0000 | 0100 | 0200 | 0300 | 0400 | 0500 | 0600 | 0700 | Total Time | |
---|---|---|---|---|---|---|---|---|---|
Acceptable Beam in Use | 50 | 50 | 40 | 50 | 30 | 0 | 0 | 0 | 3.66666666666667 |
Beam Available but Not in Use | 10 | 10 | 20 | 10 | 30 | 0 | 0 | 0 | 1.33333333333333 |
Beam Not Available or Unacceptable | 0 | 0 | 0 | 0 | 0 | 60 | 0 | 0 | 1 |
Accelerator Con- figuration Chage | 0 | 0 | 0 | 0 | 0 | 0 | 60 | 60 | 2 |
Experiment Ready | 50 | 50 | 40 | 50 | 30 | 60 | 0 | 0 | 4.66666666666667 |
Planned Config- uration Change | 10 | 10 | 5 | 10 | 30 | 0 | 60 | 60 | 3.08333333333333 |
Unplanned Experiment Down | 0 | 0 | 15 | 0 | 0 | 0 | 0 | 0 | 0.25 |
Hall not ready reasons | |||||||||
Target | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 |
HMS | 0 | 0 | 15 | 0 | 0 | 0 | 0 | 0 | 0.25 |
SOS | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 |
Data Acq | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 |
Other | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 |
Comments: 5:00 Cavity problem in the south linac 6:00 end of run
Data Entry by: bruell