Wednesday
33500 01/31/01 23:00 C. Howell vme scaler server
33496 01/31/01 16:13 hcf Moller motion restored
33491 01/31/01 11:34 tireman PH calibration done
33480 01/31/01 10:23 tireman NPOL HV restored .... back to work
33479 01/31/01 09:56 tireman NPOL HV off per Bill Vulcan
Tuesday
33437 01/30/01 12:09 tireman junk, junk.....the runs are junk
33434 01/30/01 11:45 tireman January pulse height calibration data for NPOL
Monday
33427 01/29/01 14:36 tireman HMS update -- Q3 manual control of value 8
33425 01/29/01 09:12 tireman DO NOT TURN NPOL HV OFF!!!!
33424 01/29/01 06:32 hcf DO Leave Moller Voltages ON
33423 01/29/01 04:59 garrow MOLLER VOLTAGES STILL ON
33422 01/29/01 02:24 garrow shift summary
33420 01/29/01 01:35 garrow access to reset target turbo pump
33417 01/29/01 00:02 smithg shift summary
Sunday
33416 01/28/01 23:40 hamlet Next shift tasks
33414 01/28/01 22:15 hamlet Beam current 43uA for run #38411
33412 01/28/01 22:09 tajima bcm and bpm
33411 01/28/01 22:01 Vardan target IOC rebooted once more
33410 01/28/01 21:57 hamlet Beam current now ~45uA
33408 01/28/01 20:55 hamlet Change disk data5-->data8
33407 01/28/01 19:54 Vardan target IOC rebooted.
33405 01/28/01 18:00 hamlet Shift summary
33401 01/28/01 15:48 hamlet Unstable and Intensity beam
33398 01/28/01 13:07 stevec Adjust target alarm point for ecCEV6711C
33397 01/28/01 13:02 hamlet 4He flow rump up to ~9g/s
33396 01/28/01 12:28 hamlet Change disk data4-->data5
33394 01/28/01 11:57 hamlet Run #38402 junk
33393 01/28/01 11:50 hamlet TSO reboot
33390 01/28/01 11:40 hamlet Q3 trip
33388 01/28/01 10:43 stevec Target turbo pump is running
33387 01/28/01 10:23 hcf moller target motion bad
33386 01/28/01 10:19 hamlet One more time Controlled access for moller
33385 01/28/01 09:46 stevec Scattering chamber vacuum deteriorating
33384 01/28/01 08:20 hamlet Controlled access for moller
33382 01/28/01 08:03 garrow shift summary
33381 01/28/01 07:22 s taylor moller problems
33379 01/28/01 04:21 garrow mcc lost beam due to power supply trip
33378 01/28/01 04:09 garrow run 38398 also at 55 microa amps
33377 01/28/01 04:07 garrow Steve Wood needs to contact MCC today
33374 01/28/01 03:16 garrow injector ioc crash
33373 01/28/01 01:49 garrow run 38397 @55 micro amps
33372 01/28/01 01:48 tajima bcm and bpm
Saturday
33369 01/27/01 23:49 Danagoulian Shift summary
33366 01/27/01 21:14 Danagoulian Moller run # 38339-38342
33365 01/27/01 20:33 Vardan target IOC rebooted.
33358 01/27/01 16:00 hamlet shift summary
33354 01/27/01 14:19 stevec Q3 back online
33353 01/27/01 13:44 stevec Q3 Trip
33351 01/27/01 12:06 hamlet Change disk data2-->data3
33348 01/27/01 11:06 hamlet Beam "off" for Injector test.
33347 01/27/01 11:01 hamlet EPICS for HMS magnets was in wrong units
33346 01/27/01 10:58 stevec EPICS printout modified
33344 01/27/01 10:29 hamlet No beam. RF trip
33339 01/27/01 07:47 garrow shift summary
33335 01/27/01 05:25 garrow LOST bpm/bcm screens
33334 01/27/01 05:20 garrow Q1 crash at 1:50
33332 01/27/01 03:00 garrow problem restoring target communication
Friday
33325 01/26/01 20:11 tireman detector problem alerts -- 7, 36, 59, 67
33316 01/26/01 13:42 Gueye Shift summary
33315 01/26/01 13:42 stevec beam back
33312 01/26/01 11:18 stevec Put in 4cm LD2 target for MCC tests
33309 01/26/01 09:29 stevec Beam off for about 15 minutes for MCC tests
33308 01/26/01 08:57 stevec Charybdis off
33304 01/26/01 07:59 garrow shift summary
33303 01/26/01 07:57 garrow reboot target ioc
33302 01/26/01 06:39 garrow roc 2 crash
33299 01/26/01 04:27 garrow MCC can deliver 70-72 micro amps
33298 01/26/01 04:23 garrow MCC having trouble getting 75 micor amps
33295 01/26/01 03:23 garrow changed He bottle and Argon
33294 01/26/01 03:22 garrow Q1 trip
33293 01/26/01 03:03 tajima 1/2 plate info corrected for #38343-38352
Thursday
33284 01/25/01 20:41 Gueye Beam back
33283 01/25/01 20:33 Gueye Beam off
33281 01/25/01 20:13 Gueye Beam back.
33280 01/25/01 19:56 Gueye Beam off
33279 01/25/01 19:34 Vardan Target Loop1 HeatLoad adjusted
33277 01/25/01 19:22 Vardan Target HL1 increased temporarily.
33276 01/25/01 19:13 Gueye Beam bouncing. HallA beam in study
33275 01/25/01 18:44 Gueye Change disk to data12
33273 01/25/01 17:43 s taylor Moller results
33271 01/25/01 17:23 Gueye Short update on the experiment
33266 01/25/01 15:45 smithg hms shower counters A&B hv trip
33262 01/25/01 07:58 garrow shift summary
33257 01/25/01 02:56 garrow bpm bcm screens
33255 01/25/01 01:26 garrow roc 2 crash
33252 01/25/01 00:03 Gueye Shift summary
Wednesday
33249 01/24/01 23:26 Gueye Change disk to data11
33247 01/24/01 23:17 Gueye ROC2 problem for run 38328
33245 01/24/01 21:57 Vardan Target IOC rebooted.
33244 01/24/01 21:53 Gueye Run 38326 junk
33242 01/24/01 21:31 Gueye Reboot all ROCS & target IOC
33240 01/24/01 21:05 Gueye ROC2 crashed
33235 01/24/01 17:10 Gueye Reboot Q3
33234 01/24/01 17:03 Gueye Q1 tripped & Q2 PC frozen
33233 01/24/01 16:54 Gueye Change disk
33229 01/24/01 15:56 ent ROC2 failed
33227 01/24/01 14:42 smithg ibcm1 in tgt guis & checklist
33226 01/24/01 14:37 smithg target ioc rebooted
33223 01/24/01 12:28 ent run 38315 junk
33218 01/24/01 09:48 ent charybdis on runs
33216 01/24/01 08:32 smithg reset target loop2 fan
33213 01/24/01 06:52 s taylor NPOL 7R, continued
33212 01/24/01 06:39 s taylor charybdis on running
33210 01/24/01 06:29 s taylor target loop 2 temperature oscillations
33205 01/24/01 02:24 s taylor NPOL 7R
33204 01/24/01 02:02 staylor bpm and bcm screens
33202 01/24/01 00:46 C.Yan right side of detector 7 lost signal
Tuesday
33190 01/23/01 16:31 Finn Normal running restored: the plan for the next two days
33188 01/23/01 15:44 ent beware change in run cycle!
33187 01/23/01 15:42 ent lambda/2 IN for 38294
33185 01/23/01 15:07 hcf moller controls up again
33184 01/23/01 12:19 hcf Moller solenoid is OK
33183 01/23/01 12:03 hcf Moller cooldown valves opened by IOC reset!
33182 01/23/01 11:58 hcf Moller quench?
33181 01/23/01 11:24 hcf Moller Q1 GPIB problems
33180 01/23/01 10:10 stevec 300.8 million events so far
33179 01/23/01 10:00 tireman NPOL HV change for PMT gain
33175 01/23/01 06:25 s taylor ESR recovery update
33173 01/23/01 02:39 s taylor hms magnet recovery
33172 01/23/01 02:29 Gueye Shift summary
Monday
33170 01/22/01 22:52 Gueye HMS work
33169 01/22/01 21:58 Gueye HMS quads He valves closed
33168 01/22/01 21:46 Gueye Update on ESR crash
33167 01/22/01 21:08 samuel cryotarget trip
33166 01/22/01 20:04 Zhu ESR crash
33165 01/22/01 19:55 maclachlan moller results
33161 01/22/01 19:17 maclachlan moller setup
33159 01/22/01 18:46 Gueye Moller measurement
33157 01/22/01 18:08 Gueye More (again) on ion chambers
33156 01/22/01 18:05 Gueye Update on ion chambers
33155 01/22/01 17:41 Gueye Dum ion chamber problem
33154 01/22/01 17:37 Gueye Switch Charybdis off
33152 01/22/01 16:18 gueye Beam back
33151 01/22/01 16:14 gueye Switch Charybdis polarity
33149 01/22/01 15:39 ent Current to 70 muA
33147 01/22/01 15:23 ent change disk --> 8
33146 01/22/01 15:22 ent 38283+38284 junk
33142 01/22/01 14:38 stevec Target IOC rebooted
33141 01/22/01 14:35 ent target/conf. change
33138 01/22/01 12:16 tajima bcm and bpm
33136 01/22/01 11:07 ent Q2 reset
33134 01/22/01 09:49 tireman HMS silent trip -- possible reason
33133 01/22/01 09:43 ent Run 38276 stopped: no ER
33132 01/22/01 09:42 ent 38277 no EPICS screen
33129 01/22/01 08:40 stevec Target IOC rebooted
33127 01/22/01 08:22 ent Run 38274 junk
33125 01/22/01 08:12 stevec Target temperature variations even without beam
33123 01/22/01 08:04 s taylor DAQ crash
33122 01/22/01 08:00 s taylor HMS shower counters off, cont.
33121 01/22/01 07:19 s taylor HMS shower counters off
33117 01/22/01 06:18 s taylor HMS Q3 trip
33113 01/22/01 03:44 s taylor bcm and bpm screens
Sunday
33106 01/21/01 18:28 tireman 4th plane vetos -- IT's good to go
33105 01/21/01 10:18 finn no beam since 3 am due to vaccuum leak in accelerator
33104 01/21/01 09:49 lgan day shift summary
33102 01/21/01 07:54 s taylor rebooted Q2 PC
33100 01/21/01 06:38 s taylor update from MCC
33097 01/21/01 04:50 s taylor bcm screen
33092 01/21/01 00:41 s taylor funny NPOL histograms
33089 01/21/01 00:01 s taylor LD2 target for runs 38252 and 38253
Saturday
33088 01/20/01 22:32 Hubt helium bottle change
33087 01/20/01 22:22 hubt Dipole problem fixed and field ajusted
33085 01/20/01 20:32 Bitao Hu HMS dipole problem
33081 01/20/01 16:57 garrow TSO and ROC5 died.
33078 01/20/01 15:53 lgan shift summary
33075 01/20/01 13:48 lgan HV trip
33070 01/20/01 11:45 Vardan Target IOC rebooted.
33067 01/20/01 10:40 lgan beam spot change and moller run
33064 01/20/01 09:54 tireman 4th plane veto isolation transformers installed
33062 01/20/01 08:43 s taylor shift summary, moller results
33055 01/20/01 05:57 s taylor bcm and bpm screens
33052 01/20/01 03:23 s taylor hms dipole trip
Friday
33044 01/19/01 23:09 mack The Plan
33039 01/19/01 19:47 garrow bpm/bcm screens
33037 01/19/01 19:11 garrow Q3 trip
33035 01/19/01 18:11 mack maxed out at source with 69 microA
33033 01/19/01 17:36 garrow charybdis on electron polarity
33032 01/19/01 17:18 garrow Entry for Q1 reset
33024 01/19/01 10:52 Vardan Target IOC rebooted.
33020 01/19/01 06:19 hamlet No beam, MCC need experts for to fix RF problem!
33018 01/19/01 05:25 hamlet No Beam, RF trip & QE measurement
33016 01/19/01 04:19 yuan BPM and BCM screens.
33013 01/19/01 02:06 hamlet Change disk
Thursday
33008 01/18/01 23:23 mack dipole current readback missing
33004 01/18/01 21:39 mack No long distance phone capability?!!
33003 01/18/01 21:07 mack double peak in mtime id=7
33001 01/18/01 20:49 mack rebooted Q3
33000 01/18/01 20:05 mack CLAS torus tripped on low Helium
32998 01/18/01 19:13 mack charybdis is on, proton polarity
32997 01/18/01 18:59 garrow bpm/bcm screens
32987 01/18/01 10:49 saw Q2 reboot
32986 01/18/01 10:49 Vardan Target flactuations.
32984 01/18/01 09:47 s taylor temporary procedure for recovering Q3 after a trip
32982 01/18/01 08:58 xfzhu HMS Q1 trip
32980 01/18/01 08:00 hamlet Shift 18 Jan'01; 00:00-08:00
32978 01/18/01 07:39 xfzhu HMS Q3 magnet trip
32977 01/18/01 07:22 xfzhu Disk change
32975 01/18/01 07:03 xfzhu Target IOC reboot
32973 01/18/01 06:26 xfzhu HMS Q3 tripped
32970 01/18/01 04:11 xfzhu BPM & BCM screen
32968 01/18/01 03:07 hamlet Turning Charybdis Off
32966 01/18/01 01:43 hamlet Pol Veto pos ID=68
32964 01/18/01 01:15 hamlet Changed Charybdis polarity for "proton"
32963 01/18/01 01:03 hamlet Disk change
32961 01/18/01 00:02 hamlet Current and Charybdis for run #38179
Wednesday
32959 01/17/01 23:09 mack turning Charybdis on
32957 01/17/01 21:48 mack dipole trip at 21:28
32956 01/17/01 21:44 mack BCM and BPM plots
32955 01/17/01 20:57 mack half-wit plate is OUT
32949 01/17/01 16:49 s taylor results of moller runs
32938 01/17/01 14:49 finn CHCHPCOLOR printer , has been fine tuned
32937 01/17/01 14:44 finn Hall C dipole trip run 38162
32933 01/17/01 12:18 finn magnets cooled down ready for beam
32932 01/17/01 12:10 hcf cryo systems cold an d full
32931 01/17/01 11:31 tireman detector 11 R -- my fault this time
32930 01/17/01 11:12 Finn magnets are being coolled dowm
32929 01/17/01 09:59 Vardan Target IOC rebooted.
32928 01/17/01 09:48 smithg target data logger fix
32927 01/17/01 08:03 hamlet Shift 17 Jan'01; 00:00-08:00
32925 01/17/01 06:13 hamlet Don't find any problem in Hall
32924 01/17/01 05:42 hamlet Ask MCC for controlled access
32923 01/17/01 02:28 hamlet Hall C taking only ~3.9g/s He from CHL
32922 01/17/01 00:51 hamlet Beam off and Set "0" current for Q1-Q3
32921 01/17/01 00:38 hamlet He low level problem for HMS
Tuesday
32919 01/16/01 23:54 mack lost hms dipole due to low He level
32917 01/16/01 23:08 mack more than the usual number of missing helicity gate triggers
32916 01/16/01 23:01 mack happy with the beam uptime
32915 01/16/01 22:57 mack Q3 crash
32911 01/16/01 20:06 mack HMS and NPOL HV screens
32908 01/16/01 18:19 mack bcm and bpm screens
32906 01/16/01 18:15 MacLachlan Funny target pressure behavior
32902 01/16/01 16:12 mack CW beam coming back
32900 01/16/01 14:39 tireman detector 11 R cable change
32897 01/16/01 09:49 hcf Moller Quads ON
32896 01/16/01 09:42 hcf MOller Cryo
32895 01/16/01 09:33 samuel cryotarget ready
32894 01/16/01 08:04 hamlet Shift 16 Jan'01; 00:00-08:00
32892 01/16/01 07:14 hamlet Hall TV camera rotation problem
32891 01/16/01 06:30 hamlet HV trip on HCAL A & B
32890 01/16/01 05:36 hamlet Started cool down target
32889 01/16/01 04:29 hamlet All HMS magnets ready !
32888 01/16/01 03:56 hamlet Dipole and Q1 ready !
Monday
32886 01/15/01 22:02 mack cryo update
32885 01/15/01 21:02 mack switched to new Ethane bottle
32884 01/15/01 19:09 mack Run Plan and contacts for Hall C cooldown
32883 01/15/01 19:01 mack cryo update
32882 01/15/01 18:54 stevec More Timing stuff
32881 01/15/01 18:31 stevec Neutron timing (picture)
32880 01/15/01 18:25 stevec Timing Calibrations
32879 01/15/01 16:25 mack slowly cooling down
32877 01/15/01 07:58 hamlet Shift 15 Jan'01;00:00-08:00
32875 01/15/01 07:28 hamlet Started Hall A & C target warmup
32874 01/15/01 07:05 Gueye Change Helium bottle
32873 01/15/01 07:04 hamlet Helum level "0" for Dipole
32872 01/15/01 06:14 hamlet Moller set to "0" current
32871 01/15/01 05:25 Gueye ESR & CEBAF went down
32870 01/15/01 05:20 hamlet Target and Dipole problem
Sunday
32868 01/14/01 23:45 khandaker Evening Shift Summary
32867 01/14/01 16:46 tireman Hall C access for NPOL checks -- nothing new
32865 01/14/01 15:51 lgan Shift summary
32864 01/14/01 15:12 lgan HMS dipole nitrogen level
32863 01/14/01 13:14 lgan Q2 rebooted
32862 01/14/01 13:13 lgan HMS dipole nitrogen level
32861 01/14/01 12:35 Farkhondeh Beam stopped at 12:05 for Hall A and B tune up
32860 01/14/01 11:41 lgan switch disk
32857 01/14/01 10:07 aram About 38140 run
32855 01/14/01 09:40 s taylor target IOC reboot
32854 01/14/01 08:24 Danagoulian Shift summary
32846 01/14/01 04:42 Danagoulian Dipole N2 level
32843 01/14/01 03:05 Danagoulian ROC 2 crush
32841 01/14/01 02:04 Danagoulian BPM and BCM windows
32838 01/14/01 00:07 M Jones Shift summary
Saturday
32831 01/13/01 20:09 M Jones beam current last 8 hours
32825 01/13/01 15:57 J. Watson Shift Summary: day shift 1/13/01
32823 01/13/01 14:22 tireman more high voltage text
32821 01/13/01 14:20 Farkhondeh Charybdis on, Proton Polarity
32820 01/13/01 14:18 tireman more high voltages and currents
32819 01/13/01 12:45 plaster Run #38123 - Charybdis ON
32817 01/13/01 12:09 madey Energy per pass
32816 01/13/01 12:04 plaster HV NPOL Veto Secondary
32815 01/13/01 12:04 plaster HV NPOL Veto Secondary
32814 01/13/01 12:02 plaster HV NPOL Veto Secondary
32813 01/13/01 12:01 plaster HV NPOL Rear Secondary
32812 01/13/01 12:00 plaster HV NPOL Rear Seconday
32811 01/13/01 11:58 plaster HV NPOL Front Secondary
32810 01/13/01 11:54 plaster HV Front Secondary
32809 01/13/01 11:50 plaster Beam currents as of start 38122
32804 01/13/01 08:04 Danagoulian Shift summary
32799 01/13/01 04:40 Vardan target IOC rebooted.
32797 01/13/01 03:56 Danagoulian vmec15 reboot
32796 01/13/01 03:18 Danagoulian Moller solenoid
32792 01/13/01 00:43 ysato VMEC2 rebooted
32791 01/13/01 00:41 S. Danagouli He bottle change
32788 01/13/01 00:01 J. Watson Summary--Swing Shift 1/12/01
Friday
32787 01/12/01 23:30 Abdellah HMS d.c. trip
32781 01/12/01 19:42 Farkhondeh No run 38104
32773 01/12/01 14:02 Farkhondeh LH2 run began after Restarted Coda
32771 01/12/01 12:58 tireman Access to NPOL detector checks
32770 01/12/01 12:07 tireman Q2 and Q3 PC reboot
32769 01/12/01 11:32 s taylor hall A current calib.
32768 01/12/01 11:16 s taylor Moller runs
32759 01/12/01 08:00 tajima shift summary
32757 01/12/01 06:20 tajima BCM and BPM screens
32753 01/12/01 02:41 Vardan target IOC reboted
32752 01/12/01 02:40 tajima Run#38078-38081
32748 01/12/01 00:07 J. Watson Swing Shift Summary 01/11/01
Thursday
32742 01/11/01 20:34 J. Watson BPMs screwy.
32737 01/11/01 16:07 smithg hv snapshots
32735 01/11/01 15:36 cdaq starting running again
32733 01/11/01 14:05 hcf HMS Dipole ready
32732 01/11/01 13:48 hcf HMS Dipole Trip
32731 01/11/01 13:17 hcf Veto59LAB draws no current?
32730 01/11/01 12:28 hcf Added helicity signal buffered outputs for G0
32729 01/11/01 12:06 hcf Opened HMS Shutter
32728 01/11/01 11:57 hcf Moller collimator scan plots from last week
32727 01/11/01 11:21 smithg oops... hms window shield still there
32726 01/11/01 11:07 hcf MCC- couple of hours more
32725 01/11/01 10:55 hcf cdaqs1 and DAQ problems
32724 01/11/01 10:51 hcf Down for MCC
32723 01/11/01 10:50 hcf MOller Q2 -- OK
32722 01/11/01 09:21 smithg target boot file modified
32718 01/11/01 08:01 tajima shift summary
32717 01/11/01 07:54 Vardan 15cm LD2 target under 60uA.
32716 01/11/01 07:35 s taylor MOSFET fault for moller q2
32714 01/11/01 06:04 tajima MOSFET fault
32711 01/11/01 04:12 tajima BCM and BPM screens
32709 01/11/01 00:30 tajima beam off
32707 01/11/01 00:03 J. Watson Shift Summary
Wednesday
32705 01/10/01 22:22 tireman misc. Beam screens
32704 01/10/01 21:08 J. Watson Q1 crash
32700 01/10/01 17:06 johna HMS electronic dead time test.
32696 01/10/01 15:45 Elaasar Shift check list scan
32695 01/10/01 15:30 Elaasar Veto counter Det 69
32693 01/10/01 14:55 maclachlan cryo target excursion
32691 01/10/01 12:59 tireman mysterious NPOL afterburner trip
32689 01/10/01 12:10 hcf Moller Runs SUmmary
32687 01/10/01 11:47 hcf Moller HV change
32685 01/10/01 11:45 hcf Moller Collimator miniscan
32681 01/10/01 10:42 smithg target temp. fluctuations with beam on/off
32680 01/10/01 10:16 hcf Moller run beam currents
32675 01/10/01 08:59 maclachlan moller parameters
32673 01/10/01 08:29 hickson empty cylinders
32671 01/10/01 08:04 tajima shift summary
32669 01/10/01 06:53 tajima disk changed to data11
32667 01/10/01 06:18 tajima BPM and BCM screens
32665 01/10/01 03:51 tajima #38049 is junk
32664 01/10/01 03:50 tajima beam back
Tuesday
32661 01/09/01 23:08 tireman accelerator update
32660 01/09/01 17:50 John Watson Beam off
32659 01/09/01 17:17 plaster Beam Off for 4 hours
32655 01/09/01 16:04 Elaasar Shift run summary
32654 01/09/01 15:24 plaster HV NPOL Veto Secondary con't
32653 01/09/01 15:24 plaster HV NPOL Veto Secondary con't
32652 01/09/01 15:22 plaster HV NPOL Veto Secondary
32651 01/09/01 15:18 maclachlan Secondary High Voltages
32650 01/09/01 15:16 maclachlan Secondary High Voltages
32649 01/09/01 15:14 voltages Secondary High Voltages
32648 01/09/01 15:12 maclachlan Secondary High Voltages for NPOL
32647 01/09/01 15:04 maclachlan Secondary High Voltages for NPOL
32646 01/09/01 15:02 maclach Secondary High Voltages for NPOL
32645 01/09/01 14:59 Elaasar HMS and GEN HV
32643 01/09/01 13:12 Elaasar ROC2 Crashed
32640 01/09/01 11:27 maclachlan Charybdis misbehavior
32636 01/09/01 09:40 gueye Beam profile at target
32634 01/09/01 08:03 hamlet Shift 09 Jan'01; 00:00-08:00
32633 01/09/01 07:59 hamlet Big fluctuation of He in ESR and Hall A
32631 01/09/01 07:21 gueye HMS magnets tripped
32629 01/09/01 05:23 hamlet HMS Dipole field unstable?
32627 01/09/01 04:35 gueye HMS dipole tripped
32626 01/09/01 04:31 gueye Q1 tripped
32624 01/09/01 03:29 gueye All magnets up: ask for beam
32623 01/09/01 03:12 gueye Q2 & Q3 problems
32622 01/09/01 02:54 gueye All HMS magnets tripped
32621 01/09/01 02:53 hamlet BPM screen back
32620 01/09/01 01:09 hamlet Controlled access for MCC
32619 01/09/01 00:44 hamlet No BPM info. for run #38037
32617 01/09/01 00:11 hamlet Q3 trip
32615 01/09/01 00:01 hamlet For run #38036 Charybdis off !
Monday
32614 01/08/01 23:57 hamlet Beam curren 40 uA for run #39036
32610 01/08/01 21:12 J. Watson Dipole crash + Charybdis --> proton polarity
32609 01/08/01 21:04 Kelly negative time correlation
32608 01/08/01 19:42 J. Watson 75 uA
32606 01/08/01 19:08 J. Watson Charybdis on
32601 01/08/01 16:42 elaasar shift summary
32600 01/08/01 16:27 s taylor moller run results
32599 01/08/01 16:21 plaster shift checklist
32596 01/08/01 14:36 tireman Detector update after Hall Access
32595 01/08/01 14:03 Elaasar Trigger gate
32594 01/08/01 13:58 Lassiter hms q2 screens
32589 01/08/01 11:37 lassiter hms q2 screen
32584 01/08/01 08:00 hamlet Shift 08 Jan'01; 00:00-08:00
32580 01/08/01 06:25 hamlet Beam off for MCC Q measurement
32578 01/08/01 05:17 hamlet HCAL HV trip
32575 01/08/01 02:26 hamlet Change disk
32572 01/08/01 00:41 hamlet Beam current for run #38010
Sunday
32570 01/07/01 23:57 hamlet BPM & BCM screen
32566 01/07/01 20:34 tireman DATA file size/number of events changed per run
32565 01/07/01 20:23 mitchell bcms
32564 01/07/01 19:32 tireman Detector 11 R -- the plot thickens
32563 01/07/01 19:20 plaster 38006
32557 01/07/01 16:13 Elaasar Shift summary
32555 01/07/01 15:53 plaster HMS & POL HV
32553 01/07/01 15:18 elaasar HV NPOL Veto secondary 69-70
32552 01/07/01 15:17 Elaasar HV NPOL Veto Secondary 57-68
32551 01/07/01 15:13 Elaasar HV NPOL Veto secondary 45-56
32550 01/07/01 15:08 Elaasar HV NPOL Rear secondar 33-44
32549 01/07/01 15:06 Howell COSMIC runs
32548 01/07/01 15:05 Elaasar HV NPOL Rear Secondar 21-32
0 01/07/01 15:02 no_name no_key
32546 01/07/01 14:58 Elaasar NPOL Front secondary HV 1-12
32545 01/07/01 14:44 Howell Trigger timing - bad runs
32539 01/07/01 12:30 Howell Trigger circuit timing change
32535 01/07/01 11:47 s taylor moller run results
32527 01/07/01 08:44 Elaasar Errors
32525 01/07/01 08:02 hamlet Shift 08 Jan'00; 00:00-08:00
32523 01/07/01 07:23 hamlet BPM & BCM screen
32521 01/07/01 06:13 hamlet TSO reboot & no run 37983
32518 01/07/01 03:19 hamlet Q2 problem
32517 01/07/01 03:02 hamlet Q2 trip
32514 01/07/01 01:44 hamlet Beam off for Q measurement
32511 01/07/01 00:30 hamlet Q2 back !
Saturday
32509 01/06/01 23:39 Vardan HMS LG HVs went off.
32508 01/06/01 23:27 mitchell Q2 computer problem
32505 01/06/01 21:29 Howell Coincidence timing change
32499 01/06/01 17:43 Vardan Target IOC rebooted.
32497 01/06/01 17:08 tireman secondary power supplies @ 75 uA
32496 01/06/01 17:07 tireman secondary power supplies @ 75 uA
32494 01/06/01 17:03 tireman secondary power supply @ 75 uA
32493 01/06/01 17:01 tireman secondary power supplies @ 75 uA
32492 01/06/01 16:57 tireman Update on detector 36B
32491 01/06/01 16:42 mitchell position feedback
32489 01/06/01 16:22 Elaasar NPOL rear secondary
32488 01/06/01 16:21 Elaasar Rear secondary NPOL
32487 01/06/01 16:16 Elaasar NPOL rear secondary
32486 01/06/01 16:14 Elaasar NPOL front secondary
32485 01/06/01 16:10 elaasar I=40 uA
32482 01/06/01 14:58 tireman hall entry for detector work
32480 01/06/01 14:30 Hamlet beam current
32479 01/06/01 13:21 maclachlan NPOL High Voltages
32478 01/06/01 13:20 maclachlan NPOL High Voltages
32476 01/06/01 10:09 s taylor beam current
32471 01/06/01 08:25 maclachlan Q3 reboot
32470 01/06/01 08:05 hamlet Shift 06 Jan'01, 00:00-08:00
32464 01/06/01 06:14 hamlet Beam off, RF problem
32463 01/06/01 06:12 hamlet No Epics quant. for HMS magnets
32459 01/06/01 04:56 hamlet Beam off for MCC
32457 01/06/01 04:21 hamlet Q2 trip
32456 01/06/01 04:03 hamlet Change Disk
32454 01/06/01 03:47 hamlet BPM & BCM screen
32448 01/06/01 02:08 tireman comments on running NPOL @ 50uA
32444 01/06/01 01:03 hamlet No signal POL VETO ID=70
32442 01/06/01 00:24 tireman Note on secondary power supply currents
32441 01/06/01 00:23 tireman secondary power supply currents
32440 01/06/01 00:21 tireman secondary power supply currents
32439 01/06/01 00:19 tireman secondary power supply currents
32438 01/06/01 00:17 tireman secondary power supply currents
Friday
32435 01/05/01 23:51 mitchell/fen moller production runs
32432 01/05/01 23:29 Vardan target changed to 4cm LD2
32431 01/05/01 23:24 hcf Moller conditions at tune.
32429 01/05/01 23:19 hcf Moller Collimator Scan notes
32424 01/05/01 21:06 hcf harp scans prior to Moller running
32422 01/05/01 18:53 tireman Data is bad...Q3 at wrong current
32419 01/05/01 17:38 tireman HV GUI is updated and working
32415 01/05/01 15:02 s taylor moller magnet on
32414 01/05/01 14:30 Howell pulse transformers
32413 01/05/01 14:20 Howell 4th veto plane
32411 01/05/01 12:50 tajima analyzer is ready
32410 01/05/01 12:39 smithg npol hv heartbeat
32408 01/05/01 06:00 khandaker Owl Shift Summary
32407 01/05/01 04:16 tireman Unable to add detectors 63-70 to HV GUI
32406 01/05/01 04:14 tireman Primary and secondary HV restored to 1 - 62 detectors
32405 01/05/01 03:29 Howell 4th veto plane
32404 01/05/01 03:25 tireman comments about NPOL
32403 01/05/01 03:01 tireman 4th plane vetos set up and ready to go
32400 01/05/01 00:33 saw Longer runs
Thursday
32395 01/04/01 20:58 Howell 3rd veto plane
32386 01/04/01 17:43 beaufait gen cables and target camera
32384 01/04/01 17:11 tireman HV is on to Vetos 63 - 70
32383 01/04/01 16:10 s taylor hms magnet settings for 3.395 GeV
32382 01/04/01 16:02 smithg target cold & ready
32376 01/04/01 14:36 hcf VESDA trip of clean power.
32375 01/04/01 14:33 hcf Moller Cooldown/checkout
32373 01/04/01 13:22 tireman GEN GUI disabled
32372 01/04/01 10:23 smithg be windows
32371 01/04/01 10:13 smithg tgt cooldown
Wednesday
32367 01/03/01 22:57 C. Howell Det. Hut electronics for 4th Veto plane
32366 01/03/01 18:15 tireman NPOL primary HV powered up and replacement of detectors
Tuesday
32356 01/02/01 11:40 beaufait gen 16 channel add on