0000 | 0100 | 0200 | 0300 | 0400 | 0500 | 0600 | 0700 | Total Time | |
---|---|---|---|---|---|---|---|---|---|
Acceptable Beam in Use | 0 | 0 | 36 | 45 | 1 | 47 | 1 | 53 | 5.02 |
Beam Available but Not in Use | 0 | 0 | 0 | 9 | 0 | 13 | 0 | 7 | 0.48 |
Beam Not Available or Unacceptable | 1 | 1 | 24 | 6 | 0 | 0 | 0 | 0 | 2.50 |
Accelerator Con- figuration Chage | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0.00 |
Experiment Ready | 1 | 1 | 1 | 51 | 1 | 47 | 1 | 53 | 7.52 |
Planned Config- uration Change | 0 | 0 | 0 | 9 | 0 | 13 | 0 | 7 | 0.48 |
Unplanned Experiment Down | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0.00 |
Hall not ready reasons | |||||||||
Target | 0 | 0 | 0 | 9 | 0 | 0 | 0 | 7 | 0.27 |
HMS | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0.00 |
Npol | 0 | 0 | 0 | 0 | 0 | 13 | 0 | 0 | 0.22 |
Data Acq | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0.00 |
Other | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0.00 |
Comments: Beam off at start of shift problems at injector. 2:24 Start data taking. 3:27 Finished 12M for +237 LD2 move to dummy since limited to 50uA 5:35 Finished +237 15cm dummy. start -237 15cm dummy. 7:45 Finished -237 15cm dummy. Start LH2. 7:53 Start LH2 -237
Data Entry by: M Jones