
|
500
|
0%
|
|
103
|
Bolt both end caps together, seal and move to lead storage Bld.
|
Jul 11
|
Jul 11
|
1d
|
500
|
0%
|
|
104
|
RADCON support required
|
Jul 11
|
Jul 11
|
1d
|
500
|
0%
|
|
105
|
Install shipping frame onto magnet, torque bolts and seal gaps
|
Jul 18
|
Jul 22
|
3d
|
500
|
0%
|
|
106
|
Truck cribbing mats and rails into Hall and lay out for position 1
|
Jul 23
|
Jul 24
|
2d
|
500
|
0%
|
|
107
|
Move 2 hydraulic towers, pump, H beam and swivel in and setup
|
Jul 23
|
Jul 23
|
1d
|
500
|
0%
|
|
108
|
Lineup towers, connect magnet to swivel and takeout slack
|
Jul 24
|
Jul 24
|
1d
|
500
|
0%
|
|
109
|
Unbolt magnet from base, lift, rotate and move to the Hall center
|
Jul 24
|
Jul 24
|
1d
|
500
|
0%
|
|
110
|
Set magnet on cribbing, disconnect and remove hydraulic towers.
|
Jul 25
|
Jul 25
|
1d
|
500
|
0%
|
|
111
|
Move cribbing mats and rails to position 2
|
Jul 28
|
Jul 28
|
1d
|
500
|
0%
|
|
112
|
Set up 2 pairs of hydraulic towers with H beams
|
Jul 28
|
Jul 28
|
1d
|
500
|
0%
|
|
113
|
Lift and rotate magnet 90 derg. then onto rollers and secure
|
Jul 29
|
Jul 29
|
1d
|
500
|
0%
|
|
114
|
Pull magnet up the truck ramp and into position for loading
|
Jul 29
|
Jul 29
|
1d
|
500
|
0%
|
|
115
|
Load magnet onto trailer, secure and move lead storage Bld.
|
Jul 30
|
Jul 30
|
1d
|
500
|
0%
|
|
116
|
RADCON support required
|
Jul 30
|
Jul 30
|
1d
|
500
|
0%
|
|
117
|
Unload magnet and roll into lead storage Bld.
|
Jul 30
|
Jul 30
|
1d
|
500
|
0%
|
|
118
|
RADCON support required
|
Jul 30
|
Jul 30
|
1d
|
500
|
0%
|
|
119
|
Remove all Lockwood equipment from Hall C
|
Jul 30
|
Jul 30
|
1d
|
500
|
0%
|
|
120
|
Shrink-wrap G-0 magnet
|
Aug 1
|
Aug 1
|
1d
|
500
|
0%
|
|
121
|
Setup N2 flow from CHL through magnet
|
Aug 6
|
Aug 7
|
2d
|
500
|
0%
|
|
122
|
HES / HKS preparation (concrete, magnet assembly etc)
|
Sep 8
|
Oct 6
|
|
500
|
0%
|
|
123
|
Drill and tap for hoist rings, then place 7/8" steel under new HES base
|
Aug 6
|
Aug 7
|
2d
|
500
|
0%
|
|
124
|
Assemble HES magnets base with hilman rollers and hydraulic system
|
Aug 11
|
Aug 12
|
2d
|
500
|
0%
|
|
125
|
Place lower dipole half in position and bolt down
|
Aug 11
|
Aug 11
|
1d
|
500
|
0%
|
|
126
|
Move upper dipole half on top and torque down
|
Aug 12
|
Aug 12
|
1d
|
500
|
0%
|
|
127
|
Crane Q1 into position next to dipole, align and torque down
|
Aug 12
|
Aug 12
|
1d
|
500
|
0%
|
|
128
|
Crane Q2 into position next to dipole, align and torque down
|
Aug 13
|
Aug 13
|
1d
|
500
|
0%
|
|
129
|
Connect vacuum chambers and leak check
|
Aug 20
|
Aug 25
|
4d
|
500
|
0%
|
|
130
|
Fiducialize magnet assembly
|
Aug 22
|
Aug 25
|
2d
|
500
|
0%
|
|
131
|
Layout of 9.5" concrete pad extension for new location of the HKS dipole
|
Aug 22
|
Aug 22
|
1d
|
500
|
0%
|
|
132
|
Roll HES magnet assembly and HKS dipole close to the wall to clear space
|
Aug 22
|
Aug 22
|
1d
|
500
|
0%
|
|
133
|
Brake open and remove concrete over the SOS rail section
|
Aug 25
|
Aug 26
|
2d
|
500
|
0%
|
|
134
|
Unbolt and remove SOS rail section and transport to bone yard
|
Aug 27
|
Aug 27
|
1d
|
500
|
0%
|
|
135
|
RADCON support required
|
Aug 27
|
Aug 27
|
1d
|
500
|
0%
|
|
136
|
Remove all bolts and nuts from the SOS rail base plate
|
Aug 27
|
Aug 27
|
1d
|
500
|
0%
|
|
137
|
Place plastic sheeting over the base plate, then temporary cove gap
|
Aug 27
|
Aug 27
|
1d
|
500
|
0%
|
|
138
|
Build concrete forms as marked for new HKS dipole position and place rebar
|
Sep 3
|
Sep 8
|
4d
|
500
|
0%
|
|
139
|
Fill SOS rail base gap with concrete and level
|
Sep 4
|
Sep 4
|
1d
|
500
|
0%
|
|
140
|
Pore concrete into HKS extension forms, level and finish
|
Sep 4
|
Sep 5
|
2d
|
500
|
0%
|
|
141
|
SANE beam line and low power dump installation
|
Oct 7
|
Nov 6
|
|
500
|
0%
|
|
142
|
Remove only necessary railing and pivot extensions to fit detector platform
|
Sep 2
|
Sep 2
|
1d
|
500
|
0%
|
|
143
|
Install and align Cerenkov detector platform
|
Sep 2
|
Sep 3
|
2d
|
500
|
0%
|
|
144
|
Crane in and bolt down support beam and post for lead shielding boxes
|
Sep 2
|
Sep 2
|
1d
|
500
|
0%
|
|
145
|
Align and weld box beam security brackets to pivot acc. to drwg.
|
Sep 3
|
Sep 3
|
1d
|
500
|
0%
|
|
146
|
RADCON support required
|
Sep 3
|
Sep 3
|
1d
|
500
|
0%
|
|
147
|
Weld security brackets for lead ALU shield boxes (SOS side) to pivot
|
Sep 3
|
Sep 3
|
1d
|
500
|
0%
|
|
148
|
RADCON support required
|
Sep 3
|
Sep 3
|
1d
|
500
|
0%
|
|
149
|
Place and secure ALU shield boxes on box beam and bolt down
|
Sep 3
|
Sep 3
|
1d
|
500
|
0%
|
|
150
|
Place and bolt down lead shield boxes on the SOS side
|
Sep 4
|
Sep 4
|
1d
|
500
|
0%
|
|
151
|
Assemble target chamber exit beam line section and support
|
Sep 4
|
Sep 4
|
1d
|
500
|
0%
|
|
152
|
Assemble He beam line unistrud support frame on the floor (dwg. 6750400050)
|
Sep 10
|
Sep 12
|
3d
|
500
|
0%
|
|
153
|
Layout anchor hole pattern for unistrud support frame
|
Sep 9
|
Sep 9
|
1d
|
500
|
0%
|
|
154
|
Lift up beam line support frame with 25' spreader bar and bolt to floor
|
Sep 10
|
Sep 10
|
1d
|
500
|
0%
|
|
155
|
Roll out He beam line bag and hang onto frame with crane (dwg. 6750400050)
|
Sep 10
|
Sep 10
|
1d
|
500
|
0%
|
|
156
|
Align and secure entire beam line
|
Sep 10
|
Sep 10
|
1d
|
500
|
0%
|
|
157
|
RADCON support required for work in beam dump area
|
Sep 10
|
Sep 10
|
1d
|
500
|
0%
|
|
158
|
Align Cerenkov detector mirrors (on the floor)
|
Sep 9
|
Sep 11
|
3d
|
500
|
0%
|
|
159
|
Place Cerenkov detector on platform
|
Sep 8
|
Sep 8
|
1d
|
500
|
0%
|
|
160
|
Align Cerenkov detector and secure
|
Sep 9
|
Sep 9
|
1d
|
500
|
0%
|
|
161
|
Connect all cables and detector gas system
|
Sep 10
|
Sep 10
|
1d
|
500
|
0%
|
|
162
|
Mount lucite detectors onto BIG CAL
|
Sep 9
|
Sep 9
|
1d
|
500
|
0%
|
|
163
|
Layout for 2nd beam line dump
|
Sep 9
|
Sep 9
|
1d
|
500
|
0%
|
|
164
|
Crane in S4 steel blocks and place with 4 ton wall cane
|
Sep 12
|
Sep 16
|
3d
|
500
|
0%
|
|
165
|
Install He-supply pipe for He bag (from gas Bld to beam dump)
|
Sep 16
|
Sep 17
|
2d
|
500
|
0%
|
|
166
|
SOS disassembly
|
Sep 26
|
Oct 7
|
|
500
|
0%
|
|
167
|
Remove SOS detectors
|
Sep 26
|
Oct 2
|
5d
|
500
|
0%
|
|
168
|
RADCON support required
|
Sep 22
|
Sep 25
|
4d
|
500
|
0%
|
|
169
|
Place rail section to large angle and shim to level
|
Sep 29
|
Sep 29
|
1d
|
500
|
0%
|
|
170
|
Place all toe-clamps
|
Sep 29
|
Sep 29
|
1d
|
500
|
0%
|
|
171
|
shim level and align Rail, then torque down toe-clamps
|
Sep 29
|
Sep 29
|
1d
|
500
|
0%
|
|
172
|
Move SOS to smaller angle
|
Sep 29
|
Sep 29
|
1d
|
500
|
0%
|
|
173
|
Remove hydraulic fluid
|
Sep 29
|
Sep 29
|
1d
|
500
|
0%
|
|
174
|
RADCON support required
|
Sep 29
|
Sep 29
|
1d
|
500
|
0%
|
|
175
|
Remove hydraulic tank and pump
|
Sep 29
|
Sep 29
|
1d
|
500
|
0%
|
|
176
|
RADCON support required
|
Sep 29
|
Sep 29
|
1d
|
500
|
0%
|
|
177
|
Disconnect and remove A/C unit
|
Sep 29
|
Sep 29
|
1d
|
500
|
0%
|
|
178
|
RADCON support required
|
Sep 29
|
Sep 29
|
1d
|
500
|
0%
|
|
179
|
Remove SOS doors
|
Sep 29
|
Sep 29
|
1d
|
500
|
0%
|
|
180
|
RADCON support required
|
Sep 29
|
Sep 29
|
1d
|
500
|
0%
|
|