1
|
2008 Jun. to Oct. Hall-C SANE installation and HHS/HES Prep.
|
Jun 9
|
Sep 23
|
|
500
|
0%
|
|
2
|
Meeting with Hall C Staff, RADCON, ALIGN, ACC, EH&S, Target group
|
Jun 9
|
Jun 9
|
|
500
|
0%
|
|
3
|
Beam line and target cool down
|
Jun 9
|
Jun 16
|
|
500
|
0%
|
|
4
|
Prepare safety / work documentation for this schedule
|
Jun 9
|
Jun 16
|
6d
|
500
|
0%
|
|
5
|
GEP decommissioning June 9 to July 3
|
Jun 9
|
Jun 9
|
|
500
|
0%
|
|
6
|
Clear truck ramp, move in areal platforms, tools and equipment into Hall
|
Jun 9
|
Jun 9
|
1d
|
500
|
0%
|
|
7
|
RADCON support required
|
Jun 9
|
Jun 9
|
1d
|
500
|
0%
|
|
8
|
Crane HES dipole sections to beam left side
|
Jun 9
|
Jun 9
|
1d
|
500
|
0%
|
|
9
|
Move HMS to 45 deg.
|
Jun 9
|
Jun 9
|
1d
|
500
|
0%
|
|
10
|
Crane BIG CAL close to wall (to clear space)
|
Jun 9
|
Jun 9
|
1d
|
500
|
0%
|
|
11
|
Disassemble beam line from pivot to dump and store in Hall
|
Jun 9
|
Jun 9
|
1d
|
500
|
0%
|
|
12
|
RADCON support required
|
Jun 9
|
Jun 9
|
1d
|
500
|
0%
|
|
13
|
FPP removal and standard HMS detector installation
|
Jun 17
|
Jun 17
|
|
500
|
0%
|
|
14
|
Crane 45' JLG's into position
|
Jun 17
|
Jun 17
|
1d
|
500
|
0%
|
|
15
|
Crane HMS shield house wall sections down and secure to frame
|
Jun 18
|
Jun 18
|
1d
|
500
|
0%
|
|
16
|
Disconnect and remove FPP Electronic racks
|
Jun 9
|
Jun 9
|
1d
|
500
|
0%
|
|
17
|
RADCON support required
|
Jun 9
|
Jun 9
|
1d
|
500
|
0%
|
|
18
|
Disconnect and remove HMS trigger electronics
|
Jun 9
|
Jun 9
|
1d
|
500
|
0%
|
|
19
|
Disconnect and crane out focal planes
|
Jun 17
|
Jun 17
|
1d
|
500
|
0%
|
|
20
|
RADCON support required
|
Jun 17
|
Jun 17
|
1d
|
500
|
0%
|
|
21
|
Remove small scintillator assembly in front of exit window
|
Jun 9
|
Jun 9
|
1d
|
500
|
0%
|
|
22
|
Position and connect installation fixtures 67502-00019
|
Jun 9
|
Jun 9
|
1d
|
500
|
0%
|
|
23
|
Disconnect and remove wire chambers
|
Jun 9
|
Jun 9
|
1d
|
500
|
0%
|
|
24
|
Place chambers in shipping crate and cover
|
Jun 9
|
Jun 9
|
1d
|
500
|
0%
|
|
25
|
RADCON support required
|
Jun 17
|
Jun 17
|
1d
|
500
|
0%
|
|
26
|
Set up and align installation fixtures for CH2 blocks
|
Jun 9
|
Jun 9
|
1d
|
500
|
0%
|
|
27
|
Unbolt and slide out all CH2 blocks then crane out storage
|
Jun 9
|
Jun 9
|
1d
|
500
|
0%
|
|
28
|
RADCON support required
|
Jun 17
|
Jun 17
|
1d
|
500
|
0%
|
|
29
|
Remove installation fixture
|
Jun 9
|
Jun 9
|
1d
|
500
|
0%
|
|
30
|
Unbolt and remove wire chamber support frame
|
Jun 9
|
Jun 9
|
1d
|
500
|
0%
|
|
31
|
Restore position for first hodoscope plane
|
Jun 9
|
Jun 9
|
1d
|
500
|
0%
|
|
32
|
Reinstall Cerenkov detector
|
Jun 17
|
Jun 17
|
1d
|
500
|
0%
|
|
33
|
Align Cerenkov detector and secure
|
Jun 9
|
Jun 9
|
1d
|
500
|
0%
|
|
34
|
Reinstall aerogell chamber
|
Jun 9
|
Jun 9
|
1d
|
500
|
0%
|
|
35
|
Install 2nd hodoscopes plane
|
Jun 9
|
Jun 9
|
1d
|
500
|
0%
|
|
36
|
HMS light bulbs
|
Jun 9
|
Jun 9
|
1d
|
500
|
0%
|
|
37
|
BIG CAL glass anneal
|
Aug 19
|
Oct 1
|
|
500
|
0%
|
|
38
|
Uncover and prepare lead glass detector stack
|
Jun 9
|
Jun 9
|
1d
|
500
|
0%
|
|
39
|
Crane and install and connect UV lights
|
Jun 9
|
Jun 9
|
1d
|
500
|
0%
|
|
40
|
Disconnect UV lights and crane of BIG CAL
|
Jun 9
|
Jun 9
|
1d
|
500
|
0%
|
|
41
|
Cover and seal lead glass stack
|
Jun 9
|
Jun 9
|
1d
|
500
|
0%
|
|
42
|
Cryo Target disassembly and removal
|
Jun 9
|
Jun 9
|
1d
|
500
|
0%
|
|
43
|
Polarized Target installation
|
Jun 9
|
Jun 9
|
1d
|
500
|
0%
|
|
44
|
G-0 Magnet move from Hall C to long term storage (52 tons)
|
Jun 9
|
Jun 9
|
|
500
|
0%
|
|
45
|
Move HMS to large angle to max floor space
|
Jun 9
|
Jun 9
|
1d
|
500
|
0%
|
|
46
|
Clear floor space, move beam line and RAD parts to a secure location
|
Jun 9
|
Jun 9
|
1d
|
500
|
0%
|
|
47
|
Move HKS magnets and FW close to the wall
|
Jun 9
|
Jun 9
|
1d
|
500
|
0%
|
|
48
|
Assure BIG CAL and cable train are save
|
Jun 9
|
Jun 9
|
1d
|
500
|
0%
|
|
49
|
Move G-0 magnet into position and secure
|
Jun 9
|
Jun 9
|
1d
|
500
|
0%
|
|
50
|
Remove upstream end cap and lay onto cribbing
|
Jun 9
|
Jun 9
|
1d
|
500
|
0%
|
|
51
|
RADCON support required
|
Jun 9
|
Jun 9
|
1d
|
500
|
0%
|
|
52
|
Unbolt lead, pack into containers and move lead storage Bld.
|
Jun 9
|
Jun 9
|
1d
|
500
|
0%
|
|
53
|
RADCON support required
|
Jun 9
|
Jun 9
|
1d
|
500
|
0%
|
|
54
|
Remove down stream gate valve and end cap
|
Jun 9
|
Jun 9
|
1d
|
500
|
0%
|
|
55
|
RADCON support required
|
Jun 9
|
Jun 9
|
1d
|
500
|
0%
|
|
56
|
Bolt support base onto gate valve and move storage container
|
Jun 9
|
Jun 9
|
1d
|
500
|
0%
|
|
57
|
RADCON support required
|
Jun 9
|
Jun 9
|
1d
|
500
|
0%
|
|
58
|
Bolt both end caps together, seal and move to lead storage Bld.
|
Jun 9
|
Jun 9
|
1d
|
500
|
0%
|
|
59
|
RADCON support required
|
Jun 9
|
Jun 9
|
1d
|
500
|
0%
|
|
60
|
Remove 22" lead pipe, pack into box and move to lead storage Bld.
|
Jun 9
|
Jun 9
|
1d
|
500
|
0%
|
|
61
|
RADCON support required
|
Jun 9
|
Jun 9
|
1d
|
500
|
0%
|
|
62
|
Secure Cryo can with special fixture
|
Jun 9
|
Jun 9
|
1d
|
500
|
0%
|
|
63
|
Install shipping frame onto magnet, torque bolts and seal gabs
|
Jun 9
|
Jun 9
|
1d
|
500
|
0%
|
|
64
|
Truck into Hall and lay out cribbing mats and rails for position 1
|
Jun 9
|
Jun 9
|
1d
|
500
|
0%
|
|
65
|
Move 2 hydraulic towers, pump, H beam and swivel in and setup
|
Jun 9
|
Jun 9
|
1d
|
500
|
0%
|
|
66
|
Lineup towers, connect magnet to swivel and takeout slack
|
Jun 9
|
Jun 9
|
1d
|
500
|
0%
|
|
67
|
Unbolt magnet from base, rotate and move to the Hall center
|
Jun 9
|
Jun 9
|
1d
|
500
|
0%
|
|
68
|
Set magnet on cribbing, disconnect and remove hydraulic towers.
|
Jun 9
|
Jun 9
|
1d
|
500
|
0%
|
|
69
|
Move cribbing mats and rails to position 2
|
Jun 9
|
Jun 9
|
1d
|
500
|
0%
|
|
70
|
Set up 2 pairs of hydraulic towers with H beams
|
Jun 9
|
Jun 9
|
1d
|
500
|
0%
|
|
71
|
Lift and rotate magnet 90 derg. then onto rollers and secure
|
Jun 9
|
Jun 9
|
1d
|
500
|
0%
|
|
72
|
Pull magnet up the truck ramp and into position for loading
|
Jun 9
|
Jun 9
|
1d
|
500
|
0%
|
|
73
|
Load magnet onto trailer, secure and move lead storage Bld.
|
Jun 9
|
Jun 9
|
1d
|
500
|
0%
|
|
74
|
RADCON support required
|
Jun 9
|
Jun 9
|
1d
|
500
|
0%
|
|
75
|
Unload magnet and roll into lead storage Bld.
|
Jun 9
|
Jun 9
|
1d
|
500
|
0%
|
|
76
|
Remove all Lockwood equipment from Hall C
|
Jun 9
|
Jun 9
|
1d
|
500
|
0%
|
|
77
|
Shrink-wrap G-0 magnet and setup N2 flow from CHL
|
Jun 9
|
Jun 9
|
1d
|
500
|
0%
|
|
78
|
Install and commission Secondary emission monitor
|
Jun 9
|
Jun 9
|
|
500
|
0%
|
|
79
|
Disconnect and remove up stream girder
|
Jun 9
|
Jun 9
|
1d
|
500
|
0%
|
|
80
|
RADCON support required
|
Jun 9
|
Jun 9
|
1d
|
500
|
0%
|
|
81
|
Mount SEM onto new girder and bolt into position
|
Jun 9
|
Jun 9
|
1d
|
500
|
0%
|
|
82
|
Connect girder beam line and cables
|
Jun 9
|
Jun 9
|
1d
|
500
|
0%
|
|
83
|
Align and secure girder
|
Jun 9
|
Jun 9
|
1d
|
500
|
0%
|
|
84
|
|
Jun 9
|
Jun 9
|
|
500
|
0%
|
|
85
|
SOS disassembly
|
Jun 9
|
Jun 9
|
|
500
|
0%
|
|
86
|
Remove SOS detectors
|
Jun 9
|
Jun 9
|
1d
|
500
|
0%
|
|
87
|
RADCON support required
|
Jun 9
|
Jun 9
|
1d
|
500
|
0%
|
|
88
|
Remove remaining SOS rail from in between HKS concrete pad
|
Jun 9
|
Jun 9
|
1d
|
500
|
0%
|
|
89
|
Place rail section to large angle and shim to level
|
Jun 9
|
Jun 9
|
1d
|
500
|
0%
|
|
90
|
Place all toe-clamps
|
Jun 9
|
Jun 9
|
1d
|
500
|
0%
|
|
91
|
Chim level and align Rail, then torque down toe-clamps
|
Jun 9
|
Jun 9
|
1d
|
500
|
0%
|
|
92
|
Move SOS to smaller angle
|
Jun 9
|
Jun 9
|
1d
|
500
|
0%
|
|
93
|
Remove hydraulic fluid
|
Jun 9
|
Jun 9
|
1d
|
500
|
0%
|
|
94
|
RADCON support required
|
Jun 9
|
Jun 9
|
1d
|
500
|
0%
|
|
95
|
Remove hydraulic tank and pump
|
Jun 9
|
Jun 9
|
1d
|
500
|
0%
|
|
96
|
RADCON support required
|
Jun 9
|
Jun 9
|
1d
|
500
|
0%
|
|
97
|
Disconnect and remove A/C unit
|
Jun 9
|
Jun 9
|
1d
|
500
|
0%
|
|
98
|
RADCON support required
|
Jun 9
|
Jun 9
|
1d
|
500
|
0%
|
|
99
|
Remove SOS doors
|
Jun 9
|
Jun 9
|
1d
|
500
|
0%
|
|
100
|
RADCON support required
|
Jun 9
|
Jun 9
|
1d
|
500
|
0%
|
|
101
|
HES / HKS preparation (concrete, magnet assembly etc)
|
Jun 9
|
Jun 9
|
|
500
|
0%
|
|
102
|
Assemble HES magnets base with hilman rollers and hydraulic
|
Jun 9
|
Jun 9
|
1d
|
500
|
0%
|
|
103
|
Place lower dipole half in position and bolt down
|
Jun 9
|
Jun 9
|
1d
|
500
|
0%
|
|
104
|
Move upper dipole half on top and torque down
|
Jun 9
|
Jun 9
|
1d
|
500
|
0%
|
|
105
|
Crane Q1 into postion next to dipole, align and torque down
|
Jun 9
|
Jun 9
|
1d
|
500
|
0%
|
|
106
|
Crane Q2 into postion next to dipole, align and torque down
|
Jun 9
|
Jun 9
|
1d
|
500
|
0%
|
|
107
|
Connect vacuum chambers and leak check
|
Jun 9
|
Jun 9
|
1d
|
500
|
0%
|
|
108
|
Cover SOS rail base with plastic, fill with concrete and level
|
Jun 9
|
Jun 9
|
1d
|
500
|
0%
|
|
109
|
Extent 9.5" concrete pade for new location of the HKS dipole
|
Jun 9
|
Jun 9
|
1d
|
500
|
0%
|
|
110
|
SANE beam line and low power dump installation
|
Jun 9
|
Jun 9
|
|
500
|
0%
|
|
111
|
Remove necessary railing and pivot extensions
|
Jun 9
|
Jun 9
|
1d
|
500
|
0%
|
|
112
|
Install and align Cerenkov detector platform
|
Jun 9
|
Jun 9
|
1d
|
500
|
0%
|
|
113
|
Set beam line support posts and reassemble beam line form pivot to dump
|
Jun 9
|
Jun 9
|
1d
|
500
|
0%
|
|
114
|
RADCON support required
|
Jun 9
|
Jun 9
|
1d
|
500
|
0%
|
|
115
|
Align and secure entire beam line
|
Jun 9
|
Jun 9
|
1d
|
500
|
0%
|
|
116
|
Crane in and bolt down support beam and post for lead shielding boxes
|
Jun 9
|
Jun 9
|
1d
|
500
|
0%
|
|
117
|
Weld brackets to pivot (for H beam and for boxes on SOS side acc to drwg.)
|
Jun 9
|
Jun 9
|
1d
|
500
|
0%
|
|
118
|
RADCON support required
|
Jun 9
|
Jun 9
|
1d
|
500
|
0%
|
|
119
|
Place and bolt down lead shield boxes on girder and on the SOS side
|
Jun 9
|
Jun 9
|
1d
|
500
|
0%
|
|
120
|
Align Cerenkov detector mirrors (on the floor)
|
Jun 9
|
Jun 9
|
1d
|
500
|
0%
|
|
121
|
Place Cerenkov detector on platform
|
Jun 9
|
Jun 9
|
1d
|
500
|
0%
|
|
122
|
Align Cerenkov detector and secure
|
Jun 9
|
Jun 9
|
1d
|
500
|
0%
|
|
123
|
Connect all cables and detector gas system
|
Jun 9
|
Jun 9
|
1d
|
500
|
0%
|
|
124
|
Mount lucite detectors onto BIG CAL
|
Jun 9
|
Jun 9
|
1d
|
500
|
0%
|
|
125
|
Install He-supply pipe for He bag (from gas Bld to beam dump)
|
Jun 9
|
Jun 9
|
1d
|
500
|
0%
|
|