  • 157411 05/31/08 23:56 jensen Swing Shift Summary
  • 157410 05/31/08 23:40 jensen bcm/bpm
  • 157409 05/31/08 23:36 cdaq Run 70656: GEp-III high Q2, 94uA, ps1=2000 ps2=2000 ps3=99999 ps4=1, ps5=1, ps6=99999, {ps7=1;FPP=3.0V} BigCal_thr=410mV raster 3x3
  • 157408 05/31/08 23:35 cdaq End of Run 70655:
  • 157407 05/31/08 22:22 cdaq Run 70655: GEp-III high Q2, 94uA, ps1=2000 ps2=2000 ps3=99999 ps4=1, ps5=1, ps6=99999, {ps7=1;FPP=3.0V} BigCal_thr=410mV raster 3x3
  • 157406 05/31/08 22:21 cdaq End of Run 70654:
  • 157405 05/31/08 21:11 cdaq Run 70654: GEp-III high Q2, 94uA, ps1=2000 ps2=2000 ps3=99999 ps4=1, ps5=1, ps6=99999, {ps7=1;FPP=3.0V} BigCal_thr=410mV raster 3x3
  • 157404 05/31/08 21:09 cdaq End of Run 70653:
  • 157403 05/31/08 20:36 jensen Beam current
  • 157402 05/31/08 20:24 jensen bcm
  • 157401 05/31/08 19:59 jensen beam current
  • 157400 05/31/08 19:35 cdaq Run 70653: GEp-III high Q2, 94uA, ps1=2000 ps2=2000 ps3=99999 ps4=1, ps5=1, ps6=99999, {ps7=1;FPP=3.0V} BigCal_thr=410mV raster 3x3
  • 157399 05/31/08 19:34 cdaq End of Run 70652:
  • 157398 05/31/08 18:09 jensen Lowered current
  • 157397 05/31/08 18:03 cdaq Run 70652: GEp-III high Q2, 94uA, ps1=2000 ps2=2000 ps3=99999 ps4=1, ps5=1, ps6=99999, {ps7=1;FPP=3.0V} BigCal_thr=410mV raster 3x3
  • 157396 05/31/08 18:02 cdaq End of Run 70651:
  • 157395 05/31/08 17:57 jensen BCM screen
  • 157394 05/31/08 17:14 smithg Target: screen snapshot
  • 157393 05/31/08 16:46 cdaq Run 70651: GEp-III high Q2, 94uA, ps1=2000 ps2=2000 ps3=99999 ps4=1, ps5=1, ps6=99999, {ps7=1;FPP=3.0V} BigCal_thr=410mV raster 3x3
  • 157392 05/31/08 16:44 cdaq End of Run 70650:
  • 157391 05/31/08 16:01 cdaq Beam Time Accounting
  • 157390 05/31/08 16:00 bogdanw shift summary
  • 157389 05/31/08 15:33 cdaq Run 70650: GEp-III high Q2, 94uA, ps1=2000 ps2=2000 ps3=99999 ps4=1, ps5=1, ps6=99999, {ps7=1;FPP=3.0V} BigCal_thr=410mV raster 3x3
  • 157388 05/31/08 15:32 cdaq End of Run 70649:
  • 157387 05/31/08 14:21 cdaq Run 70649: GEp-III high Q2, 94uA, ps1=2000 ps2=2000 ps3=99999 ps4=1, ps5=1, ps6=99999, {ps7=1;FPP=3.0V} BigCal_thr=410mV raster 3x3
  • 157386 05/31/08 14:20 cdaq End of Run 70648:
  • 157385 05/31/08 13:08 cdaq Run 70648: GEp-III high Q2, 94uA, ps1=2000 ps2=2000 ps3=99999 ps4=1, ps5=1, ps6=99999, {ps7=1;FPP=3.0V} BigCal_thr=410mV raster 3x3
  • 157384 05/31/08 13:07 cdaq End of Run 70647:
  • 157383 05/31/08 12:00 cdaq Run 70647: GEp-III high Q2, 94uA, ps1=2000 ps2=2000 ps3=99999 ps4=1, ps5=1, ps6=99999, {ps7=1;FPP=3.0V} BigCal_thr=410mV raster 3x3
  • 157382 05/31/08 11:58 cdaq End of Run 70646:
  • 157381 05/31/08 10:55 Target Screen snapshot
  • 157380 05/31/08 10:43 cdaq Run 70646: GEp-III high Q2, 94uA, ps1=2000 ps2=2000 ps3=99999 ps4=1, ps5=1, ps6=99999, {ps7=1;FPP=3.0V} BigCal_thr=410mV raster 3x3
  • 157379 05/31/08 10:42 cdaq End of Run 70645:
  • 157378 05/31/08 09:25 cdaq Run 70645: GEp-III high Q2, 94uA, ps1=2000 ps2=2000 ps3=99999 ps4=1, ps5=1, ps6=99999, {ps7=1;FPP=3.0V} BigCal_thr=410mV raster 3x3
  • 157377 05/31/08 09:23 cdaq End of Run 70644:
  • 157376 05/31/08 08:44 cdaq Run 70644: GEp-III high Q2, 94uA, ps1=2000 ps2=2000 ps3=99999 ps4=1, ps5=1, ps6=99999, {ps7=1;FPP=3.0V} BigCal_thr=410mV raster 3x3
  • 157375 05/31/08 08:43 cdaq End of Run 70643:
  • 157374 05/31/08 08:03 cdaq Beam Time Accounting
  • 157373 05/31/08 08:03 reinhold owl shift summary
  • 157372 05/31/08 07:31 cdaq Run 70643: GEp-III high Q2, 94uA, ps1=2000 ps2=2000 ps3=99999 ps4=1, ps5=1, ps6=99999, {ps7=1;FPP=3.0V} BigCal_thr=410mV raster 3x3
  • 157371 05/31/08 07:24 reinhold no beam last 40 min; MCC tries to resume delivery
  • 157370 05/31/08 07:19 cdaq End of Run 70642:
  • 157369 05/31/08 06:30 wpierce HV under voltage
  • 157368 05/31/08 05:40 cdaq Run 70642: GEp-III high Q2, 94uA, ps1=2000 ps2=2000 ps3=99999 ps4=1, ps5=1, ps6=99999, {ps7=1;FPP=3.0V} BigCal_thr=410mV raster 3x3
  • 157367 05/31/08 05:39 cdaq End of Run 70641:
  • 157366 05/31/08 05:28 narayan Target Screenshot, alarm limit
  • 157365 05/31/08 04:34 cdaq Run 70641: GEp-III high Q2, 94uA, ps1=2000 ps2=2000 ps3=99999 ps4=1, ps5=1, ps6=99999, {ps7=1;FPP=3.0V} BigCal_thr=410mV raster 3x3
  • 157364 05/31/08 04:33 cdaq End of Run 70640:
  • 157363 05/31/08 04:27 wpierce bcm/bpm screenshots
  • 157362 05/31/08 03:24 cdaq Run 70640: GEp-III high Q2, 94uA, ps1=2000 ps2=2000 ps3=99999 ps4=1, ps5=1, ps6=99999, {ps7=1;FPP=3.0V} BigCal_thr=410mV raster 3x3
  • 157361 05/31/08 03:23 cdaq End of Run 70639:
  • 157360 05/31/08 03:15 reinhold bcm screen (~1 hour of data taking @ 80uA)
  • 157359 05/31/08 02:15 cdaq Run 70639: GEp-III high Q2, 94uA, ps1=2000 ps2=2000 ps3=99999 ps4=1, ps5=1, ps6=99999, {ps7=1;FPP=3.0V} BigCal_thr=410mV raster 3x3
  • 157358 05/31/08 02:11 reinhold first beam in a while
  • 157357 05/31/08 01:29 reinhold no beam for last ~55 min (bcm screen)
  • 157356 05/31/08 01:15 cdaq End of Run 70638:
  • 157355 05/31/08 00:24 narayan Target Routine Screenshot
  • 157354 05/31/08 00:20 reinhold AC in G0 cage seems to be working
  • 157353 05/31/08 00:14 cdaq Run 70638: GEp-III high Q2, 94uA, ps1=2000 ps2=2000 ps3=99999 ps4=1, ps5=1, ps6=99999, {ps7=1;FPP=3.0V} BigCal_thr=410mV raster 3x3
  • 157352 05/31/08 00:13 cdaq End of Run 70637:
  • 157351 05/31/08 00:05 cdaq Beam Time Accounting
  • Friday

  • 157350 05/30/08 23:58 jensen Swing Shift Summary
  • 157349 05/30/08 23:24 jensen Unsteady beam
  • 157348 05/30/08 23:21 cdaq Run 70637: GEp-III high Q2, 94uA, ps1=2000 ps2=2000 ps3=99999 ps4=1, ps5=1, ps6=99999, {ps7=1;FPP=3.0V} BigCal_thr=410mV raster 3x3
  • 157347 05/30/08 23:19 cdaq End of Run 70636:
  • 157346 05/30/08 22:58 jensen bpm/bcm
  • 157345 05/30/08 22:05 cdaq Run 70636: GEp-III high Q2, 94uA, ps1=2000 ps2=2000 ps3=99999 ps4=1, ps5=1, ps6=99999, {ps7=1;FPP=3.0V} BigCal_thr=410mV raster 3x3
  • 157344 05/30/08 22:03 cdaq End of Run 70635:
  • 157343 05/30/08 21:03 cdaq Run 70635: GEp-III high Q2, 94uA, ps1=2000 ps2=2000 ps3=99999 ps4=1, ps5=1, ps6=99999, {ps7=1;FPP=3.0V} BigCal_thr=410mV raster 3x3
  • 157342 05/30/08 21:00 jensen EB1
  • 157341 05/30/08 20:59 cdaq Run 70634: GEp-III high Q2, 94uA, ps1=2000 ps2=2000 ps3=99999 ps4=1, ps5=1, ps6=99999, {ps7=1;FPP=3.0V} BigCal_thr=410mV raster 3x3
  • 157340 05/30/08 20:01 jensen roc13 crash
  • 157339 05/30/08 20:01 cdaq Run 70633: GEp-III high Q2, 94uA, ps1=2000 ps2=2000 ps3=99999 ps4=1, ps5=1, ps6=99999, {ps7=1;FPP=3.0V} BigCal_thr=410mV raster 3x3
  • 157338 05/30/08 19:13 cdaq Run 70632: GEp-III high Q2, 94uA, ps1=2000 ps2=2000 ps3=99999 ps4=1, ps5=1, ps6=99999, {ps7=1;FPP=3.0V} BigCal_thr=410mV raster 3x3
  • 157337 05/30/08 19:12 cdaq End of Run 70631:
  • 157336 05/30/08 18:20 cdaq Run 70631: GEp-III high Q2, 94uA, ps1=2000 ps2=2000 ps3=99999 ps4=1, ps5=1, ps6=99999, {ps7=1;FPP=3.0V} BigCal_thr=410mV raster 3x3
  • 157335 05/30/08 18:19 cdaq End of Run 70630:
  • 157334 05/30/08 17:39 smithg Target: Target screen snapshot
  • 157333 05/30/08 17:20 jensen roc 13 crash
  • 157332 05/30/08 17:20 cdaq Run 70630: GEp-III high Q2, 94uA, ps1=2000 ps2=2000 ps3=99999 ps4=1, ps5=1, ps6=99999, {ps7=1;FPP=3.0V} BigCal_thr=410mV raster 3x3
  • 157331 05/30/08 16:40 cdaq Run 70629: GEp-III high Q2, 94uA, ps1=2000 ps2=2000 ps3=99999 ps4=1, ps5=1, ps6=99999, {ps7=1;FPP=3.0V} BigCal_thr=410mV raster 3x3
  • 157330 05/30/08 16:38 cdaq End of Run 70628:
  • 157329 05/30/08 16:04 cdaq Beam Time Accounting
  • 157328 05/30/08 16:04 Boeglin Shift Summary
  • 157327 05/30/08 16:00 vahe Target: End of shift: Target screenshot
  • 157326 05/30/08 15:45 cdaq Run 70628: GEp-III high Q2, 94uA, ps1=2000 ps2=2000 ps3=99999 ps4=1, ps5=1, ps6=99999, {ps7=1;FPP=3.0V} BigCal_thr=410mV raster 3x3
  • 157325 05/30/08 15:44 cdaq End of Run 70627:
  • 157324 05/30/08 14:46 cdaq Run 70627: GEp-III high Q2, 94uA, ps1=2000 ps2=2000 ps3=99999 ps4=1, ps5=1, ps6=99999, {ps7=1;FPP=3.0V} BigCal_thr=410mV raster 3x3
  • 157323 05/30/08 14:44 cdaq End of Run 70626:
  • 157322 05/30/08 13:52 cdaq Run 70626: GEp-III high Q2, 80uA, ps1=2000 ps2=2000 ps3=99999 ps4=1, ps5=1, ps6=99999, {ps7=1;FPP=3.0V} BigCal_thr=410mV raster 3x3
  • 157321 05/30/08 13:42 cdaq End of Run 70625:
  • 157320 05/30/08 13:36 cdaq Run 70625: GEp-III high Q2, 80uA, ps1=2000 ps2=2000 ps3=99999 ps4=1, ps5=1, ps6=99999, {ps7=1;FPP=3.0V} BigCal_thr=410mV raster 3x3
  • 157319 05/30/08 13:35 cdaq End of Run 70624:
  • 157318 05/30/08 12:39 cdaq Run 70624: GEp-III high Q2, 80uA, ps1=2000 ps2=2000 ps3=99999 ps4=1, ps5=1, ps6=99999, {ps7=1;FPP=3.0V} BigCal_thr=410mV raster 3x3
  • 157317 05/30/08 12:32 cdaq End of Run 70623:
  • 157316 05/30/08 12:16 cdaq Run 70623: GEp-III high Q2, 80uA, ps1=2000 ps2=2000 ps3=99999 ps4=1, ps5=1, ps6=99999, {ps7=1;FPP=3.0V} BigCal_thr=410mV raster 3x3
  • 157315 05/30/08 12:15 cdaq End of Run 70622:
  • 157314 05/30/08 11:43 silviu Beam: beam issues
  • 157313 05/30/08 11:42 silviu Beam: beam issues
  • 157312 05/30/08 11:22 cdaq Run 70622: GEp-III high Q2, 80uA, ps1=2000 ps2=2000 ps3=99999 ps4=1, ps5=1, ps6=99999, {ps7=1;FPP=3.0V} BigCal_thr=410mV raster 3x3
  • 157311 05/30/08 11:20 cdaq End of Run 70621:
  • 157310 05/30/08 10:18 cdaq Run 70621: GEp-III high Q2, 80uA, ps1=2000 ps2=2000 ps3=99999 ps4=1, ps5=1, ps6=99999, {ps7=1;FPP=3.0V} BigCal_thr=410mV raster 3x3
  • 157309 05/30/08 10:18 cdaq End of Run 70620:
  • 157308 05/30/08 09:10 Boeglin ROC 11 reboot
  • 157307 05/30/08 09:08 cdaq Run 70620: GEp-III high Q2, 80uA, ps1=2000 ps2=2000 ps3=99999 ps4=1, ps5=1, ps6=99999, {ps7=1;FPP=3.0V} BigCal_thr=410mV raster 3x3
  • 157306 05/30/08 08:33 cdaq Run 70619: GEp-III high Q2, 80uA, ps1=2000 ps2=2000 ps3=99999 ps4=1, ps5=1, ps6=99999, {ps7=1;FPP=3.0V} BigCal_thr=410mV raster 3x3
  • 157305 05/30/08 08:31 cdaq End of Run 70618:
  • 157304 05/30/08 08:03 vahe Target: Start of shift: Target screenshot
  • 157303 05/30/08 08:01 reinhold owl shift summary
  • 157302 05/30/08 08:01 cdaq Beam Time Accounting
  • 157301 05/30/08 07:35 cdaq Run 70618: GEp-III high Q2, 80uA, ps1=2000 ps2=2000 ps3=99999 ps4=1, ps5=1, ps6=99999, {ps7=1;FPP=3.0V} BigCal_thr=410mV raster 3x3
  • 157300 05/30/08 07:25 cdaq End of Run 70617:
  • 157299 05/30/08 06:08 cdaq Run 70617: GEp-III high Q2, 80uA, ps1=2000 ps2=2000 ps3=99999 ps4=1, ps5=1, ps6=99999, {ps7=1;FPP=3.0V} BigCal_thr=410mV raster 3x3
  • 157298 05/30/08 06:07 cdaq End of Run 70616:
  • 157297 05/30/08 06:05 Ransome target: screen shot
  • 157296 05/30/08 06:04 reinhold BPM snapshot of last hour
  • 157295 05/30/08 04:38 cdaq Run 70616: GEp-III high Q2, 80uA, ps1=2000 ps2=2000 ps3=99999 ps4=1, ps5=1, ps6=99999, {ps7=1;FPP=3.0V} BigCal_thr=410mV raster 3x3
  • 157294 05/30/08 04:37 cdaq End of Run 70615:
  • 157293 05/30/08 04:22 reinhold BPM screen of 4th hour of beam
  • 157292 05/30/08 03:21 reinhold 3rd hour of beam BPM screen
  • 157291 05/30/08 03:20 cdaq Run 70615: GEp-III high Q2, 80uA, ps1=2000 ps2=2000 ps3=99999 ps4=1, ps5=1, ps6=99999, {ps7=1;FPP=3.0V} BigCal_thr=410mV raster 3x3
  • 157290 05/30/08 03:19 cdaq End of Run 70614:
  • 157289 05/30/08 03:16
  • 157288 05/30/08 02:24 reinhold let's throw in a BPM screen ...
  • 157287 05/30/08 02:23 reinhold bcm screen 2nd hour
  • 157286 05/30/08 02:04 cdaq Run 70614: GEp-III high Q2, 80uA, ps1=2000 ps2=2000 ps3=99999 ps4=1, ps5=1, ps6=99999, {ps7=1;FPP=3.0V} BigCal_thr=410mV raster 3x3
  • 157285 05/30/08 02:04 reinhold 1:54 am: no beam; MCC has a cavity problem
  • 157284 05/30/08 01:54 cdaq End of Run 70613:
  • 157283 05/30/08 01:33 W. Luo Yes, that channel was set to 500v by us
  • 157282 05/30/08 01:25 cdaq Run 70613: GEp-III high Q2, 90uA, ps1=2000 ps2=2000 ps3=99999 ps4=1, ps5=1, ps6=99999, {ps7=1;FPP=3.0V} BigCal_thr=410mV raster 3x3
  • 157281 05/30/08 01:24 cdaq End of Run 70612:
  • 157280 05/30/08 01:21 reinhold trip rate 1st hour of beam
  • 157279 05/30/08 00:36 Ransome target: JT readout frozen
  • 157278 05/30/08 00:29 reinhold BigCal High Voltage (HV) channel 32-1-9 is 500 V
  • 157277 05/30/08 00:23 reinhold MCC brings beam back ~ 00:20 AM
  • 157276 05/30/08 00:22 cdaq Run 70612: GEp-III high Q2, 90uA, ps1=2000 ps2=2000 ps3=99999 ps4=1, ps5=1, ps6=99999, {ps7=1;FPP=3.0V} BigCal_thr=410mV raster 3x3
  • 157275 05/30/08 00:00 cdaq Beam Time Accounting
  • Thursday

  • 157274 05/29/08 23:56 jmaxwell Swing Shift Summary, 5/29/08
  • 157273 05/29/08 21:53 jmaxwell No Beam
  • 157272 05/29/08 20:52 jmaxwell jmaxwell
  • 157271 05/29/08 20:06 jmaxwell Beam still down
  • 157270 05/29/08 19:12 jmaxwell Down for MCC
  • 157269 05/29/08 18:53 cdaq End of Run 70611:
  • 157268 05/29/08 17:59 W. Luo restarted BETABRITE display
  • 157267 05/29/08 17:55 cdaq Run 70611: GEp-III high Q2, 90uA, ps1=2000 ps2=2000 ps3=99999 ps4=1, ps5=1, ps6=99999, {ps7=1;FPP=3.0V} BigCal_thr=410mV raster 3x3
  • 157266 05/29/08 17:55 cdaq End of Run 2:
  • 157265 05/29/08 17:54 cdaq Run 2: GEp-III high Q2, 80uA, ps1=2000 ps2=2000 ps3=99999 ps4=1, ps5=1, ps6=99999, {ps7=1;FPP=3.0V} BigCal_thr=410mV raster 3x3
  • 157264 05/29/08 17:53 cdaq End of Run 1:
  • 157263 05/29/08 17:51 saw DAQ problem resolution
  • 157262 05/29/08 17:50 puckett Run 1! Does that mean we get to start over?
  • 157261 05/29/08 17:47 jmaxwell Hall C Switch Reboot and Finally Back Up
  • 157260 05/29/08 17:43 cdaq Run 1: GEp-III high Q2, 80uA, ps1=2000 ps2=2000 ps3=99999 ps4=1, ps5=1, ps6=99999, {ps7=1;FPP=3.0V} BigCal_thr=410mV raster 3x3
  • 157259 05/29/08 17:28 jamxwell Problems Fixed?
  • 157258 05/29/08 17:16 jmaxwell Down: DAQ Problems
  • 157257 05/29/08 17:08 W. Luo BigCal HV channels in group38 lower than set value from time to time
  • 157256 05/29/08 16:40 saw HMS Hall Probe EPICS working again
  • 157255 05/29/08 16:19 cdaq End of Run 70599:
  • 157254 05/29/08 16:18 cdaq Beam Time Accounting
  • 157253 05/29/08 16:10 Rondon Reboot Hall C switch at end of run 70599
  • 157252 05/29/08 16:09 Rondon Day shift summary
  • 157251 05/29/08 16:06 J Mulholland Target : Gui screenshot
  • 157250 05/29/08 16:03 saw End of run entries
  • 157249 05/29/08 16:02 Rondon Moller message about lost connection to vmec10
  • 157248 05/29/08 15:23 Rondon Loss of communication to BigCal HV
  • 157247 05/29/08 15:21 cdaq Run 70599: GEp-III high Q2, 80uA, ps1=2000 ps2=2000 ps3=99999 ps4=1, ps5=1, ps6=99999, {ps7=1;FPP=3.0V} BigCal_thr=410mV raster 3x3
  • 157246 05/29/08 15:11 cdaq End of Run 70598:
  • 157245 05/29/08 15:07 cdaq Run 70598: GEp-III high Q2, 80uA, ps1=2000 ps2=2000 ps3=99999 ps4=1, ps5=1, ps6=99999, {ps7=1;FPP=3.0V} BigCal_thr=410mV raster 3x3
  • 157244 05/29/08 15:04 cdaq End of Run 70597:
  • 157243 05/29/08 14:59 Rondon Analysis: End of run info not logged for runs 70582 and later
  • 157242 05/29/08 13:58 cdaq Run 70597: GEp-III high Q2, 80uA, ps1=2000 ps2=2000 ps3=99999 ps4=1, ps5=1, ps6=99999, {ps7=1;FPP=3.0V} BigCal_thr=410mV raster 3x3
  • 157241 05/29/08 13:56 cdaq End of Run 70596:
  • 157240 05/29/08 13:08 vahe BPM/BCM screenshots
  • 157239 05/29/08 12:47 L. Zhu Target: strange dips
  • 157238 05/29/08 12:42 cdaq Run 70596: GEp-III high Q2, 80uA, ps1=2000 ps2=2000 ps3=99999 ps4=1, ps5=1, ps6=99999, {ps7=1;FPP=3.0V} BigCal_thr=410mV raster 3x3
  • 157237 05/29/08 12:40 cdaq End of Run 70595:
  • 157236 05/29/08 12:30 L. Zhu Target: screenshot
  • 157235 05/29/08 11:24 cdaq Run 70595: GEp-III high Q2, 80uA, ps1=2000 ps2=2000 ps3=99999 ps4=1, ps5=1, ps6=99999, {ps7=1;FPP=3.0V} BigCal_thr=410mV raster 3x3
  • 157234 05/29/08 11:23 cdaq End of Run 70594:
  • 157233 05/29/08 11:12 vahe GEP HV alarm
  • 157232 05/29/08 10:57 silviu Beam: beam studies
  • 157231 05/29/08 10:43 Analysis: Runs with missing BigCal channels are 70590-70593
  • 157230 05/29/08 10:22 Rondon Upstairs counting house AC status
  • 157229 05/29/08 10:13 Rondon Beam: Spot moved
  • 157228 05/29/08 09:59 cdaq Run 70594: GEp-III high Q2, 80uA, ps1=2000 ps2=2000 ps3=99999 ps4=1, ps5=1, ps6=99999, {ps7=1;FPP=3.0V} BigCal_thr=410mV raster 3x3
  • 157227 05/29/08 09:33 W. Luo Due to two HV crate failed problem, Run 69590-69593 was taken without 64 channels in the middle of BigCal
  • 157226 05/29/08 09:20 W. Luo Put 2 fans near these two crate, and the AC in the room was off
  • 157225 05/29/08 09:01 cdaq End of Run 70593:
  • 157224 05/29/08 08:49 Rondon Beam: will be off around 9:00 for about 1/2 h
  • 157223 05/29/08 08:42 gaskell Moller ioc reboot
  • 157222 05/29/08 08:18 cdaq Run 70593: GEp-III high Q2, 80uA, ps1=2000 ps2=2000 ps3=99999 ps4=1, ps5=1, ps6=99999, {ps7=1;FPP=3.0V} BigCal_thr=410mV raster 3x3
  • 157221 05/29/08 08:16 cdaq End of Run 70592:
  • 157220 05/29/08 08:02 reinhold owl shift summary
  • 157219 05/29/08 08:01 cdaq Beam Time Accounting
  • 157218 05/29/08 07:06 cdaq Run 70592: GEp-III high Q2, 80uA, ps1=2000 ps2=2000 ps3=99999 ps4=1, ps5=1, ps6=99999, {ps7=1;FPP=3.0V} BigCal_thr=410mV raster 3x3
  • 157217 05/29/08 07:05 cdaq End of Run 70591:
  • 157216 05/29/08 06:45 reinhold turned off trip beep in gep HV GUI
  • 157215 05/29/08 05:51 Nuruzzaman BPM/BCM Screenshot
  • 157214 05/29/08 05:47 Phil Carter Target: fan died, recovered
  • 157213 05/29/08 05:44 cdaq Run 70591: GEp-III high Q2, 80uA, ps1=2000 ps2=2000 ps3=99999 ps4=1, ps5=1, ps6=99999, {ps7=1;FPP=3.0V} BigCal_thr=410mV raster 3x3
  • 157212 05/29/08 05:41 W. Luo HV crate 32, 34 problem
  • 157211 05/29/08 05:36 cdaq End of Run 70590:
  • 157210 05/29/08 04:49 reinhold There are 2 spare HV crates in electronics room
  • 157209 05/29/08 04:48 Reinhold running with 2 groups off in big cal
  • 157208 05/29/08 04:41 cdaq Run 70590: GEp-III high Q2, 80uA, ps1=2000 ps2=2000 ps3=99999 ps4=1, ps5=1, ps6=99999, {ps7=1;FPP=3.0V} BigCal_thr=410mV raster 3x3
  • 157207 05/29/08 04:41 reinhold Continue taking beam with bigcal HV group 2 & 4 off
  • 157206 05/29/08 03:38 Reinhold hcreboot14.jlab.org not reachable
  • 157205 05/29/08 03:16
  • 157204 05/29/08 03:12 Reinhold still HV problems
  • 157203 05/29/08 02:56 Reinhold Still BigCal HV problem; called Wei Luo
  • 157202 05/29/08 02:33 rei8nhold request beam off to investigate HV trips
  • 157201 05/29/08 02:25 reinhold MCC sending tuned again
  • 157200 05/29/08 02:16 cdaq End of Run 70589:
  • 157199 05/29/08 02:10 Nuruzzaman 5th group of Gep HV Controls shows alarm
  • 157198 05/29/08 02:08 cdaq Run 70589: GEp-III high Q2, 80uA, ps1=2000 ps2=2000 ps3=99999 ps4=1, ps5=1, ps6=99999, {ps7=1;FPP=3.0V} BigCal_thr=410mV raster 3x3
  • 157197 05/29/08 01:58 cdaq End of Run 70588:
  • 157196 05/29/08 01:56 reinhold MCC sending beam again
  • 157195 05/29/08 01:54 cdaq Run 70588: GEp-III high Q2, 80uA, ps1=2000 ps2=2000 ps3=99999 ps4=1, ps5=1, ps6=99999, {ps7=1;FPP=3.0V} BigCal_thr=410mV raster 3x3
  • 157194 05/29/08 01:50 cdaq End of Run 70587:
  • 157193 05/29/08 00:31 cdaq Run 70587: GEp-III high Q2, 80uA, ps1=2000 ps2=2000 ps3=99999 ps4=1, ps5=1, ps6=99999, {ps7=1;FPP=3.0V} BigCal_thr=410mV raster 3x3
  • 157192 05/29/08 00:28 cdaq End of Run 70586:
  • 157191 05/29/08 00:05 jmaxwell Swing Shift Summary, 5/28/08
  • 157190 05/29/08 00:01 cdaq Beam Time Accounting
  • Wednesday

  • 157189 05/28/08 23:14 cdaq Run 70586: GEp-III high Q2, 80uA, ps1=2000 ps2=2000 ps3=99999 ps4=1, ps5=1, ps6=99999, {ps7=1;FPP=3.0V} BigCal_thr=410mV raster 3x3
  • 157188 05/28/08 23:13 cdaq End of Run 70585:
  • 157187 05/28/08 23:11 pking Target: screenshots with 78 uA
  • 157186 05/28/08 22:14 cdaq Run 70585: GEp-III high Q2, 80uA, ps1=2000 ps2=2000 ps3=99999 ps4=1, ps5=1, ps6=99999, {ps7=1;FPP=3.0V} BigCal_thr=410mV raster 3x3
  • 157185 05/28/08 21:44 cdaq End of Run 70584:
  • 157184 05/28/08 21:43 cdaq Run 70584: GEp-III high Q2, 80uA, ps1=2000 ps2=2000 ps3=99999 ps4=1, ps5=1, ps6=99999, {ps7=1;FPP=3.0V} BigCal_thr=410mV raster 3x3
  • 157183 05/28/08 21:42 cdaq End of Run 70583:
  • 157182 05/28/08 21:37 j mulholland bpm shot while the beam is on
  • 157181 05/28/08 21:36 j mulholland bpm and bcm screenshots
  • 157180 05/28/08 20:55 jmaxwell HCLog Web Interface Back Online
  • 157179 05/28/08 20:37 J Mulholland Full replay run 70581
  • 157178 05/28/08 20:27 cdaq Run 70583: GEp-III high Q2, 90uA, ps1=2000 ps2=2000 ps3=99999 ps4=1, ps5=1, ps6=99999, {ps7=1;FPP=3.0V} BigCal_thr=410mV raster 3x3
  • 157177 05/28/08 20:16 cdaq End of Run 70582:
  • 157176 05/28/08 19:27 pking Target: mid-shift screenshots
  • 157175 05/28/08 19:17 cdaq Run 70582: GEp-III high Q2, 90uA, ps1=2000 ps2=2000 ps3=99999 ps4=1, ps5=1, ps6=99999, {ps7=1;FPP=3.0V} BigCal_thr=410mV raster 3x3
  • 157174 05/28/08 19:16 cdaq End of Run 70581:
  • 157173 05/28/08 18:19 cdaq Run 70581: GEp-III high Q2, 90uA, ps1=2000 ps2=2000 ps3=99999 ps4=1, ps5=1, ps6=99999, {ps7=1;FPP=3.0V} BigCal_thr=410mV raster 3x3
  • 157172 05/28/08 18:18 cdaq End of Run 70580:
  • 157171 05/28/08 17:51 J Mulholland Big Cal ADC Pedestal offset.
  • 157170 05/28/08 17:24 cdaq Run 70580: GEp-III high Q2, 90uA, ps1=2000 ps2=2000 ps3=99999 ps4=1, ps5=1, ps6=99999, {ps7=1;FPP=3.0V} BigCal_thr=410mV raster 3x3
  • 157169 05/28/08 17:23 cdaq End of Run 70579:
  • 157168 05/28/08 16:50 pking Target: control screens at beginning of shift
  • 157167 05/28/08 16:28 jmaxwell ROC 2 crash
  • 157166 05/28/08 16:23 Rondon Day shift summary
  • 157165 05/28/08 16:21 cdaq Run 70579: GEp-III high Q2, 80uA, ps1=2000 ps2=2000 ps3=99999 ps4=1, ps5=1, ps6=99999, {ps7=1;FPP=3.0V} BigCal_thr=410mV raster 3x3
  • 157164 05/28/08 16:07 cdaq Beam Time Accounting
  • 157163 05/28/08 15:16 Rondon Current up to 82 muA
  • 157162 05/28/08 15:16 cdaq Run 70578: GEp-III high Q2, 80uA, ps1=2000 ps2=2000 ps3=99999 ps4=1, ps5=1, ps6=99999, {ps7=1;FPP=3.0V} BigCal_thr=410mV raster 3x3
  • 157161 05/28/08 15:14 cdaq End of Run 70577:
  • 157160 05/28/08 14:07 cdaq Run 70577: GEp-III high Q2, 70uA, ps1=2000 ps2=2000 ps3=99999 ps4=1, ps5=1, ps6=99999, {ps7=1;FPP=3.0V} BigCal_thr=410mV, raster 3x3 SO HV added 25V
  • 157159 05/28/08 14:06 cdaq S0 HV change
  • 157158 05/28/08 14:03 cdaq End of Run 70576:
  • 157157 05/28/08 13:37 Rondon MCC says 73 muA is max stable current for the moment
  • 157156 05/28/08 12:43 cdaq Run 70576: GEp-III high Q2, 60uA, ps1=2000 ps2=2000 ps3=99999 ps4=1, ps5=1, ps6=99999, {ps7=1;FPP=3.0V} BigCal_thr=410mV, raster 3x3
  • 157155 05/28/08 12:36 cdaq End of Run 70575:
  • 157154 05/28/08 11:31 puckett BigCal threshold is 410 mV, not 440 mV as in the run start comments
  • 157153 05/28/08 11:28 Rondon Beam status: 65 muA maximum stable current for time being
  • 157152 05/28/08 11:25 cdaq Run 70575: GEp-III high Q2, 80uA, ps1=2000 ps2=2000 ps3=99999 ps4=1, ps5=1, ps6=99999, {ps7=1;FPP=3.0V} BigCal_thr=440mV RASTER 3x3mm
  • 157151 05/28/08 11:16 cdaq End of Run 70574:
  • 157150 05/28/08 11:16 cdaq Run 70574: GEp-III high Q2, 80uA, ps1=10 ps2=10 ps3=99999 ps4=1, ps5=1, ps6=99999, {ps7=1;FPP=3.0V} BigCal_thr=440mV
  • 157149 05/28/08 11:07 Rondon Prescale, raster changes
  • 157148 05/28/08 09:48 cdaq End of Run 70573:
  • 157147 05/28/08 09:45 Rondon MCC called about beam trips: beam will be off to invetigate
  • 157146 05/28/08 09:18 cdaq Run 70573: GEp-III high Q2, 80uA, ps1=10 ps2=10 ps3=99999 ps4=1, ps5=1, ps6=99999, {ps7=1;FPP=3.0V} BigCal_thr=440mV
  • 157145 05/28/08 09:16 cdaq End of Run 70572:
  • 157144 05/28/08 08:43 smithg Target: screen snapshot
  • 157143 05/28/08 08:13 cdaq Beam Time Accounting
  • 157142 05/28/08 08:07 Reinhold Owl shift summary
  • 157141 05/28/08 08:00 reinhold horrible trip rate
  • 157140 05/28/08 07:55 cdaq Run 70572: GEp-III high Q2, 80uA, ps1=10 ps2=10 ps3=99999 ps4=1, ps5=1, ps6=99999, {ps7=1;FPP=3.0V} BigCal_thr=440mV
  • 157139 05/28/08 07:54 cdaq End of Run 70571:
  • 157138 05/28/08 06:12 cdaq Run 70571: GEp-III high Q2, 80uA, ps1=10 ps2=10 ps3=99999 ps4=1, ps5=1, ps6=99999, {ps7=1;FPP=3.0V} BigCal_thr=440mV
  • 157137 05/28/08 06:11 cdaq End of Run 70570:
  • 157136 05/28/08 05:26 Nuruzzaman BPM/BCM Screenshot
  • 157135 05/28/08 05:15 cdaq Run 70570: GEp-III high Q2, 80uA, ps1=10 ps2=10 ps3=99999 ps4=1, ps5=1, ps6=99999, {ps7=1;FPP=3.0V} BigCal_thr=440mV
  • 157134 05/28/08 05:14 cdaq End of Run 70569:
  • 157133 05/28/08 04:10 cdaq Run 70569: GEp-III high Q2, 80uA, ps1=10 ps2=10 ps3=99999 ps4=1, ps5=1, ps6=99999, {ps7=1;FPP=3.0V} BigCal_thr=440mV
  • 157132 05/28/08 04:09 cdaq End of Run 70568:
  • 157131 05/28/08 03:16
  • 157130 05/28/08 03:02 cdaq Run 70568: GEp-III high Q2, 80uA, ps1=10 ps2=10 ps3=99999 ps4=1, ps5=1, ps6=99999, {ps7=1;FPP=3.0V} BigCal_thr=440mV
  • 157129 05/28/08 03:01 cdaq End of Run 70567:
  • 157128 05/28/08 02:11 Phil Carter Target: unusual transient alarm
  • 157127 05/28/08 01:56 Nuruzzaman With changed gold file Histograms are matching perfectly
  • 157126 05/28/08 01:44 cdaq Run 70567: GEp-III high Q2, 80uA, ps1=10 ps2=10 ps3=99999 ps4=1, ps5=1, ps6=99999, {ps7=1;FPP=3.0V} BigCal_thr=440mV
  • 157125 05/28/08 01:43 cdaq End of Run 70566:
  • 157124 05/28/08 01:38 puckett changed golden file to run 70566
  • 157123 05/28/08 00:57 Nuruzzaman Histograms are changed as the kinematics satting has been changed
  • 157122 05/28/08 00:45 cdaq Run 70566: GEp-III high Q2, 80uA, ps1=10 ps2=10 ps3=99999 ps4=1, ps5=1, ps6=99999, ps7=1;FPP=3.0V BigCal_thr=230mV
  • 157121 05/28/08 00:41 cdaq End of Run 70565:
  • 157120 05/28/08 00:34 Reinhold Guard calls: keywatcher box in EEL gives alarm
  • 157119 05/28/08 00:31 Reinhold Beam: Run plan: Updated Beam Positions
  • 157118 05/28/08 00:06 Phil Carter Target: screenshot
  • 157117 05/28/08 00:01 cdaq Beam Time Accounting
  • Tuesday

  • 157116 05/27/08 23:59 puckett elastic yield before and after S0 HV increase
  • 157115 05/27/08 23:57 jmaxwell Swing Shift Summary, 5/27/08
  • 157114 05/27/08 23:09 J. Maxwell SO HV increased by 25 v
  • 157113 05/27/08 23:04 cdaq Run 70565: GEp-III high Q2, 80uA, ps1=10 ps2=10 ps3=99999 ps4=2000, ps5=1, FPP=3.0V BigCal_thr=230mV
  • 157112 05/27/08 23:01 cdaq End of Run 70564:
  • 157111 05/27/08 22:40 cdaq Run 70564: GEp-III high Q2, 80uA, ps1=10 ps2=10 ps3=99999 ps4=2000, ps5=1, FPP=3.0V BigCal_thr=230mV
  • 157110 05/27/08 22:40 cdaq End of Run 70563:
  • 157109 05/27/08 22:31 Rondon Hall C beam energy
  • 157108 05/27/08 22:27 Rondon BPM and BCM
  • 157107 05/27/08 21:36 cdaq Run 70563: GEp-III high Q2, 80uA, ps1=10 ps2=10 ps3=99999 ps4=2000, ps5=1, FPP=3.0V BigCal_thr=230mV
  • 157106 05/27/08 21:36 puckett noticed that three bigcal.tcl displays were running on cdaql6--killed
  • 157105 05/27/08 21:35 cdaq End of Run 70562:
  • 157104 05/27/08 20:35 cdaq Run 70562: GEp-III high Q2, 80uA, ps1=10 ps2=10 ps3=99999 ps4=2000, ps5=1, FPP=3.0V BigCal_thr=230mV
  • 157103 05/27/08 20:34 cdaq End of Run 70561:
  • 157102 05/27/08 20:33 jmaxwell Deadtime Higher Why?
  • 157101 05/27/08 19:58 puckett updated BigCal ADC thresholds using nsparse=20
  • 157100 05/27/08 19:34 cdaq Run 70561: GEp-III high Q2, 100uA, ps1=10 ps2=10 ps3=99999 ps4=2000, ps5=1, FPP=3.0V BigCal_thr=230mV
  • 157099 05/27/08 19:34 cdaq End of Run 70560:
  • 157098 05/27/08 19:31 puckett updated BigCal ADC thresholds using nsparse = 18
  • 157097 05/27/08 19:21 puckett elastic rate at new kinematics for low current run 70559
  • 157096 05/27/08 19:18 cdaq Run 70560: GEp-III high Q2, 100uA, ps1=10 ps2=10 ps3=99999 ps4=2000, ps5=1, FPP=3.0V BigCal_thr=230mV
  • 157095 05/27/08 19:14 cdaq End of Run 70559:
  • 157094 05/27/08 19:03 cdaq Run 70559: GEp-III high Q2, 80uA, ps1=10 ps2=10 ps3=99999 ps4=2000, ps5=1, FPP=3.0V BigCal_thr=230mV
  • 157093 05/27/08 18:51 cdaq End of Run 70558:
  • 157092 05/27/08 17:43 cdaq Run 70558: GEp-III high Q2 Dummy, 40uA, ps1=10 ps2=10 ps3=99999 ps4=2000, ps5=1, FPP=3.0V BigCal_thr=230mV
  • 157091 05/27/08 17:43 cdaq End of Run 70557:
  • 157090 05/27/08 16:44 cdaq Run 70557: GEp-III high Q2 Dummy, 40uA, ps1=10 ps2=10 ps3=99999 ps4=2000, ps5=1, FPP=3.0V BigCal_thr=230mV
  • 157089 05/27/08 16:44 W. Luo BigCal Gain and resolution now
  • 157088 05/27/08 16:35 J Mulholland Target : Moving to 20cm dummy
  • 157087 05/27/08 16:33 cdaq End of Run 70556:
  • 157086 05/27/08 16:06 J Mulholland Target : Screenshot Swing Shift
  • 157085 05/27/08 16:02 cdaq Beam Time Accounting
  • 157084 05/27/08 15:58 Keppel shift summary
  • 0 05/27/08 15:58 no_name no_key
  • 157082 05/27/08 15:50 vahe Screen snapshots bpm/bcm
  • 157081 05/27/08 15:47 L. Zhu target: screenshots
  • 157080 05/27/08 15:42 Keppel ROC reboots
  • 157079 05/27/08 15:35 cdaq Run 70556: GEp-III Q2=6.8, 80uA, ps1=1000 ps2=500 ps3=99999 ps4=1, ps5=1, FPP=3.0V BigCal_thr=410mV
  • 157078 05/27/08 15:08 Keppel Q3 Hall probe fluctuations
  • 157077 05/27/08 14:53 puckett Increased BigCal threshold from 230 mV to 410 mV
  • 157076 05/27/08 14:51 puckett Turned back on S1X HV for channels 1-4 and 13-16
  • 157075 05/27/08 14:50 Keppel prescale, threshold changes
  • 157074 05/27/08 14:50 cdaq Run 70555: GEp-III high Q2, 80uA, ps1=1000 ps2=500 ps3=99999 ps4=1, ps5=1, FPP=3.0V BigCal_thr=410mV
  • 157073 05/27/08 14:42 cdaq End of Run 70554:
  • 157072 05/27/08 14:30 puckett turn back on S1X 1-4 and 13-16?
  • 157071 05/27/08 14:18 horn energy measurement software test
  • 157070 05/27/08 14:07 cdaq Run 70554: GEp-III high Q2, 80uA, ps1=1000 ps2=500 ps3=99999 ps4=2000, ps5=1, FPP=3.0V BigCal_thr=230mV
  • 157069 05/27/08 13:52 gaskell One more Moller ioc reboot
  • 157068 05/27/08 13:42 L. Zhu Taget: back to LH2
  • 157067 05/27/08 11:59 frw Run plan for the Q2 = 6.8 GeV2 Kinematic Point
  • 157066 05/27/08 11:46 W. Luo Updated KINEMATICS.db
  • 157065 05/27/08 11:34 puckett "TOYGEP" rate estimate for new kinematics:
  • 157064 05/27/08 11:19 L. Zhu Target: move to empty
  • 157063 05/27/08 10:57 M Jones Changed "S1S0X1" trigger
  • 157062 05/27/08 10:57 cdaq End of Run 70553:
  • 157061 05/27/08 10:56 frw pre-beam studies access
  • 157060 05/27/08 10:55 cdaq Run 70553: BigCal LED run
  • 157059 05/27/08 10:54 M Jones Change to HMS trigger
  • 157058 05/27/08 10:54 cdaq End of Run 70552:
  • 157057 05/27/08 10:53 cdaq Run 70552: BigCal LED run
  • 157056 05/27/08 09:14 Keppel magnet control computer
  • 157055 05/27/08 09:06 cdaq End of Run 70551:
  • 157054 05/27/08 08:05 cdaq Beam Time Accounting
  • 157053 05/27/08 08:04 Dutta Owl shift summary
  • 157052 05/27/08 08:00 cdaq Run 70551: GEp-III high Q2, 80uA, ps1=1000 ps2=500 ps3=99999 ps4=2000, ps5=1, FPP=3.0V BigCal_thr=230mV
  • 157051 05/27/08 07:59 cdaq End of Run 70550:
  • 157049 05/27/08 06:45 Phil Carter Target: screenshot
  • 157048 05/27/08 06:42 Nuruzzaman Screenshot of BPM/BCM
  • 157047 05/27/08 06:35 cdaq Run 70550: GEp-III high Q2, 80uA, ps1=1000 ps2=500 ps3=99999 ps4=2000, ps5=1, FPP=3.0V BigCal_thr=230mV
  • 157046 05/27/08 06:34 cdaq End of Run 70549:
  • 157045 05/27/08 04:57 cdaq Run 70549: GEp-III high Q2, 80uA, ps1=1000 ps2=500 ps3=99999 ps4=2000, ps5=1, FPP=3.0V BigCal_thr=230mV
  • 157044 05/27/08 04:56 cdaq End of Run 70548:
  • 157043 05/27/08 03:57 Nuruzzaman Histograms are looking fine
  • 157042 05/27/08 03:29 cdaq Run 70548: GEp-III high Q2, 80uA, ps1=1000 ps2=500 ps3=99999 ps4=2000, ps5=1, FPP=3.0V BigCal_thr=230mV
  • 157041 05/27/08 03:18 cdaq End of Run 70547:
  • 157040 05/27/08 03:18
  • 157039 05/27/08 02:35 cdaq Run 70547: GEp-III high Q2, 40uA, 20cm Dummy target, ps1=1000 ps2=500 ps3=99999 ps4=2000, ps5=1, FPP=3.0V BigCal_thr=230mV
  • 157038 05/27/08 02:32 cdaq End of Run 70546:
  • 157037 05/27/08 01:17 Nuruzzaman Histograms with Dummy target
  • 157036 05/27/08 01:02 Dutta Current is 40 muA not 80 muA for run 70546
  • 157035 05/27/08 01:00 Dutta Target is Dummy not LH2 for run 70546
  • 157034 05/27/08 00:52 cdaq Run 70546: GEp-III high Q2, 80uA, ps1=1000 ps2=500 ps3=99999 ps4=2000, ps5=1, FPP=3.0V BigCal_thr=230mV
  • 157033 05/27/08 00:34 jmaxwell Swing Shift Summary, 5/26/08
  • 157032 05/27/08 00:32 horn Moller Summary
  • 157031 05/27/08 00:20 horn Moller done
  • 157030 05/27/08 00:14 cdaq End of Run 70545:
  • 157029 05/27/08 00:03 cdaq Moller Run 70545: HWP=IN, Wien angle=-13.53 deg, after spot move
  • 157028 05/27/08 00:01 cdaq Beam Time Accounting
  • Monday

  • 157027 05/26/08 23:46 cdaq End of Run 70544:
  • 157026 05/26/08 23:45 horn Moller ioc rebooted (late entry)
  • 157025 05/26/08 23:37 cdaq Moller Run 70544: HWP=IN, Wien angle=-13.53 deg
  • 157024 05/26/08 23:36 cdaq End of Run 70543:
  • 157023 05/26/08 23:27 cdaq Moller Run 70543: HWP=IN, Wien angle=-13.53 deg
  • 157022 05/26/08 23:25 cdaq End of Run 70542:
  • 157021 05/26/08 23:11 cdaq Moller Run 70542: HWP=IN, Wien angle=-13.53 deg
  • 157020 05/26/08 23:03 narayan Target: Moller Measurement in process finally
  • 157019 05/26/08 22:12 horn no beam
  • 157018 05/26/08 20:34 Punjabi Measurement with dummy target
  • 157017 05/26/08 20:18 cdaq End of Run 70541:
  • 157016 05/26/08 20:17 cdaq Moller Run 70541: test
  • 157015 05/26/08 20:03 frw ...or not
  • 157014 05/26/08 19:38 frw Plan for the night
  • 157013 05/26/08 19:34 narayan Target parked > Moller Measurement in line
  • 157012 05/26/08 19:20 cdaq End of Run 70540:
  • 157011 05/26/08 19:16 cdaq Run 70540: GEp-III high Q2, 80uA, ps1=1000 ps2=500 ps3=99999 ps4=2000, ps5=1, FPP=3.0V BigCal_thr=230mV
  • 157010 05/26/08 18:16 jmaxwell Status From ELOG
  • 157009 05/26/08 16:56 narayan Target: On Shift
  • 157008 05/26/08 16:33 cdaq End of Run 70539:
  • 157007 05/26/08 16:32 cdaq Run 70539: BigCal LED run
  • 157006 05/26/08 16:28 W. Luo Target: Start of Shift with no beam
  • 157005 05/26/08 16:12 W. Luo I will be there as TO
  • 157004 05/26/08 16:08 J Mulholland Target : GUI shot and lack of operator
  • 157003 05/26/08 16:04 Boeglin Shift Summary
  • 157002 05/26/08 16:03 cdaq Beam Time Accounting
  • 157001 05/26/08 13:50 frw Beam: spot move tonight -- assessing Moller options
  • 157000 05/26/08 13:39 Boeglin Beam problems
  • 156999 05/26/08 13:32 cdaq End of Run 70538:
  • 156998 05/26/08 12:18 cdaq Run 70538: GEp-III high Q2, 80uA, ps1=1000 ps2=500 ps3=99999 ps4=2000, ps5=1, FPP=3.0V BigCal_thr=230mV
  • 156997 05/26/08 12:17 cdaq End of Run 70537:
  • 156996 05/26/08 11:34 boeglin BCM snapshot
  • 156995 05/26/08 11:33 boeglin BPM snapshot
  • 156994 05/26/08 10:49 cdaq Run 70537: GEp-III high Q2, 80uA, ps1=1000 ps2=500 ps3=99999 ps4=2000, ps5=1, FPP=3.0V BigCal_thr=230mV
  • 156993 05/26/08 10:48 cdaq End of Run 70536:
  • 156992 05/26/08 09:15 boeglin HMS powers supply comm. OK
  • 156991 05/26/08 09:14 cdaq Run 70536: GEp-III high Q2, 80uA, ps1=1000 ps2=500 ps3=99999 ps4=2000, ps5=1, FPP=3.0V BigCal_thr=230mV
  • 156990 05/26/08 09:13 cdaq End of Run 70535:
  • 156989 05/26/08 08:55 cdaq Run 70535: GEp-III high Q2, 80uA, ps1=1000 ps2=500 ps3=99999 ps4=2000, ps5=1, FPP=3.0V BigCal_thr=230mV
  • 156988 05/26/08 08:53 cdaq End of Run 70534:
  • 156987 05/26/08 08:52 Boeglin HMS powersupply comm. error
  • 156986 05/26/08 08:08 vahe Target: Start of shift,Target status
  • 156985 05/26/08 08:01 cdaq Beam Time Accounting
  • 156984 05/26/08 08:00 Dutta Owl shift summary
  • 156983 05/26/08 07:36 cdaq Run 70534: GEp-III high Q2, 80uA, ps1=1000 ps2=500 ps3=99999 ps4=2000, ps5=1, FPP=3.0V BigCal_thr=230mV
  • 156982 05/26/08 07:32 Dutta Beam off for 15 mins
  • 156981 05/26/08 07:29 cdaq End of Run 70533:
  • 156980 05/26/08 06:58 Phil Carter Target: screenshot
  • 156979 05/26/08 06:22 Nuruzzaman Shift Checklist
  • 156978 05/26/08 06:20 cdaq Run 70533: GEp-III high Q2, 80uA, ps1=1000 ps2=500 ps3=99999 ps4=2000, ps5=1, FPP=3.0V BigCal_thr=230mV
  • 156977 05/26/08 06:19 cdaq End of Run 70532:
  • 156976 05/26/08 05:14 Nuruzzaman Beam Energy Monitor Screenshot
  • 156975 05/26/08 05:12 Nuruzzaman BPM/BCM Screenshot
  • 156974 05/26/08 05:05 Dutta ROC 13 crashes
  • 156973 05/26/08 04:49 cdaq Run 70532: GEp-III high Q2, 80uA, ps1=1000 ps2=500 ps3=99999 ps4=2000, ps5=1, FPP=3.0V BigCal_thr=230mV
  • 156972 05/26/08 03:48 Phil Carter Target: IOC reboot
  • 156971 05/26/08 03:48 cdaq Run 70531: GEp-III high Q2, 80uA, ps1=1000 ps2=500 ps3=99999 ps4=2000, ps5=1, FPP=3.0V BigCal_thr=230mV
  • 156970 05/26/08 03:42 cdaq End of Run 70530:
  • 156969 05/26/08 03:22
  • 156968 05/26/08 02:18 Nuruzzaman Histograms are looking good
  • 156967 05/26/08 02:06 cdaq Run 70530: GEp-III high Q2, 80uA, ps1=1000 ps2=500 ps3=99999 ps4=2000, ps5=1, FPP=3.0V BigCal_thr=230mV
  • 156966 05/26/08 02:05 cdaq End of Run 70529:
  • 156965 05/26/08 00:54 Dutta Beam is back
  • 156964 05/26/08 00:45 cdaq Run 70529: GEp-III high Q2, 80uA, ps1=1000 ps2=500 ps3=99999 ps4=2000, ps5=1, FPP=3.0V BigCal_thr=230mV
  • 156963 05/26/08 00:09 Dutta Update from MCC
  • 156962 05/26/08 00:01 cdaq Beam Time Accounting
  • Sunday

  • 156961 05/25/08 23:49 Kumbartzki Swing shift summary
  • 156960 05/25/08 23:45 Kumbartzki BCBPM screen
  • 156959 05/25/08 23:41 narayan Target Routine Screenshot
  • 156958 05/25/08 23:26 kumbartzki slow running
  • 156957 05/25/08 22:59 puckett why large gaps between runs? Please make log entries about problems
  • 156956 05/25/08 22:41 cdaq End of Run 70528:
  • 156955 05/25/08 22:17 cdaq Run 70528: GEp-III high Q2, 80uA, ps1=1000 ps2=500 ps3=99999 ps4=2000, ps5=1, FPP=3.0V BigCal_thr=230mV
  • 156954 05/25/08 21:30 cdaq End of Run 70527:
  • 156953 05/25/08 19:52 cdaq Run 70527: GEp-III high Q2, 80uA, ps1=1000 ps2=500 ps3=99999 ps4=2000, ps5=1, FPP=3.0V BigCal_thr=230mV
  • 156952 05/25/08 19:49 cdaq End of Run 70526:
  • 156951 05/25/08 18:26 kumbartzki Roc 12 error
  • 156950 05/25/08 18:21 cdaq Run 70526: GEp-III high Q2, 80uA, ps1=1000 ps2=500 ps3=99999 ps4=2000, ps5=1, FPP=3.0V BigCal_thr=230mV
  • 156949 05/25/08 18:16 narayan Target Routine Screenshot
  • 156948 05/25/08 18:15 cdaq End of Run 70525:
  • 156947 05/25/08 18:15 yez run70524 Hit Stats 1 shape shifts
  • 156946 05/25/08 18:12 cdaq Run 70525: GEp-III high Q2, 80uA, ps1=1000 ps2=500 ps3=99999 ps4=2000, ps5=1, FPP=3.0V BigCal_thr=230mV
  • 156945 05/25/08 18:08 cdaq End of Run 70524:
  • 156944 05/25/08 17:11 Kumbartzki Q3 status
  • 156943 05/25/08 17:07 cdaq Run 70524: GEp-III high Q2, 80uA, ps1=1000 ps2=500 ps3=99999 ps4=2000, ps5=1, FPP=3.0V BigCal_thr=230mV
  • 156942 05/25/08 16:19 Kumbartzki Q3 power supply off
  • 156941 05/25/08 16:03 cdaq End of Run 70523:
  • 156940 05/25/08 16:02 Boeglin Shift Summary
  • 156939 05/25/08 16:02 cdaq Beam Time Accounting
  • 156938 05/25/08 15:51 Nuruzzaman Heater power variation during the shift
  • 156937 05/25/08 14:49 Nuruzzaman Routine Screenshot of Target GUI
  • 156936 05/25/08 14:47 cdaq Run 70523: GEp-III high Q2, 80uA, ps1=1000 ps2=500 ps3=99999 ps4=2000, ps5=1, FPP=3.0V BigCal_thr=230mV
  • 156935 05/25/08 14:45 cdaq End of Run 70522:
  • 156934 05/25/08 14:26 Nuruzzaman Cryo Flow of Hall-A & Hall-C
  • 156933 05/25/08 13:29 cdaq Run 70522: GEp-III high Q2, 80uA, ps1=1000 ps2=500 ps3=99999 ps4=2000, ps5=1, FPP=3.0V BigCal_thr=230mV
  • 156932 05/25/08 13:27 cdaq End of Run 70521:
  • 156931 05/25/08 11:34 cdaq Run 70521: GEp-III high Q2, 80uA, ps1=1000 ps2=500 ps3=99999 ps4=2000, ps5=1, FPP=3.0V BigCal_thr=230mV
  • 156930 05/25/08 11:33 cdaq End of Run 70520:
  • 156929 05/25/08 10:48 Nuruzzaman Beam Energy Monitor Screenshot
  • 156928 05/25/08 10:47 Nuruzzaman BCM Screenshot
  • 156927 05/25/08 10:46 Nuruzzaman He Supply gives a sudden spike
  • 156926 05/25/08 10:33 Nuruzzaman BPM Screenshot
  • 156925 05/25/08 10:01 cdaq Run 70520: GEp-III high Q2, 80uA, ps1=1000 ps2=500 ps3=99999 ps4=2000, ps5=1, FPP=3.0V BigCal_thr=230mV
  • 156924 05/25/08 09:58 cdaq End of Run 70519:
  • 156923 05/25/08 09:00 Nuruzzaman Routine Screen shot of Target GUI
  • 156922 05/25/08 08:58 Nuruzzaman Histograms are looking good for run# 70519
  • 156921 05/25/08 08:38 cdaq Run 70519: GEp-III high Q2, 80uA, ps1=1000 ps2=500 ps3=99999 ps4=2000, ps5=1, FPP=3.0V BigCal_thr=230mV
  • 156920 05/25/08 08:36 cdaq End of Run 70518:
  • 156919 05/25/08 08:02 cdaq Beam Time Accounting
  • 156918 05/25/08 07:46 puckett Shift summary
  • 156917 05/25/08 07:37 puckett slight decrease in elastic yield with BigCal threshold at 220 mV
  • 156916 05/25/08 07:22 puckett BPM/BCM and energy monitor screenshots
  • 156915 05/25/08 07:14 cdaq Run 70518: GEp-III high Q2, 80uA, ps1=1000 ps2=500 ps3=99999 ps4=2000, ps5=1, FPP=3.0V BigCal_thr=230mV
  • 156914 05/25/08 07:07 puckett ramp rate slow and decreasing--~0.1 A/s. Arggh
  • 156913 05/25/08 06:55 puckett Q3 ramping really slowly--is that normal?
  • 156912 05/25/08 06:35 puckett manually reset Q3 dump switch in hall
  • 156911 05/25/08 06:09 puckett asked for controlled access to reset Q3 dump switch in hall
  • 156910 05/25/08 05:57 puckett Asked MCC for beam off while waiting for Q3 recovery
  • 156909 05/25/08 05:53 puckett Called Steve Lassiter, he is looking at things remotely.
  • 156908 05/25/08 05:48 puckett HMS Q3 interlock won't reset
  • 156907 05/25/08 05:46 puckett HMS Q3 tripped off suddenly, ended run 70517
  • 156906 05/25/08 05:38 cdaq End of Run 70517:
  • 156905 05/25/08 05:32 puckett restored nominal BigCal threshold before run 70517
  • 156904 05/25/08 05:31 puckett ROC13 crash--ended run 70516, ~5 min recovery time
  • 156903 05/25/08 05:24 cdaq Run 70517: GEp-III high Q2, 80uA, ps1=1000 ps2=500 ps3=99999 ps4=2000, ps5=1, FPP=3.0V BigCal_thr=230mV
  • 156902 05/25/08 04:30 cdaq Run 70516: GEp-III high Q2, 80uA, ps1=1000 ps2=500 ps3=99999 ps4=2000, ps5=1, FPP=3.0V BigCal_thr=220mV
  • 156901 05/25/08 04:29 cdaq End of Run 70515:
  • 156900 05/25/08 04:24 kumbartzki target screen
  • 156899 05/25/08 04:13 puckett Lowered BigCal threshold to 220 mV during run 70515
  • 156898 05/25/08 03:22
  • 156897 05/25/08 03:08 cdaq Run 70515: GEp-III high Q2, 80uA, ps1=1000 ps2=500 ps3=99999 ps4=2000, ps5=1, FPP=3.0V BigCal_thr=230mV
  • 156896 05/25/08 03:07 cdaq End of Run 70514:
  • 156895 05/25/08 01:37 cdaq Run 70514: GEp-III high Q2, 80uA, ps1=1000 ps2=500 ps3=99999 ps4=2000, ps5=1, FPP=3.0V BigCal_thr=230mV
  • 156894 05/25/08 01:36 cdaq End of Run 70513:
  • 156893 05/25/08 00:06 cdaq Run 70513: GEp-III high Q2, 80uA, ps1=1000 ps2=500 ps3=99999 ps4=2000, ps5=1, FPP=3.0V BigCal_thr=230mV
  • 156892 05/25/08 00:05 cdaq End of Run 70512:
  • 156891 05/25/08 00:01 cdaq Beam Time Accounting
  • Saturday

  • 156890 05/24/08 23:56 hamlet Swing Shift Summary, 24 May 2008
  • 156889 05/24/08 23:50 narayan Target Routine Screenshot
  • 156888 05/24/08 22:33 cdaq Run 70512: GEp-III high Q2, 80uA, ps1=1000 ps2=500 ps3=99999 ps4=2000, ps5=1, FPP=3.0V BigCal_thr=230mV
  • 156887 05/24/08 22:32 cdaq End of Run 70511:
  • 156886 05/24/08 21:07 cdaq Run 70511: GEp-III high Q2, 80uA, ps1=1000 ps2=500 ps3=99999 ps4=2000, ps5=1, FPP=3.0V BigCal_thr=230mV
  • 156885 05/24/08 21:06 cdaq End of Run 70510:
  • 156884 05/24/08 19:53 hamlet ROC13 power cycled before run 70510
  • 156883 05/24/08 19:44 cdaq Run 70510: GEp-III high Q2, 80uA, ps1=1000 ps2=500 ps3=99999 ps4=2000, ps5=1, FPP=3.0V BigCal_thr=230mV
  • 156882 05/24/08 18:59 cdaq Run 70509: GEp-III high Q2, 80uA, ps1=1000 ps2=500 ps3=99999 ps4=2000, ps5=1, FPP=3.0V BigCal_thr=230mV
  • 156881 05/24/08 18:58 cdaq End of Run 70508:
  • 156880 05/24/08 18:53 narayan Target Routine Screenshot
  • 156879 05/24/08 17:44 hamlet ROC13 power cycled
  • 156878 05/24/08 17:39 cdaq Run 70508: GEp-III high Q2, 80uA, ps1=1000 ps2=500 ps3=99999 ps4=2000, ps5=1, FPP=3.0V BigCal_thr=230mV
  • 156877 05/24/08 16:14 cdaq Run 70507: GEp-III high Q2, 80uA, ps1=1000 ps2=500 ps3=99999 ps4=2000, ps5=1, FPP=3.0V BigCal_thr=230mV
  • 156876 05/24/08 16:13 cdaq End of Run 70506:
  • 156875 05/24/08 16:02 cdaq Beam Time Accounting
  • 156874 05/24/08 15:52 Kumbartzki Day shift summary
  • 156873 05/24/08 14:58 Nuruzzaman Target: Routine Screenshot of Target GUI
  • 156872 05/24/08 14:58 cdaq Run 70506: GEp-III high Q2, 80uA, ps1=1000 ps2=500 ps3=99999 ps4=2000, ps5=1, FPP=3.0V BigCal_thr=230mV
  • 156871 05/24/08 14:54 cdaq End of Run 70505:
  • 156870 05/24/08 14:17 Nuruzzaman Target: Cryo Flow Snapshot
  • 156869 05/24/08 13:40 cdaq Run 70505: GEp-III high Q2, 80uA, ps1=1000 ps2=500 ps3=99999 ps4=2000, ps5=1, FPP=3.0V BigCal_thr=230mV
  • 156868 05/24/08 13:38 cdaq End of Run 70504:
  • 156867 05/24/08 12:40 Boeglin beam energy snapshot
  • 156866 05/24/08 12:29 boeglin bpm/bcm screen shot
  • 156865 05/24/08 12:06 cdaq Run 70504: GEp-III high Q2, 80uA, ps1=1000 ps2=500 ps3=99999 ps4=2000, ps5=1, FPP=3.0V BigCal_thr=230mV
  • 156864 05/24/08 12:04 cdaq End of Run 70503:
  • 156863 05/24/08 11:04 Nuruzzaman Target: Routine Screenshot of Target GUI
  • 156862 05/24/08 11:04 Nuruzzaman Target: Routine Screenshot of Target GUI
  • 156861 05/24/08 10:02 cdaq Run 70503: GEp-III high Q2, 80uA, ps1=1000 ps2=500 ps3=99999 ps4=2000, ps5=1, FPP=3.0V BigCal_thr=230mV
  • 156860 05/24/08 10:01 cdaq End of Run 70502:
  • 156859 05/24/08 08:28 cdaq Run 70502: GEp-III high Q2, 80uA, ps1=1000 ps2=500 ps3=99999 ps4=2000, ps5=1, FPP=3.0V BigCal_thr=230mV
  • 156858 05/24/08 08:27 cdaq End of Run 70501:
  • 156857 05/24/08 08:02 silviu Owl shift summary
  • 156856 05/24/08 08:01 cdaq Beam Time Accounting
  • 156855 05/24/08 07:15 cdaq Run 70501: GEp-III high Q2, 80uA, ps1=1000 ps2=500 ps3=99999 ps4=2000, ps5=1, FPP=3.0V BigCal_thr=230mV
  • 156854 05/24/08 07:14 cdaq End of Run 70500:
  • 156853 05/24/08 06:31 puckett Target snapshots--well behaved this shift
  • 156852 05/24/08 06:03 cdaq Run 70500: GEp-III high Q2, 95uA, ps1=1000 ps2=500 ps3=99999 ps4=2000, ps5=1, FPP=3.0V BigCal_thr=230mV
  • 156851 05/24/08 06:02 cdaq End of Run 70499:
  • 156850 05/24/08 04:45 cdaq Run 70499: GEp-III high Q2, 95uA, ps1=1000 ps2=500 ps3=99999 ps4=2000, ps5=1, FPP=3.0V BigCal_thr=230mV
  • 156849 05/24/08 04:44 cdaq End of Run 70498:
  • 156848 05/24/08 04:33 wpierce beam energy screenshot
  • 156847 05/24/08 03:33 cdaq Run 70498: GEp-III high Q2, 85uA, ps1=1000 ps2=500 ps3=99999 ps4=2000, ps5=1, FPP=3.0V BigCal_thr=230mV
  • 156846 05/24/08 03:33 cdaq End of Run 70497:
  • 156845 05/24/08 03:23
  • 156844 05/24/08 02:32 silviu bcm/bpm routine screen-shot
  • 156843 05/24/08 02:19 puckett asked MCC for faster ramp rate
  • 156842 05/24/08 02:03 cdaq Run 70497: GEp-III high Q2, 80uA, ps1=1000 ps2=500 ps3=99999 ps4=2000, ps5=1, FPP=3.0V BigCal_thr=230mV
  • 156841 05/24/08 02:02 cdaq End of Run 70496:
  • 156840 05/24/08 00:36 cdaq Run 70496: GEp-III high Q2, 80uA, ps1=1000 ps2=500 ps3=99999 ps4=2000, ps5=1, FPP=3.0V BigCal_thr=230mV
  • 156839 05/24/08 00:08 cdaq End of Run 70495:
  • 156838 05/24/08 00:01 cdaq Beam Time Accounting
  • 156837 05/24/08 00:00 Kumbartzki Swing shift summary
  • Friday

  • 156836 05/23/08 23:54 cdaq Run 70495: GEp-III high Q2, 80uA, ps1=1000 ps2=500 ps3=99999 ps4=2000, ps5=1, FPP=3.0V BigCal_thr=230mV
  • 156835 05/23/08 23:46 W. Luo Please check all the other groups
  • 156834 05/23/08 23:28 albayrak grup 6 HVs
  • 156833 05/23/08 23:24 narayan target routine screenshot
  • 156832 05/23/08 21:30 Kumbartzki waiting for beam
  • 156831 05/23/08 19:32 Kumbartzki still no beam
  • 156830 05/23/08 19:13 frw gate valve open again
  • 156829 05/23/08 18:40 narayan Target routine screenshot
  • 156828 05/23/08 18:13 frw downstream vacuum good
  • 156827 05/23/08 16:53 frw Beam: none for you! or: target exit valve problems
  • 156826 05/23/08 16:52 frw HMS: Q2 tripped
  • 156825 05/23/08 16:22 cdaq End of Run 70494:
  • 156824 05/23/08 16:03 cdaq Beam Time Accounting
  • 156823 05/23/08 15:58 Higinbotham Shift Summary
  • 156822 05/23/08 15:21 Higinbotham Beam Energy Numbers
  • 156821 05/23/08 15:07 cdaq Run 70494: GEp-III high Q2, 80uA, ps1=1000 ps2=500 ps3=99999 ps4=2000, ps5=1, FPP=3.0V BigCal_thr=230mV
  • 156820 05/23/08 14:56 Lassiter HMS Q2 repairs
  • 156819 05/23/08 14:43 Higinbotham Q2 Back
  • 156818 05/23/08 14:30 Nuruzzaman Routine Screen shot of Target GUI
  • 156817 05/23/08 12:43 cdaq End of Run 70493:
  • 156816 05/23/08 12:41 cdaq Run 70493: BigCal LED run
  • 156815 05/23/08 12:38 cdaq End of Run 70492:
  • 156814 05/23/08 12:36 W. Luo Load BigCal HV file hv_70030.new, calibrated with run 70458-70476
  • 156813 05/23/08 11:33 Higinbotham Controlled Access
  • 156812 05/23/08 10:17 cdaq Run 70492: GEp-III high Q2, 80uA, ps1=1000 ps2=500 ps3=99999 ps4=2000, ps5=1, FPP=3.0V BigCal_thr=230mV
  • 156811 05/23/08 10:16 cdaq End of Run 70491:
  • 156810 05/23/08 10:11 Nuruzzaman Routine Screenshot of Target GUI
  • 156809 05/23/08 08:44 cdaq Run 70491: GEp-III high Q2, 80uA, ps1=1000 ps2=500 ps3=99999 ps4=2000, ps5=1, FPP=3.0V BigCal_thr=230mV
  • 156808 05/23/08 08:43 cdaq End of Run 70490:
  • 156807 05/23/08 08:32 saw epics.dictionary changes
  • 156806 05/23/08 08:27 frw Q2 ramp rate back to nominal
  • 156805 05/23/08 08:22 Higinbotham Magnitude of Quad. Problem Changed
  • 156804 05/23/08 08:01 cdaq Beam Time Accounting
  • 156803 05/23/08 07:57 jensen owl shift summary
  • 156802 05/23/08 07:55 jensen channel plot time
  • 156801 05/23/08 07:40 jensen q2 current
  • 156800 05/23/08 07:38 Phil Carter Target: screenshot
  • 156799 05/23/08 07:22 cdaq Run 70490: GEp-III high Q2, 80uA, ps1=1000 ps2=500 ps3=99999 ps4=2000, ps5=1, FPP=3.0V BigCal_thr=230mV
  • 156798 05/23/08 06:45
  • 156797 05/23/08 06:38 cdaq Run 70489: GEp-III high Q2, 80uA, ps1=1000 ps2=500 ps3=99999 ps4=2000, ps5=1, FPP=3.0V BigCal_thr=230mV
  • 156796 05/23/08 06:36 cdaq End of Run 70488:
  • 156795 05/23/08 05:24 wpierce bcm/bpm
  • 156794 05/23/08 05:22 jensen q2 current
  • 156793 05/23/08 04:42 jensen roc13 crash
  • 156792 05/23/08 04:42 cdaq Run 70488: GEp-III high Q2, 80uA, ps1=1000 ps2=500 ps3=99999 ps4=2000, ps5=1, FPP=3.0V BigCal_thr=230mV
  • 156791 05/23/08 04:20 jensen hv trip
  • 156790 05/23/08 04:17 cdaq Run 70487: GEp-III high Q2, 80uA, ps1=1000 ps2=500 ps3=99999 ps4=2000, ps5=1, FPP=3.0V BigCal_thr=230mV
  • 156789 05/23/08 04:13 cdaq End of Run 70486:
  • 156788 05/23/08 02:53 cdaq Run 70486: GEp-III high Q2, 80uA, ps1=1000 ps2=500 ps3=99999 ps4=2000, ps5=1, FPP=3.0V BigCal_thr=230mV
  • 156787 05/23/08 02:52 jensen beam trip
  • 156786 05/23/08 02:43 cdaq End of Run 70485:
  • 156785 05/23/08 02:05 jensen beam trip
  • 156784 05/23/08 01:49 cdaq Run 70485: GEp-III high Q2, 80uA, ps1=1000 ps2=500 ps3=99999 ps4=2000, ps5=1, FPP=3.0V BigCal_thr=230mV
  • 156783 05/23/08 01:47 cdaq End of Run 70484:
  • 156782 05/23/08 01:34 jensen q2 current snapshot
  • 156781 05/23/08 01:31 jensen q2 magnet
  • 156780 05/23/08 00:15 cdaq Run 70484: GEp-III high Q2, 80uA, ps1=1000 ps2=500 ps3=99999 ps4=2000, ps5=1, FPP=3.0V BigCal_thr=230mV
  • 156779 05/23/08 00:14 cdaq End of Run 70483:
  • 156778 05/23/08 00:01 cdaq Beam Time Accounting
  • Thursday

  • 156777 05/22/08 23:59 narayan target screenshot
  • 156776 05/22/08 23:59 hamlet Swing Shift Summary, 22 May 2008
  • 156775 05/22/08 23:43 hamlet Beam and HMS Q2 during swing shift
  • 156774 05/22/08 22:47 hamlet Thanks to Andrew, replay on cdaql5 much faster.
  • 156773 05/22/08 22:46 cdaq Run 70483: GEp-III high Q2, 80uA, ps1=1000 ps2=500 ps3=99999 ps4=2000, ps5=1, FPP=3.0V BigCal_thr=230mV
  • 156772 05/22/08 22:45 cdaq End of Run 70482:
  • 156771 05/22/08 21:57 puckett try running replay on a computer other than kirby
  • 156770 05/22/08 21:21 cdaq Run 70482: GEp-III high Q2, 80uA, ps1=1000 ps2=500 ps3=99999 ps4=2000, ps5=1, FPP=3.0V BigCal_thr=230mV
  • 156769 05/22/08 21:20 cdaq End of Run 70481:
  • 156768 05/22/08 20:10 frw Not strange events
  • 156767 05/22/08 19:55 cdaq Run 70481: GEp-III high Q2, 80uA, ps1=1000 ps2=500 ps3=99999 ps4=2000, ps5=1, FPP=3.0V BigCal_thr=230mV
  • 156766 05/22/08 19:54 cdaq End of Run 70480:
  • 156765 05/22/08 19:11 hamlet Is this info from On-line replay problem ?
  • 156764 05/22/08 18:32 cdaq Run 70480: GEp-III high Q2, 80uA, ps1=1000 ps2=500 ps3=99999 ps4=2000, ps5=1, FPP=3.0V BigCal_thr=230mV
  • 156763 05/22/08 18:31 cdaq End of Run 70479:
  • 156762 05/22/08 17:27 hamlet Lost communication with HMS Dipole. NMR power cycled.
  • 156761 05/22/08 17:13 narayan routine target screenshot
  • 156760 05/22/08 17:11 hamlet Beam back with current 80 uA
  • 156759 05/22/08 17:10 cdaq Run 70479: GEp-III high Q2, 80uA, ps1=1000 ps2=500 ps3=99999 ps4=2000, ps5=1, FPP=3.0V BigCal_thr=230mV
  • 156758 05/22/08 16:44 hamlet Beam OFF since beginning of the shift, and may expect only after 30-40 min
  • 156757 05/22/08 16:07 Higinbotham Shift Summary
  • 156756 05/22/08 16:06 cdaq Beam Time Accounting
  • 156755 05/22/08 16:01 cdaq End of Run 70478:
  • 156754 05/22/08 14:35 Higinbotham Q2 Still Ramping
  • 156753 05/22/08 14:07 Higinbotham Beam Is Back!
  • 156752 05/22/08 14:02 cdaq Run 70478: GEp-III high Q2, 90uA, ps1=1000 ps2=500 ps3=99999 ps4=2000, ps5=1, FPP=3.0V BigCal_thr=230mV
  • 156751 05/22/08 11:46 M Jones Spot move was done during down
  • 156750 05/22/08 10:43 cdaq Beam Time Accounting
  • 156749 05/22/08 08:27 frw beam studies started early: NOW
  • 156748 05/22/08 08:07 cdaq End of Run 70477:
  • 156747 05/22/08 08:00 wpierce Owl Shift Summary
  • 156746 05/22/08 07:21 cdaq Run 70477: GEp-III high Q2, 90uA, ps1=1000 ps2=500 ps3=99999 ps4=2000, ps5=1, FPP=3.0V BigCal_thr=230mV
  • 156745 05/22/08 07:19 cdaq End of Run 70476:
  • 156744 05/22/08 05:53 cdaq Run 70476: GEp-III high Q2, 90uA, ps1=1000 ps2=500 ps3=99999 ps4=2000, ps5=1, FPP=3.0V BigCal_thr=230mV
  • 156743 05/22/08 05:52 cdaq End of Run 70475:
  • 156742 05/22/08 05:45 Phil Carter Target: screenshot
  • 156741 05/22/08 05:31 veilleux checklist screenshots
  • 156740 05/22/08 05:14
  • 156739 05/22/08 04:18 cdaq Run 70475: GEp-III high Q2, 90uA, ps1=1000 ps2=500 ps3=99999 ps4=2000, ps5=1, FPP=3.0V BigCal_thr=230mV
  • 156738 05/22/08 04:17 cdaq End of Run 70474:
  • 156737 05/22/08 04:13 wpierce Q2 field drop
  • 156736 05/22/08 02:31 cdaq Run 70474: GEp-III high Q2, 75uA, ps1=1000 ps2=500 ps3=99999 ps4=2000, ps5=1, FPP=3.0V BigCal_thr=230mV
  • 156735 05/22/08 02:30 cdaq End of Run 70473:
  • 156734 05/22/08 00:46 cdaq Run 70473: GEp-III high Q2, 75uA, ps1=1000 ps2=500 ps3=99999 ps4=2000, ps5=1, FPP=3.0V BigCal_thr=230mV
  • 156733 05/22/08 00:44 cdaq End of Run 70472:
  • 156732 05/22/08 00:02 cdaq Beam Time Accounting
  • Wednesday

  • 156731 05/21/08 23:59 hamlet Swing Shift Summary, 21 May 2008
  • 156730 05/21/08 23:13 hamlet Beam back. Resumed data taking
  • 156729 05/21/08 23:12 cdaq Run 70472: GEp-III high Q2, 70uA, ps1=1000 ps2=500 ps3=99999 ps4=2000, ps5=1, FPP=3.0V BigCal_thr=230mV
  • 156728 05/21/08 22:39 hamlet Beam OFF due to BPM IOC problem
  • 156727 05/21/08 22:32 cdaq End of Run 70471:
  • 156726 05/21/08 22:14 cdaq Run 70471: GEp-III high Q2, 70uA, ps1=1000 ps2=500 ps3=99999 ps4=2000, ps5=1, FPP=3.0V BigCal_thr=230mV
  • 156725 05/21/08 22:07 cdaq End of Run 70470:
  • 156724 05/21/08 20:54 cdaq Run 70470: GEp-III high Q2, 70uA, ps1=1000 ps2=500 ps3=99999 ps4=2000, ps5=1, FPP=3.0V BigCal_thr=230mV
  • 156723 05/21/08 20:51 cdaq End of Run 70469:
  • 156722 05/21/08 20:30 Abdellah Target Snapshot
  • 156721 05/21/08 20:11 hamlet Continuing run 70469, beam current now up to 70 uA
  • 156720 05/21/08 19:02 Abdellah Target IOC rebooted
  • 156719 05/21/08 19:02 cdaq Run 70469: GEp-III high Q2, 30uA, ps1=1000 ps2=500 ps3=99999 ps4=2000, ps5=1, FPP=3.0V BigCal_thr=230mV
  • 156718 05/21/08 18:55 cdaq End of Run 70468:
  • 156717 05/21/08 18:21 hamlet Actual beam current only 35 uA
  • 156716 05/21/08 17:38 hamlet Beam current about 50 uA.
  • 156715 05/21/08 17:35 cdaq Run 70468: GEp-III high Q2, 30uA, ps1=1000 ps2=500 ps3=99999 ps4=2000, ps5=1, FPP=3.0V BigCal_thr=230mV
  • 156714 05/21/08 17:19 hamlet Beam OFF. Expected down time 40 min
  • 156713 05/21/08 17:11 cdaq End of Run 70467:
  • 156712 05/21/08 16:55 hamlet Beam back, but current only 30 uA
  • 156711 05/21/08 16:40 hamlet Beam OFF since 16:10
  • 156710 05/21/08 16:10 Higinbotham Day Shift Run List
  • 156709 05/21/08 16:07 cdaq Run 70467: GEp-III high Q2, 80uA, ps1=1000 ps2=500 ps3=99999 ps4=2000, ps5=1, FPP=3.0V BigCal_thr=230mV
  • 156708 05/21/08 16:07 cdaq Beam Time Accounting
  • 156707 05/21/08 16:04 Higinbotham Shift Summary
  • 156706 05/21/08 14:13 cdaq End of Run 70466:
  • 156705 05/21/08 13:34 Higinbotham Lower Beam Current
  • 156704 05/21/08 12:36 cdaq Run 70466: GEp-III high Q2, 80uA, ps1=1000 ps2=500 ps3=99999 ps4=2000, ps5=1, FPP=3.0V BigCal_thr=230mV
  • 156703 05/21/08 12:34 cdaq End of Run 70465:
  • 156702 05/21/08 12:15 smithg Target: Target status
  • 156701 05/21/08 11:00 smithg Target: fan trip
  • 156700 05/21/08 10:58 cdaq Run 70465: GEp-III high Q2, 90uA, ps1=1000 ps2=500 ps3=99999 ps4=2000, ps5=1, FPP=3.0V BigCal_thr=230mV
  • 156699 05/21/08 10:57 cdaq End of Run 70464:
  • 156698 05/21/08 09:04 cdaq Run 70464: GEp-III high Q2, 90uA, ps1=1000 ps2=500 ps3=99999 ps4=2000, ps5=1, FPP=3.0V BigCal_thr=230mV
  • 156697 05/21/08 08:49 cdaq End of Run 70463:
  • 156696 05/21/08 08:35 smithg Fan status lights
  • 156695 05/21/08 08:30 cdaq Run 70463: GEp-III high Q2, 90uA, ps1=1000 ps2=500 ps3=99999 ps4=2000, ps5=1, FPP=3.0V BigCal_thr=230mV
  • 156694 05/21/08 08:16 cdaq End of Run 70462:
  • 156693 05/21/08 08:13 M Jones Q2 has regular dips in current at 1x10^-3 level
  • 156692 05/21/08 08:01 cdaq Beam Time Accounting
  • 156691 05/21/08 07:56 wpierce Owl Shift Summary
  • 156690 05/21/08 07:47 cdaq Run 70462: GEp-III high Q2, 90uA, ps1=1000 ps2=500 ps3=99999 ps4=2000, ps5=1, FPP=3.0V BigCal_thr=230mV
  • 156689 05/21/08 07:40 cdaq End of Run 70461:
  • 156688 05/21/08 06:24 veilleux Checklist screenshots
  • 156687 05/21/08 06:23 cdaq Run 70461: GEp-III high Q2, 90uA, ps1=1000 ps2=500 ps3=99999 ps4=2000, ps5=1, FPP=3.0V BigCal_thr=230mV
  • 156686 05/21/08 06:21 cdaq End of Run 70460:
  • 156685 05/21/08 05:28 wpierce variable beam current
  • 156684 05/21/08 05:18
  • 156683 05/21/08 04:51 cdaq Run 70460: GEp-III high Q2, 75uA, ps1=1000 ps2=500 ps3=99999 ps4=2000, ps5=1, FPP=3.0V BigCal_thr=230mV
  • 156682 05/21/08 04:45 cdaq End of Run 70459:
  • 156681 05/21/08 02:47 Phil Carter Target: screenshot
  • 156680 05/21/08 02:02 Phil Carter Target: IOC reboot
  • 156679 05/21/08 01:49 cdaq Run 70459: GEp-III high Q2, 40uA, ps1=1000 ps2=500 ps3=99999 ps4=2000, ps5=1, FPP=3.0V BigCal_thr=230mV
  • 156678 05/21/08 01:49 wpierce roc 13
  • 156677 05/21/08 01:11 veilleux plots don't match golden run
  • 156676 05/21/08 00:54 wpierce we're back on
  • 156675 05/21/08 00:50 cdaq Run 70458: GEp-III high Q2, 40uA, ps1=1000 ps2=500 ps3=99999 ps4=2000, ps5=1, FPP=3.0V BigCal_thr=230mV
  • 156674 05/21/08 00:00 cdaq Beam Time Accounting
  • Tuesday

  • 156673 05/20/08 23:56 Abdellah Swing Shift Summary
  • 156672 05/20/08 22:57 Abdellah Beam off
  • 156671 05/20/08 22:55 cdaq End of Run 70457:
  • 156670 05/20/08 21:55 cdaq Run 70457: GEp-III high Q2, 90uA, ps1=1000 ps2=500 ps3=99999 ps4=2000, ps5=1, FPP=3.0V BigCal_thr=230mV
  • 156669 05/20/08 21:55 cdaq End of Run 70456:
  • 156668 05/20/08 20:43 Arthur DAQ show 0 0 events/s
  • 156667 05/20/08 20:38 cdaq Run 70456: GEp-III high Q2, 90uA, ps1=1000 ps2=500 ps3=99999 ps4=2000, ps5=1, FPP=3.0V BigCal_thr=230mV
  • 156666 05/20/08 20:33 cdaq Run 70455: GEp-III high Q2, 90uA, ps1=1000 ps2=500 ps3=99999 ps4=2000, ps5=1, FPP=3.0V BigCal_thr=230mV
  • 156665 05/20/08 19:25 cdaq Run 70454: GEp-III high Q2, 90uA, ps1=1000 ps2=500 ps3=99999 ps4=2000, ps5=1, FPP=3.0V BigCal_thr=230mV
  • 156664 05/20/08 19:23 jinhuang Target: IOC reboot
  • 156663 05/20/08 19:13 cdaq End of Run 70452:
  • 156662 05/20/08 18:55 cdaq Run 70452: GEp-III high Q2, 90uA, ps1=1000 ps2=500 ps3=99999 ps4=2000, ps5=1, FPP=3.0V BigCal_thr=230mV
  • 156661 05/20/08 18:06 cdaq Run 70451: GEp-III high Q2, 90uA, ps1=1000 ps2=500 ps3=99999 ps4=2000, ps5=1, FPP=3.0V BigCal_thr=230mV
  • 156660 05/20/08 17:30 cdaq End of Run 70450:
  • 156659 05/20/08 16:44 jinhuang Target: ScreenShot @ 0uA
  • 156658 05/20/08 16:00 cdaq Beam Time Accounting
  • 156657 05/20/08 16:00 frw Q2 instablility -- shift crew instructions
  • 156656 05/20/08 15:52 Higinbotham Shift Summary
  • 156655 05/20/08 15:22 W. Luo BigCal status after controlled access
  • 156654 05/20/08 15:11 hamlet "Bender prototype" installed around pivot
  • 156653 05/20/08 14:52 Nuruzzaman Routine screen shot of Target GUI
  • 156652 05/20/08 14:49 L. Zhu Q2 unstable
  • 156651 05/20/08 14:47 cdaq Run 70450: GEp-III high Q2, 80uA, ps1=1000 ps2=500 ps3=99999 ps4=2000, ps5=1, FPP=3.0V BigCal_thr=230mV
  • 156650 05/20/08 11:49 cdaq End of Run 70449:
  • 156649 05/20/08 11:49 cdaq Run 70449: cosmic
  • 156648 05/20/08 11:47 frw horizontal bender installed
  • 156647 05/20/08 11:44 cdaq End of Run 70448:
  • 156646 05/20/08 11:38 W. Luo Replaced a 2nd level sum module on BigCal platform
  • 156645 05/20/08 11:26 frw controlled access
  • 156644 05/20/08 11:19 cdaq Run 70448: cosmic
  • 156643 05/20/08 11:16 cdaq End of Run 70447:
  • 156642 05/20/08 11:14 cdaq Run 70447: BigCal LED run
  • 156641 05/20/08 11:14 M Jones Fixed ROC11 remote reboot, now it works
  • 156640 05/20/08 10:40 Nuruzzaman Routine Screen shot of Target GUI
  • 156639 05/20/08 09:54 cdaq End of Run 70446:
  • 156638 05/20/08 09:52 cdaq Run 70446: BigCal LED run
  • 156637 05/20/08 09:09 cdaq End of Run 70445:
  • 156636 05/20/08 08:38 cdaq Run 70445: GEp-III high Q2, 80uA, ps1=1000 ps2=500 ps3=99999 ps4=2000, ps5=1, FPP=3.0V BigCal_thr=230mV
  • 156635 05/20/08 08:08 Dutta Owl shift summary
  • 156634 05/20/08 08:07 cdaq Beam Time Accounting
  • 156633 05/20/08 07:46 Phil Carter Target: screenshot
  • 156632 05/20/08 07:08 Phil Carter Target: fan died, recovered without reboot
  • 156631 05/20/08 06:40
  • 156630 05/20/08 06:24 veilleux checklist screenshots
  • 156629 05/20/08 04:58 Dutta Beam: ROC 13 crash
  • 156628 05/20/08 04:56 Dutta Beam: No beam
  • 156627 05/20/08 03:16 cdaq End of Run 70444:
  • 156626 05/20/08 02:29 cdaq Run 70444: GEp-III high Q2, 80uA, ps1=1000 ps2=500 ps3=99999 ps4=2000, ps5=1, FPP=3.0V BigCal_thr=230mV
  • 156625 05/20/08 01:33 Dutta Bigcal Display
  • 156624 05/20/08 01:27 cdaq Run 70443: GEp-III high Q2, 80uA, ps1=1000 ps2=500 ps3=99999 ps4=2000, ps5=1, FPP=3.0V BigCal_thr=230mV
  • 156623 05/20/08 01:26 cdaq End of Run 70442:
  • 156622 05/20/08 00:04 cdaq Beam Time Accounting
  • 156621 05/20/08 00:03 silviu swing shift summary
  • 156620 05/20/08 00:03 cdaq Run 70442: GEp-III high Q2, 80uA, ps1=1000 ps2=500 ps3=99999 ps4=2000, ps5=1, FPP=3.0V BigCal_thr=230mV
  • 156619 05/20/08 00:02 cdaq End of Run 70441:
  • Monday

  • 156618 05/19/08 23:47 narayan routine target screenshot
  • 156617 05/19/08 22:33 cdaq Run 70441: GEp-III high Q2, 90uA, ps1=1000 ps2=500 ps3=99999 ps4=2000, ps5=1, FPP=3.0V BigCal_thr=230mV
  • 156616 05/19/08 22:31 cdaq End of Run 70440:
  • 156615 05/19/08 22:06 jinhuang Run Check List (May18 swing to May 19 swing)
  • 156614 05/19/08 21:29 jinhuang BCM & BPM ScreenShot
  • 156613 05/19/08 21:20 cdaq Run 70440: GEp-III high Q2, 90uA, ps1=1000 ps2=500 ps3=99999 ps4=2000, ps5=1, FPP=3.0V BigCal_thr=230mV
  • 156612 05/19/08 21:18 cdaq End of Run 70439:
  • 156611 05/19/08 20:06 cdaq Run 70439: GEp-III high Q2, 90uA, ps1=1000 ps2=500 ps3=99999 ps4=2000, ps5=1, FPP=3.0V BigCal_thr=230mV
  • 156610 05/19/08 20:04 cdaq End of Run 70438:
  • 156609 05/19/08 19:07 narayan Target: beam current increased to 90
  • 156608 05/19/08 18:53 cdaq Run 70438: GEp-III high Q2, 85uA, ps1=1000 ps2=500 ps3=99999 ps4=2000, ps5=1, FPP=3.0V BigCal_thr=230mV
  • 156607 05/19/08 18:52 cdaq End of Run 70437:
  • 156606 05/19/08 17:36 cdaq Run 70437: GEp-III high Q2, 80uA, ps1=1000 ps2=500 ps3=99999 ps4=2000, ps5=1, FPP=3.0V BigCal_thr=230mV
  • 156605 05/19/08 17:24 NARAYAN Target: Beam Started at 85 muA
  • 156604 05/19/08 16:37 horn Moller summary
  • 156603 05/19/08 16:27 horn Moller done
  • 156602 05/19/08 16:10 cdaq End of Run 70436:
  • 156601 05/19/08 16:10 cdaq Moller Run 70436: HWP=IN, Wien angle=-13.53 deg
  • 156600 05/19/08 16:06 cdaq End of Run 70435:
  • 156599 05/19/08 16:02 cdaq Beam Time Accounting
  • 156598 05/19/08 15:58 Higinbotham Shift Summary
  • 156597 05/19/08 15:54 cdaq Moller Run 70435: HWP=IN, Wien angle=-13.53 deg
  • 156596 05/19/08 15:54 cdaq End of Run 70434:
  • 156595 05/19/08 15:51 cdaq Moller Run 70434: HWP=IN, Wien angle=-13.53 deg
  • 156594 05/19/08 15:49 cdaq End of Run 70433:
  • 156593 05/19/08 15:45 Nuruzzaman Heater power variation for the shift
  • 156592 05/19/08 15:38 Nuruzzaman Routine Target Screenshot
  • 156591 05/19/08 15:35 cdaq Moller Run 70433: HWP=IN, Wien angle=-13.53 deg
  • 156590 05/19/08 15:34 cdaq End of Run 70432:
  • 156589 05/19/08 15:18 cdaq Moller Run 70432: HWP=IN, Wien angle=-13.53 deg
  • 156588 05/19/08 15:10 cdaq End of Run 70431:
  • 156587 05/19/08 15:08 cdaq Moller Run 70431: HWP=IN, Wien angle=-13.53 deg
  • 156586 05/19/08 14:10 cdaq End of Run 70430:
  • 156585 05/19/08 14:09 cdaq Moller Run 70430: DAQ test
  • 156584 05/19/08 13:35 Nuruzzaman Target moved to empty position
  • 156583 05/19/08 13:32 horn Start Moller setup
  • 156582 05/19/08 13:22 cdaq End of Run 70429:
  • 156581 05/19/08 13:04 Higinbotham Back to 85 uA
  • 156580 05/19/08 13:02 Nuruzzaman Target GUI lost connection for a moment
  • 156579 05/19/08 12:51 cdaq Run 70429: GEp-III high Q2, 80uA, ps1=1000 ps2=500 ps3=99999 ps4=2000, ps5=1, FPP=3.0V BigCal_thr=230mV
  • 156578 05/19/08 12:49 cdaq End of Run 70428:
  • 156577 05/19/08 12:41 Nuruzzaman Fans are OK now
  • 156576 05/19/08 12:37 Nuruzzaman Cryo flow of Hall-C & Hall-A
  • 156575 05/19/08 12:21 Higinbotham Current to 90 uA
  • 156574 05/19/08 11:35 Higinbotham HV Problem End of 70427
  • 156573 05/19/08 11:33 reinhold hctsv12:2003 HV alarm during run 70427
  • 156572 05/19/08 11:33 cdaq Run 70428: GEp-III high Q2, 80uA, ps1=1000 ps2=500 ps3=99999 ps4=2000, ps5=1, FPP=3.0V BigCal_thr=230mV
  • 156571 05/19/08 11:31 cdaq End of Run 70427:
  • 156570 05/19/08 10:39 cdaq Run 70427: GEp-III high Q2, 85uA, ps1=1000 ps2=500 ps3=99999 ps4=2000, ps5=1, FPP=3.0V BigCal_thr=230mV
  • 156569 05/19/08 10:37 reinhold MCC call: will send beam again
  • 156568 05/19/08 10:26 cdaq End of Run 70426:
  • 156567 05/19/08 10:26 cdaq Run 70426: GEp-III high Q2, 85uA, ps1=1000 ps2=500 ps3=99999 ps4=2000, ps5=1, FPP=3.0V BigCal_thr=230mV
  • 156566 05/19/08 10:25 reinhold MCC stops beam to look at machine
  • 156565 05/19/08 10:18 cdaq End of Run 70425:
  • 156564 05/19/08 09:27 Phil Carter Target: moved back to 20cm LH2 (a couple hours ago -- old news)
  • 156563 05/19/08 09:15 Nuruzzaman Routine Screenshot of Target GUI
  • 156562 05/19/08 08:59 Bosted Target: Fans for loop 2 and 3
  • 156561 05/19/08 08:53 Bosted Target: Why target still at 20K instead of 19 K
  • 156560 05/19/08 08:51 Bosted Target: Why target still at 20K instead of 19 K
  • 156559 05/19/08 08:51 cdaq Run 70425: GEp-III high Q2, 80uA, ps1=1000 ps2=500 ps3=99999 ps4=2000, ps5=1, FPP=3.0V BigCal_thr=230mV
  • 156558 05/19/08 08:33 cdaq End of Run 70424:
  • 156557 05/19/08 08:22 reinhold MCC takes beam for tuning
  • 156556 05/19/08 08:21 reinhold MCC call: will soon take beam for tuning
  • 156555 05/19/08 08:08 cdaq Beam Time Accounting
  • 156554 05/19/08 07:59 Dutta Owl shift summary
  • 156553 05/19/08 07:46 cdaq Run 70424: GEp-III high Q2, 80uA, ps1=1000 ps2=500 ps3=99999 ps4=2000, ps5=1, FPP=3.0V BigCal_thr=230mV
  • 156552 05/19/08 07:40 cdaq End of Run 70423:
  • 156551 05/19/08 07:12 Phil Carter Target: heater overcorrecting again
  • 156550 05/19/08 06:49 cdaq Run 70423: GEp-III high Q2, 80uA, ps1=1000 ps2=500 ps3=99999 ps4=2000, ps5=1, FPP=3.0V BigCal_thr=230mV
  • 156549 05/19/08 06:40 Phil Target: do we still need a 20 K target?
  • 156548 05/19/08 06:25 Phil Carter Target: fan died, IOC reboot, boiled, recovered
  • 156547 05/19/08 06:24 Dutta Vacuum work completed
  • 156546 05/19/08 05:17 yan FR ceramic pipe
  • 156545 05/19/08 05:14
  • 156544 05/19/08 04:40 yan FR vacuum leakage
  • 156543 05/19/08 04:23 Dutta vacuum leak
  • 156542 05/19/08 03:54 Dutta Leak at raster
  • 156541 05/19/08 00:59 Phil Carter Target: 15 K flow
  • 156540 05/19/08 00:33 Phil Carter Target: heater power oscillating
  • 156539 05/19/08 00:00 cdaq Beam Time Accounting
  • Sunday

  • 156538 05/18/08 23:55 ent swing shift summary
  • 156537 05/18/08 23:44 horn still vacuum problems - no Moller tonight
  • 156536 05/18/08 23:37 ent vacuum update - waiting for ATLIS
  • 156535 05/18/08 22:03 narayan BPM/BCM routine screenshot
  • 156534 05/18/08 21:13 narayan Target: FAN stopped and subsequent steps
  • 156533 05/18/08 19:52 horn Vacuum problems
  • 156532 05/18/08 19:19 narayan Target: IOC reboot
  • 156531 05/18/08 18:12 narayan Target: routine screenshot, Moller measurement in progress
  • 156530 05/18/08 17:23 cdaq End of Run 70422:
  • 156529 05/18/08 17:23 cdaq Moller Run 70422: Moller DAQ test
  • 156528 05/18/08 17:09 cdaq End of Run 70421:
  • 156527 05/18/08 16:05 cdaq Beam Time Accounting
  • 156526 05/18/08 16:04 Reinhold Shift Summary Day Shift
  • 156525 05/18/08 15:58 Bosted Target screens
  • 156524 05/18/08 15:52 cdaq Run 70421: GEp-III high Q2, 80uA, ps1=1000 ps2=500 ps3=99999 ps4=2000, ps5=1, FPP=3.0V BigCal_thr=230mV
  • 156523 05/18/08 15:50 cdaq End of Run 70420:
  • 156522 05/18/08 14:32 cdaq Run 70420: GEp-III high Q2, 80uA, ps1=1000 ps2=500 ps3=99999 ps4=2000, ps5=1, FPP=3.0V BigCal_thr=230mV
  • 156521 05/18/08 14:31 cdaq End of Run 70419:
  • 156520 05/18/08 14:22 cdaq Run 70419: GEp-III high Q2, 80uA, ps1=1000 ps2=500 ps3=99999 ps4=2000, ps5=1, FPP=3.0V BigCal_thr=230mV
  • 156519 05/18/08 14:21 cdaq End of Run 70418:
  • 156518 05/18/08 13:23 frw Re: Questions about run sheet
  • 156517 05/18/08 13:09 W. Luo The question about run sheet
  • 156516 05/18/08 12:56 cdaq Run 70418: GEp-III high Q2, 80uA, ps1=1000 ps2=500 ps3=99999 ps4=2000, ps5=1, FPP=3.0V BigCal_thr=230mV
  • 156515 05/18/08 12:55 cdaq End of Run 70417:
  • 156514 05/18/08 11:21 cdaq Run 70417: GEp-III high Q2, 80uA, ps1=1000 ps2=500 ps3=99999 ps4=2000, ps5=1, FPP=3.0V BigCal_thr=230mV
  • 156513 05/18/08 11:19 cdaq End of Run 70416:
  • 156512 05/18/08 10:56 Reinhold Questions about run sheet
  • 156511 05/18/08 10:00 cdaq Run 70416: GEp-III high Q2, 80uA, ps1=1000 ps2=500 ps3=99999 ps4=2000, ps5=1, FPP=3.0V BigCal_thr=230mV
  • 156510 05/18/08 09:59 cdaq End of Run 70415:
  • 156509 05/18/08 08:51 reinhold BPM and BCM screen shots
  • 156508 05/18/08 08:48 Reinhold Beam was fine
  • 156507 05/18/08 08:35 cdaq Run 70415: GEp-III high Q2, 80uA, ps1=1000 ps2=500 ps3=99999 ps4=2000, ps5=1, FPP=3.0V BigCal_thr=230mV
  • 156506 05/18/08 08:32 reinhold MCC adjusts beam in pulsed mode
  • 156505 05/18/08 08:30 reinhold Taget IOC reboot
  • 156504 05/18/08 08:29 Bosted Target: Reboot IOC
  • 156503 05/18/08 08:26 cdaq End of Run 70414:
  • 156502 05/18/08 08:03 cdaq Beam Time Accounting
  • 156501 05/18/08 07:58 Dutta Owl shift summary
  • 156500 05/18/08 07:41 Nuruzzaman 15k Cryo flow
  • 156499 05/18/08 07:38 Nuruzzaman Heater Power Variation
  • 156498 05/18/08 06:44 cdaq Run 70414: GEp-III high Q2, 80uA, ps1=1000 ps2=500 ps3=99999 ps4=2000, ps5=1, FPP=3.0V BigCal_thr=230mV
  • 156497 05/18/08 06:43 cdaq End of Run 70413:
  • 156496 05/18/08 06:08 Nuruzzaman Routine Target Snapshot
  • 156495 05/18/08 05:22 cdaq Run 70413: GEp-III high Q2, 80uA, ps1=1000 ps2=500 ps3=99999 ps4=2000, ps5=1, FPP=3.0V BigCal_thr=230mV
  • 156494 05/18/08 05:21 cdaq End of Run 70412:
  • 156493 05/18/08 05:14
  • 156492 05/18/08 04:24 wpierce bcm and bpm screenshots
  • 156491 05/18/08 04:03 cdaq Run 70412: GEp-III high Q2, 80uA, ps1=1000 ps2=500 ps3=99999 ps4=2000, ps5=1, FPP=3.0V BigCal_thr=230mV
  • 156490 05/18/08 04:02 cdaq End of Run 70411:
  • 156489 05/18/08 02:45 cdaq Run 70411: GEp-III high Q2, 80uA, ps1=1000 ps2=500 ps3=99999 ps4=2000, ps5=1, FPP=3.0V BigCal_thr=230mV
  • 156488 05/18/08 02:44 cdaq End of Run 70410:
  • 156487 05/18/08 01:45 Nuruzzaman JT Valve doesn't showing any value in target GUI
  • 156486 05/18/08 01:23 cdaq Run 70410: GEp-III high Q2, 80uA, ps1=1000 ps2=500 ps3=99999 ps4=2000, ps5=1, FPP=3.0V BigCal_thr=230mV
  • 156485 05/18/08 01:22 cdaq End of Run 70409:
  • 156484 05/18/08 01:14 Nuruzzaman Screenhsot of target GUI
  • 156483 05/18/08 00:11 Nuruzzaman IOC rebooted
  • 156482 05/18/08 00:02 ent swing shift summary
  • 156481 05/18/08 00:02 cdaq Beam Time Accounting
  • Saturday

  • 156480 05/17/08 23:55 cdaq Run 70409: GEp-III high Q2, 80uA, ps1=1000 ps2=500 ps3=99999 ps4=2000, ps5=1, FPP=3.0V BigCal_thr=230mV
  • 156479 05/17/08 23:54 cdaq End of Run 70408:
  • 156478 05/17/08 23:24 narayan Target: routine screenshot
  • 156477 05/17/08 22:39 ent NMR lock back
  • 156476 05/17/08 22:35 cdaq Run 70408: GEp-III high Q2, 80uA, ps1=1000 ps2=500 ps3=99999 ps4=2000, ps5=1, FPP=3.0V BigCal_thr=230mV
  • 156475 05/17/08 21:56 ent HMS dipole communication alarm
  • 156474 05/17/08 21:54 Huber BPM plots
  • 156473 05/17/08 21:06 cdaq End of Run 70407:
  • 156472 05/17/08 20:06 cdaq Run 70407: GEp-III high Q2, 80uA, ps1=1000 ps2=500 ps3=99999 ps4=2000, ps5=1, FPP=3.0V BigCal_thr=230mV
  • 156471 05/17/08 20:05 cdaq End of Run 70406:
  • 156470 05/17/08 18:47 cdaq Run 70406: GEp-III high Q2, 80uA, ps1=1000 ps2=500 ps3=99999 ps4=2000, ps5=1, FPP=3.0V BigCal_thr=230mV
  • 156469 05/17/08 18:46 cdaq End of Run 70405:
  • 156468 05/17/08 17:29 cdaq Run 70405: GEp-III high Q2, 85uA, ps1=1000 ps2=500 ps3=99999 ps4=2000, ps5=1, FPP=3.0V BigCal_thr=230mV
  • 156467 05/17/08 17:23 narayan Target: IOC reboot
  • 156466 05/17/08 17:09 cdaq End of Run 70404:
  • 156465 05/17/08 16:49 cdaq Run 70404: GEp-III high Q2, 85uA, ps1=1000 ps2=500 ps3=99999 ps4=2000, ps5=1, FPP=3.0V BigCal_thr=230mV
  • 156464 05/17/08 16:48 cdaq End of Run 70403:
  • 156463 05/17/08 16:33 narayan Target: swing shift, routine target screenshot
  • 156462 05/17/08 16:01 cdaq Beam Time Accounting
  • 156461 05/17/08 15:52 Ransome Day shift summary
  • 156460 05/17/08 15:22 cdaq Run 70403: GEp-III high Q2, 85uA, ps1=1000 ps2=500 ps3=99999 ps4=2000, ps5=1, FPP=3.0V BigCal_thr=230mV
  • 156459 05/17/08 15:21 cdaq End of Run 70402:
  • 156458 05/17/08 14:51 w. Luo 37CD get bad again
  • 156457 05/17/08 14:04 cdaq Run 70402: GEp-III high Q2, 85uA, ps1=1000 ps2=500 ps3=99999 ps4=2000, ps5=1, FPP=3.0V BigCal_thr=230mV
  • 156456 05/17/08 14:03 cdaq End of Run 70401:
  • 156455 05/17/08 14:01 ransome beam position screens
  • 156454 05/17/08 13:36 Ransome current reduction
  • 156453 05/17/08 12:35 cdaq Run 70401: GEp-III high Q2, 85uA, ps1=1000 ps2=500 ps3=99999 ps4=2000, ps5=1, FPP=3.0V BigCal_thr=230mV
  • 156452 05/17/08 12:32 cdaq End of Run 70400:
  • 156451 05/17/08 11:24 cdaq Run 70400: GEp-III high Q2, 85uA, ps1=1000 ps2=500 ps3=99999 ps4=2000, ps5=1, FPP=3.0V BigCal_thr=230mV
  • 156450 05/17/08 11:21 adaniel Target: IOC reboot
  • 156449 05/17/08 11:15 Ransome target/DAQ problems
  • 156448 05/17/08 11:12 ransome spot change
  • 156447 05/17/08 11:10 cdaq End of Run 70399:
  • 156446 05/17/08 10:48 cdaq Run 70399: GEp-III high Q2, 85uA, ps1=1000 ps2=500 ps3=99999 ps4=2000, ps5=1, FPP=3.0V BigCal_thr=230mV
  • 156445 05/17/08 10:46 cdaq End of Run 70398:
  • 156444 05/17/08 10:09 adaniel Target: Screen shot of fan controls
  • 156443 05/17/08 09:42 adaniel Target: fan died
  • 156442 05/17/08 09:28 Ransome Wein angle
  • 156441 05/17/08 09:06 cdaq Run 70398: GEp-III high Q2, 85uA, ps1=1000 ps2=500 ps3=99999 ps4=2000, ps5=1, FPP=3.0V BigCal_thr=230mV
  • 156440 05/17/08 08:59 cdaq Run 70397: GEp-III high Q2, 85uA, ps1=1000 ps2=500 ps3=99999 ps4=2000, ps5=1, FPP=3.0V BigCal_thr=230mV
  • 156439 05/17/08 08:13 cdaq End of Run 70396:
  • 156438 05/17/08 08:05 cdaq Beam Time Accounting
  • 156437 05/17/08 08:03 adaniel Target: screen shot
  • 156436 05/17/08 07:46 Dutta Owl shift summary
  • 156435 05/17/08 07:46 Nuruzzaman Heater power variation during the shift
  • 156434 05/17/08 07:40 cdaq Run 70396: GEp-III high Q2, 95uA, ps1=1000 ps2=500 ps3=99999 ps4=2000, ps5=1, FPP=3.0V BigCal_thr=230mV
  • 156433 05/17/08 07:39 cdaq End of Run 70395:
  • 156432 05/17/08 06:53 Nuruzzaman JT Valve opned by one step
  • 156431 05/17/08 06:35 Dutta HMS NMR finally locks
  • 156430 05/17/08 06:34 cdaq Run 70395: GEp-III high Q2, 85uA, ps1=1000 ps2=500 ps3=99999 ps4=2000, ps5=1, FPP=3.0V BigCal_thr=230mV
  • 156429 05/17/08 06:31 Dutta HMS dipole
  • 156428 05/17/08 05:56 Nuruzzaman Target Screenshot
  • 156427 05/17/08 05:14
  • 156426 05/17/08 05:01 Dutta HMS NMR lock
  • 156425 05/17/08 04:51 Phil Carter bpm and bcm screenshots
  • 156424 05/17/08 04:46 cdaq End of Run 70394:
  • 156423 05/17/08 03:34 Dutta HMS Dipole comm. error
  • 156422 05/17/08 03:29 cdaq Run 70394: GEp-III high Q2, 80uA, ps1=1000 ps2=500 ps3=99999 ps4=2000, ps5=1, FPP=3.0V BigCal_thr=230mV
  • 156421 05/17/08 03:18 cdaq End of Run 70393:
  • 156420 05/17/08 02:28 cdaq Run 70393: GEp-III high Q2, 80uA, ps1=1000 ps2=500 ps3=99999 ps4=2000, ps5=1, FPP=3.0V BigCal_thr=230mV
  • 156419 05/17/08 02:27 cdaq End of Run 70392:
  • 156418 05/17/08 01:28 Nuruzzaman Screenshot of Cryo flow
  • 156417 05/17/08 01:10 cdaq Run 70392: GEp-III high Q2, 80uA, ps1=1000 ps2=500 ps3=99999 ps4=2000, ps5=1, FPP=3.0V BigCal_thr=230mV
  • 156416 05/17/08 01:10 Nuruzzaman Target Screenshot
  • 156415 05/17/08 01:08 cdaq End of Run 70391:
  • 156414 05/17/08 00:01 ent swing shift summary
  • 156413 05/17/08 00:01 cdaq Beam Time Accounting
  • Friday

  • 156412 05/16/08 23:53 cdaq Run 70391: GEp-III high Q2, 85uA, ps1=1000 ps2=500 ps3=99999 ps4=2000, ps5=1, FPP=3.0V BigCal_thr=230mV
  • 156411 05/16/08 23:52 cdaq End of Run 70390:
  • 156410 05/16/08 22:35 cdaq Run 70390: GEp-III high Q2, 85uA, ps1=1000 ps2=500 ps3=99999 ps4=2000, ps5=1, FPP=3.0V BigCal_thr=230mV
  • 156409 05/16/08 22:34 cdaq End of Run 70389:
  • 156408 05/16/08 21:21 cdaq Run 70389: GEp-III high Q2, 85uA, ps1=1000 ps2=500 ps3=99999 ps4=2000, ps5=1, FPP=3.0V BigCal_thr=230mV
  • 156407 05/16/08 21:20 cdaq End of Run 70388:
  • 156406 05/16/08 20:54 horn Target: Screen shot
  • 156405 05/16/08 20:07 cdaq Run 70388: GEp-III high Q2, 100uA, ps1=1000 ps2=500 ps3=99999 ps4=2000, ps5=1, FPP=3.0V BigCal_thr=230mV
  • 156404 05/16/08 20:06 cdaq End of Run 70387:
  • 156403 05/16/08 18:58 cdaq Run 70387: GEp-III high Q2, 100uA, ps1=1000 ps2=500 ps3=99999 ps4=2000, ps5=1, FPP=3.0V BigCal_thr=230mV
  • 156402 05/16/08 18:55 cdaq End of Run 70386:
  • 156401 05/16/08 17:23 cdaq Run 70386: GEp-III high Q2, 100uA, ps1=1000 ps2=500 ps3=99999 ps4=2000, ps5=1, FPP=3.0V BigCal_thr=230mV
  • 156400 05/16/08 16:58 cdaq End of Run 70385:
  • 156399 05/16/08 16:17 cdaq Run 70385: GEp-III high Q2, 100uA, ps1=1000 ps2=500 ps3=99999 ps4=2000, ps5=1, FPP=3.0V BigCal_thr=230mV
  • 156398 05/16/08 16:16 cdaq End of Run 70384:
  • 156397 05/16/08 16:01 cdaq Beam Time Accounting
  • 156396 05/16/08 15:59 Keppel day shift summary
  • 156395 05/16/08 15:54 Ransome target: screens
  • 156394 05/16/08 15:51 Ransome target: day shift
  • 156393 05/16/08 15:28 Huber BPM medm screens
  • 156391 05/16/08 14:59 cdaq Run 70384: GEp-III high Q2, 100uA, ps1=1000 ps2=500 ps3=99999 ps4=2000, ps5=1, FPP=3.0V BigCal_thr=230mV
  • 156390 05/16/08 14:57 L. Zhu beam unstable
  • 156389 05/16/08 14:35 L. Zhu beam is back
  • 156388 05/16/08 13:47 L. Zhu beam lost
  • 156387 05/16/08 13:01 cdaq End of Run 70383:
  • 156386 05/16/08 11:52 cdaq Run 70383: GEp-III high Q2, 100uA, ps1=1000 ps2=500 ps3=99999 ps4=2000, ps5=1, FPP=3.0V BigCal_thr=230mV
  • 156385 05/16/08 10:41 cdaq End of Run 70382:
  • 156384 05/16/08 10:39 cdaq Run 70382: GEp-III high Q2, 100uA, ps1=1000 ps2=500 ps3=99999 ps4=2000, ps5=1, FPP=3.0V BigCal_thr=230mV
  • 156383 05/16/08 10:38 cdaq End of Run 70381:
  • 156382 05/16/08 09:26 cdaq Run 70381: GEp-III high Q2, 100uA, ps1=1000 ps2=500 ps3=99999 ps4=2000, ps5=1, FPP=3.0V BigCal_thr=230mV
  • 156381 05/16/08 09:25 cdaq End of Run 70380:
  • 156380 05/16/08 08:09 cdaq Run 70380: GEp-III high Q2, 100uA, ps1=1000 ps2=500 ps3=99999 ps4=2000, ps5=1, FPP=3.0V BigCal_thr=230mV
  • 156379 05/16/08 08:08 cdaq End of Run 70379:
  • 156378 05/16/08 08:02 cdaq Beam Time Accounting
  • 156377 05/16/08 08:02 Dutta Owl shift summary
  • 156376 05/16/08 07:54 Nuruzzaman Histograms are looking fine
  • 156375 05/16/08 07:53 narayan Target: L1 Temp alarm limits
  • 156374 05/16/08 07:32 narayan Target: JT valve
  • 156373 05/16/08 07:06 Nuruzzaman BCM Snapshot
  • 156372 05/16/08 07:01 cdaq Run 70379: GEp-III high Q2, 100uA, ps1=1000 ps2=500 ps3=99999 ps4=2000, ps5=1, FPP=3.0V BigCal_thr=230mV
  • 156371 05/16/08 07:01 cdaq End of Run 70378:
  • 156370 05/16/08 06:47 Nuruzzaman BCM Snapshot
  • 156369 05/16/08 06:46 Nuruzzaman BPM Snapshot
  • 156368 05/16/08 05:47 cdaq Run 70378: GEp-III high Q2, 100uA, ps1=1000 ps2=500 ps3=99999 ps4=2000, ps5=1, FPP=3.0V BigCal_thr=230mV
  • 156367 05/16/08 05:46 cdaq End of Run 70377:
  • 156366 05/16/08 05:24
  • 156365 05/16/08 04:28 cdaq Run 70377: GEp-III high Q2, 100uA, ps1=1000 ps2=500 ps3=99999 ps4=2000, ps5=1, FPP=3.0V BigCal_thr=230mV
  • 156364 05/16/08 04:26 cdaq End of Run 70376:
  • 156363 05/16/08 03:57 Nuruzzaman Full run has done for rn#70374
  • 156362 05/16/08 03:51 narayan Target: cryo flow increased
  • 156361 05/16/08 03:31 narayan cryo flow decreased
  • 156360 05/16/08 03:31 Nuruzzaman ADC & TDC hits comming back
  • 156359 05/16/08 03:13 cdaq Run 70376: GEp-III high Q2, 100uA, ps1=1000 ps2=500 ps3=99999 ps4=2000, ps5=1, FPP=3.0V BigCal_thr=230mV
  • 156358 05/16/08 03:11 cdaq End of Run 70375:
  • 156357 05/16/08 02:27 narayan Target: Target: snapshot & update
  • 156356 05/16/08 02:14 Nuruzzaman Number of ADC hits and TDC hits shifted
  • 156355 05/16/08 01:52 cdaq Run 70375: GEp-III high Q2, 100uA, ps1=1000 ps2=500 ps3=99999 ps4=2000, ps5=1, FPP=3.0V BigCal_thr=230mV
  • 156354 05/16/08 01:51 cdaq End of Run 70374:
  • 156353 05/16/08 00:28 Nuruzzaman Hitograms of run #70374
  • 156352 05/16/08 00:18 cdaq Run 70374: GEp-III high Q2, 100uA, ps1=1000 ps2=500 ps3=99999 ps4=2000, ps5=1, FPP=3.0V BigCal_thr=230mV
  • 156351 05/16/08 00:15 cdaq End of Run 70373:
  • 156350 05/16/08 00:00 cdaq Beam Time Accounting
  • Thursday

  • 156349 05/15/08 23:56 hamlet Swing Shift Summary, 15 May 2008
  • 156348 05/15/08 22:56 cdaq Run 70373: GEp-III high Q2, 100uA, ps1=1000 ps2=500 ps3=99999 ps4=2000, ps5=1, FPP=3.0V BigCal_thr=230mV
  • 156347 05/15/08 22:55 hamlet Beam back. Resumed data taking
  • 156346 05/15/08 22:47 jinhuang Target: IOC reboot & Problem Solved
  • 156345 05/15/08 22:17 jinhuang Target: Software Problem
  • 156344 05/15/08 22:12 jinhuang Target: Open up JT Valve to 27-28%
  • 156342 05/15/08 18:15 jinhuang Target: JT Valve -> 12%
  • 156341 05/15/08 18:02 jinhuang Target: JT Valve to 14-15%
  • 156340 05/15/08 17:56 jinhuang Target: Closing down JT Valve
  • 156339 05/15/08 17:40 hamlet Beam OFF for Hall A pass change
  • 156338 05/15/08 17:38 cdaq End of Run 70372:
  • 156337 05/15/08 17:09 frw bad replay?
  • 156336 05/15/08 16:40 cdaq Run 70372: GEp-III high Q2, 100uA, ps1=1000 ps2=500 ps3=99999 ps4=2000, ps5=1, FPP=3.0V BigCal_thr=230mV
  • 156335 05/15/08 16:39 cdaq End of Run 70371:
  • 156334 05/15/08 16:15 jinhuang Target: ScreenShot
  • 156333 05/15/08 16:00 cdaq Beam Time Accounting
  • 156332 05/15/08 15:46 Huber Day shift summary
  • 156331 05/15/08 15:38 cdaq Run 70371: GEp-III high Q2, 100uA, ps1=1000 ps2=500 ps3=99999 ps4=2000, ps5=1, FPP=3.0V BigCal_thr=230mV
  • 156330 05/15/08 15:37 cdaq End of Run 70370:
  • 156329 05/15/08 15:01 L. Zhu Target: screenshot with hall A target cooling
  • 156328 05/15/08 14:52 puckett updated BigCal ADC thresholds with "nsparse"=12 channels to see if "number of ADC hits" spectrum returns to normal
  • 156327 05/15/08 14:45 wpierce 70368 Full Replay
  • 156326 05/15/08 14:35 wpierce BCM/BPM screenshots
  • 156325 05/15/08 14:26 Huber First run after HMS down - 70370
  • 156324 05/15/08 14:19 cdaq Run 70370: GEp-III high Q2, 100uA, ps1=1000 ps2=500 ps3=99999 ps4=2000, ps5=1, FPP=3.0V BigCal_thr=230mV
  • 156323 05/15/08 14:00 Huber Hall C access available this evening
  • 156322 05/15/08 13:44 Huber HMS quadrupole status
  • 156321 05/15/08 12:38 Huber lost Q1,Q2 and Q3
  • 156320 05/15/08 12:08 Huber Beam will be off for ~30min
  • 156319 05/15/08 12:04 cdaq End of Run 70369:
  • 156318 05/15/08 11:58 cdaq Run 70369: GEp-III high Q2, 100uA, ps1=1000 ps2=500 ps3=99999 ps4=2000, ps5=1, FPP=3.0V BigCal_thr=230mV
  • 156317 05/15/08 11:57 cdaq End of Run 70368:
  • 156316 05/15/08 11:12 L. Zhu Target: screenshot after T increase
  • 156315 05/15/08 11:00 Bosted Target: Target: NEW SETPOINT of 20 K!
  • 156314 05/15/08 10:41 cdaq Run 70368: GEp-III high Q2, 100uA, ps1=1000 ps2=500 ps3=99999 ps4=2000, ps5=1, FPP=3.0V BigCal_thr=230mV
  • 156313 05/15/08 10:40 cdaq End of Run 70367:
  • 156312 05/15/08 10:17 puckett This appears to be a real shift...
  • 156311 05/15/08 10:08 Huber Beam Studies CANCELLED
  • 156310 05/15/08 09:41 wpierce Big Cal Histogram Shift
  • 156309 05/15/08 09:39 W. Luo Power cycled GEP HV crate 38, solved the problem
  • 156308 05/15/08 09:31 cdaq Run 70367: GEp-III high Q2, 100uA, ps1=1000 ps2=500 ps3=99999 ps4=2000, ps5=1, FPP=3.0V BigCal_thr=230mV
  • 156307 05/15/08 09:23 cdaq End of Run 70366:
  • 156306 05/15/08 09:05 cdaq Run 70366: GEp-III high Q2, 100uA, ps1=1000 ps2=500 ps3=99999 ps4=2000, ps5=1, FPP=3.0V BigCal_thr=230mV
  • 156305 05/15/08 09:04 cdaq End of Run 70365:
  • 156304 05/15/08 08:57 Huber Beam studies delayed until ~10am
  • 156303 05/15/08 08:28 wpierce GEP HV problems
  • 156302 05/15/08 08:23 Huber Hall access plans for today
  • 156301 05/15/08 08:21 cdaq Run 70365: GEp-III high Q2, 100uA, ps1=1000 ps2=500 ps3=99999 ps4=2000, ps5=1, FPP=3.0V BigCal_thr=230mV
  • 156300 05/15/08 08:08 cdaq End of Run 70364:
  • 156299 05/15/08 08:03 cdaq Beam Time Accounting
  • 156298 05/15/08 07:57 Dutta Owl Shift Summary
  • 156297 05/15/08 07:32 cdaq Run 70364: GEp-III high Q2, 100uA, ps1=1000 ps2=500 ps3=99999 ps4=2000, ps5=1, FPP=3.0V BigCal_thr=230mV
  • 156296 05/15/08 07:31 cdaq End of Run 70363:
  • 156295 05/15/08 06:58 Phil Carter Target: changed cell parameter back
  • 156294 05/15/08 06:49 narayan reference histogram
  • 156293 05/15/08 06:31 narayan BigCal Reference histograms
  • 156292 05/15/08 06:24 cdaq Run 70363: GEp-III high Q2, 100uA, ps1=1000 ps2=500 ps3=99999 ps4=2000, ps5=1, FPP=3.0V BigCal_thr=230mV
  • 156291 05/15/08 06:24 Phil Carter Target: fan died, IOC reboot
  • 156290 05/15/08 06:11 cdaq End of Run 70362:
  • 156289 05/15/08 05:48 cdaq Run 70362: GEp-III high Q2, 100uA, ps1=1000 ps2=500 ps3=99999 ps4=2000, ps5=1, FPP=3.0V BigCal_thr=230mV
  • 156288 05/15/08 05:47 cdaq End of Run 70361:
  • 156287 05/15/08 05:24
  • 156286 05/15/08 05:07 narayan snapshot of BPM/BCM
  • 156285 05/15/08 04:40 cdaq Run 70361: GEp-III high Q2, 100uA, ps1=1000 ps2=500 ps3=99999 ps4=2000, ps5=1, FPP=3.0V BigCal_thr=230mV
  • 156284 05/15/08 04:39 cdaq End of Run 70360:
  • 156283 05/15/08 04:11 Phil Carter Target: hcL1_hp_pid.OVAL graph after beam trip
  • 156282 05/15/08 04:00 narayan Temp. HV beeps
  • 156281 05/15/08 03:33 cdaq Run 70360: GEp-III high Q2, 100uA, ps1=1000 ps2=500 ps3=99999 ps4=2000, ps5=1, FPP=3.0V BigCal_thr=230mV
  • 156280 05/15/08 03:30 cdaq End of Run 70359:
  • 156279 05/15/08 02:50 narayan BigCal gain shift
  • 156278 05/15/08 02:28 cdaq Run 70359: GEp-III high Q2, 100uA, ps1=1000 ps2=500 ps3=99999 ps4=2000, ps5=1, FPP=3.0V BigCal_thr=230mV
  • 156277 05/15/08 02:26 cdaq End of Run 70358:
  • 156276 05/15/08 01:25 cdaq Run 70358: GEp-III high Q2, 100uA, ps1=1000 ps2=500 ps3=99999 ps4=2000, ps5=1, FPP=3.0V BigCal_thr=230mV
  • 156275 05/15/08 01:25 Phil Carter Target: screenshot
  • 156274 05/15/08 01:24 cdaq End of Run 70357:
  • 156273 05/15/08 00:16 cdaq Run 70357: GEp-III high Q2, 100uA, ps1=1000 ps2=500 ps3=99999 ps4=2000, ps5=1, FPP=3.0V BigCal_thr=230mV
  • 156272 05/15/08 00:07 hamlet Swing Shift Summary, 14 May 2008
  • 156271 05/15/08 00:07 hamlet ROC11 power cycled
  • 156270 05/15/08 00:07 jinhuang Target: Testing Beam Compensation Parameters
  • 156269 05/15/08 00:05 cdaq End of Run 70356:
  • 156268 05/15/08 00:04 cdaq Run 70356: DAQ test
  • 156267 05/15/08 00:04 cdaq Beam Time Accounting
  • Wednesday

  • 156266 05/14/08 23:40 hamlet Ask for Controlled Access to reboot ROC11
  • 156265 05/14/08 22:00 cdaq Run 70355: GEp-III high Q2, 100uA, ps1=1000 ps2=500 ps3=99999 ps4=2000, ps5=1, FPP=3.0V BigCal_thr=230mV
  • 156264 05/14/08 21:59 cdaq End of Run 70354:
  • 156263 05/14/08 20:55 cdaq Run 70354: GEp-III high Q2, 100uA, ps1=1000 ps2=500 ps3=99999 ps4=2000, ps5=1, FPP=3.0V BigCal_thr=230mV
  • 156262 05/14/08 20:54 cdaq End of Run 70353:
  • 156261 05/14/08 19:51 cdaq Run 70353: GEp-III high Q2, 100uA, ps1=1000 ps2=500 ps3=99999 ps4=2000, ps5=1, FPP=3.0V BigCal_thr=230mV
  • 156260 05/14/08 19:51 jinhuang Target: IOC reboot
  • 156259 05/14/08 19:46 hamlet Ended run 70352 to reboot target IOC
  • 156258 05/14/08 19:43 cdaq End of Run 70352:
  • 156257 05/14/08 19:37 cdaq Run 70352: GEp-III high Q2, 100uA, ps1=1000 ps2=500 ps3=99999 ps4=2000, ps5=1, FPP=3.0V BigCal_thr=230mV
  • 156256 05/14/08 19:36 cdaq End of Run 70351:
  • 156254 05/14/08 18:32 cdaq Run 70351: GEp-III high Q2, 100uA, ps1=1000 ps2=500 ps3=99999 ps4=2000, ps5=1, FPP=3.0V BigCal_thr=230mV
  • 156253 05/14/08 18:31 cdaq End of Run 70350:
  • 156251 05/14/08 17:56 hamlet Beam quality back to normal
  • 156250 05/14/08 17:31 cdaq Run 70350: GEp-III high Q2, 100uA, ps1=1000 ps2=500 ps3=99999 ps4=2000, ps5=1, FPP=3.0V BigCal_thr=230mV
  • 156249 05/14/08 17:30 cdaq End of Run 70349:
  • 156248 05/14/08 17:25 jinhuang Target: is happy at current setting
  • 156247 05/14/08 16:48 hamlet Beam very unstable
  • 156246 05/14/08 16:24 jinhuang Target: Low Cryo Flow Causing Fluctuations
  • 156245 05/14/08 16:24 W. Luo Peds mean is good, peds width shifted because of beam at start of run
  • 156244 05/14/08 16:06 S. Frullani day shift summary
  • 156243 05/14/08 16:05 cdaq Beam Time Accounting
  • 156242 05/14/08 16:04 cdaq Run 70349: GEp-III high Q2, 90 uA, ps1=1000 ps2=500 ps3=99999 ps4=2000, ps5=1, FPP=3.0V BigCal_thr=230mV
  • 156241 05/14/08 16:02 cdaq End of Run 70348:
  • 156240 05/14/08 15:53 Nuruzzaman Pedesteral mean is totally off
  • 156239 05/14/08 15:50 Nuruzzaman Shift in BigCal ADC & BigCal Trigger ADC
  • 156238 05/14/08 15:33 pking Target: one more click.
  • 156237 05/14/08 15:22 pking Target: Opened JT again.
  • 156236 05/14/08 15:14 pking Target: JT set for about 50 W reserve HPH power
  • 156235 05/14/08 15:00 Nuruzzaman Beam come back again
  • 156234 05/14/08 14:58 cdaq Run 70348: GEp-III high Q2, 90 uA, ps1=1000 ps2=500 ps3=99999 ps4=2000, ps5=1, FPP=3.0V BigCal_thr=230mV
  • 156233 05/14/08 14:56 cdaq End of Run 70347:
  • 156232 05/14/08 14:48 pking Target: screen shots before trying to reduce HPH reserve power to 50 W
  • 156231 05/14/08 14:31 Nuruzzaman BCM Screenshot
  • 156229 05/14/08 14:30 Nuruzzaman BPM Screenshot
  • 156228 05/14/08 13:59 pking Target: opened JT valve slightly
  • 156227 05/14/08 13:32 cdaq Run 70347: GEp-III high Q2, 92 uA, ps1=1000 ps2=500 ps3=99999 ps4=2000, ps5=1, FPP=3.0V BigCal_thr=230mV
  • 156226 05/14/08 13:30 cdaq End of Run 70346:
  • 156225 05/14/08 12:40 frw run-start dialog missing
  • 156224 05/14/08 12:16 S. Frullani parameter window run start
  • 156223 05/14/08 12:09 cdaq Run 70346: GEp-III high Q2, 92 uA, ps1=1000 ps2=500 ps3=99999 ps4=2000, ps5=1, FPP=3.0V BigCal_thr=230mV
  • 156222 05/14/08 12:08 cdaq End of Run 70345:
  • 156221 05/14/08 11:26 pking Target: closed JT valve slightly
  • 156220 05/14/08 10:52 cdaq Run 70345: GEp-III high Q2, 92 uA, ps1=1000 ps2=500 ps3=99999 ps4=2000, ps5=1, FPP=3.0V BigCal_thr=230mV
  • 156219 05/14/08 10:51 cdaq End of Run 70344:
  • 156218 05/14/08 10:47 frw beam ramp rate: we do not need it
  • 156217 05/14/08 10:38 S. Frullani lower current
  • 156216 05/14/08 10:33 pking MCC is going to increase the beam ramp rate
  • 156215 05/14/08 09:27 Nuruzzaman BigCal ADC hits come back to normal
  • 156214 05/14/08 09:10 cdaq Run 70344: GEp-III high Q2, 98uA, ps1=1000 ps2=500 ps3=99999 ps4=2000, ps5=1, FPP=3.0V BigCal_thr=230mV
  • 156213 05/14/08 09:10 Nuruzzaman BigCal ADC hits changed suddenly
  • 156212 05/14/08 09:09 cdaq End of Run 70343:
  • 156211 05/14/08 08:51 cdaq Run 70343: GEp-III high Q2, 100uA, ps1=1000 ps2=500 ps3=99999 ps4=2000, ps5=1, FPP=3.0V BigCal_thr=230mV
  • 156210 05/14/08 08:47 cdaq End of Run 70342:
  • 156209 05/14/08 08:21 Nuruzzaman Histograms of run# 70342
  • 156208 05/14/08 08:08 pking Target: Screens at shift start
  • 156207 05/14/08 08:02 cdaq Beam Time Accounting
  • 156206 05/14/08 07:57 Dutta Owl Shift Summary
  • 156205 05/14/08 07:36 cdaq Run 70342: GEp-III high Q2, Read Back 95.7uA requested 100, ps1=1000 ps2=500 ps3=99999 ps4=2000, ps5=1, FPP=3.0V BigCal_thr=230mV
  • 156204 05/14/08 07:34 cdaq End of Run 70341:
  • 156203 05/14/08 06:42 Phil Carter Target: IOC reboot
  • 156202 05/14/08 06:17 cdaq Run 70341: GEp-III high Q2, 100uA, ps1=1000 ps2=500 ps3=99999 ps4=2000, ps5=1, FPP=3.0V BigCal_thr=230mV
  • 156201 05/14/08 06:14 cdaq End of Run 70340:
  • 156200 05/14/08 05:37 narayan BPM/BCM sanpshot
  • 156199 05/14/08 05:23
  • 156198 05/14/08 04:59 cdaq Run 70340: GEp-III high Q2, 100uA, ps1=1000 ps2=500 ps3=99999 ps4=2000, ps5=1, FPP=3.0V BigCal_thr=230mV
  • 156197 05/14/08 04:58 cdaq End of Run 70339:
  • 156196 05/14/08 03:49 cdaq Run 70339: GEp-III high Q2, 100uA, ps1=1000 ps2=500 ps3=99999 ps4=2000, ps5=1, FPP=3.0V BigCal_thr=230mV
  • 156195 05/14/08 03:48 cdaq End of Run 70338:
  • 156194 05/14/08 02:48 Phil Carter Target: screenshot
  • 156193 05/14/08 02:44 Dutta finally full current
  • 156192 05/14/08 02:11 Dutta beam back but unstable
  • 156191 05/14/08 02:09 cdaq Run 70338: GEp-III high Q2, 60uA, ps1=1000 ps2=500 ps3=99999 ps4=2000, ps5=1, FPP=3.0V BigCal_thr=230mV
  • 156190 05/14/08 00:59 Dutta update
  • 156189 05/14/08 00:34 Dutta Beam off
  • 156188 05/14/08 00:18 cdaq End of Run 70337:
  • 156187 05/14/08 00:00 cdaq Beam Time Accounting
  • Tuesday

  • 156186 05/13/08 23:50 Huber Swing shift report
  • 156185 05/13/08 23:01 cdaq Run 70337: GEp-III high Q2, 100uA, ps1=1000 ps2=500 ps3=99999 ps4=2000, ps5=1, FPP=3.0V BigCal_thr=230mV
  • 156184 05/13/08 23:00 cdaq End of Run 70336:
  • 156183 05/13/08 22:23 wpierce BCM and BPM Screenshots
  • 156182 05/13/08 21:52 cdaq Run 70336: GEp-III high Q2, 100uA, ps1=1000 ps2=500 ps3=99999 ps4=2000, ps5=1, FPP=3.0V BigCal_thr=230mV
  • 156181 05/13/08 21:51 cdaq End of Run 70335:
  • 156180 05/13/08 20:55 jinhuang Target: IOC reboot
  • 156179 05/13/08 20:46 cdaq Run 70335: GEp-III high Q2, 100uA, ps1=1000 ps2=500 ps3=99999 ps4=2000, ps5=1, FPP=3.0V BigCal_thr=230mV
  • 156178 05/13/08 20:37 cdaq End of Run 70334:
  • 156177 05/13/08 19:45 cdaq Run 70334: GEp-III high Q2, 100uA, ps1=1000 ps2=500 ps3=99999 ps4=2000, ps5=1, FPP=3.0V BigCal_thr=230mV
  • 156176 05/13/08 19:44 cdaq End of Run 70333:
  • 156175 05/13/08 18:37 cdaq Run 70333: GEp-III high Q2, 100uA, ps1=1000 ps2=500 ps3=99999 ps4=2000, ps5=1, FPP=3.0V BigCal_thr=230mV
  • 156174 05/13/08 18:36 cdaq End of Run 70332:
  • 156173 05/13/08 17:47 cdaq Run 70332: GEp-III high Q2, 100uA, ps1=1000 ps2=500 ps3=99999 ps4=2000, ps5=1, FPP=3.0V BigCal_thr=230mV
  • 156172 05/13/08 17:46 cdaq End of Run 70331:
  • 156171 05/13/08 17:38 puckett changed bigcal software thresholds back to "normal"
  • 156170 05/13/08 17:33 puckett not a problem--see my log entry
  • 156169 05/13/08 17:26 Pierce Big Cal Gain Loss
  • 156168 05/13/08 17:19 puckett Experimenting with higher software thresholds in engine--expect BigCal hits histos to shift to lower values
  • 156167 05/13/08 17:03 cdaq Run 70331: GEp-III high Q2, 100uA, ps1=1000 ps2=500 ps3=99999 ps4=2000, ps5=1, FPP=3.0V BigCal_thr=230mV
  • 156166 05/13/08 17:01 cdaq End of Run 70330:
  • 156165 05/13/08 16:42 jinhuang Target: ScreenShot
  • 156164 05/13/08 16:20 cdaq Run 70330: GEp-III high Q2, 100uA, ps1=1000 ps2=500 ps3=99999 ps4=2000, ps5=1, FPP=3.0V BigCal_thr=230mV
  • 156163 05/13/08 16:19 cdaq End of Run 70329:
  • 156162 05/13/08 16:07 Nuruzzaman Histograms are looking good
  • 156161 05/13/08 16:06 cdaq Beam Time Accounting
  • 156160 05/13/08 16:02 pking Day Shift Summary
  • 156159 05/13/08 15:33 cdaq Run 70329: GEp-III high Q2, 100uA, ps1=1000 ps2=500 ps3=99999 ps4=2000, ps5=1, FPP=3.0V BigCal_thr=230mV
  • 156158 05/13/08 15:26 pking TS crashed at end of run 70327; no beam in 70328
  • 156157 05/13/08 15:16 cdaq End of Run 70328:
  • 156156 05/13/08 15:15 cdaq Run 70328: GEp-III high Q2, 100uA, ps1=1000 ps2=500 ps3=99999 ps4=2000, ps5=1, FPP=3.0V BigCal_thr=230mV
  • 156155 05/13/08 14:52 cdaq Run 70327: GEp-III high Q2, 100uA, ps1=1000 ps2=500 ps3=99999 ps4=2000, ps5=1, FPP=3.0V BigCal_thr=230mV
  • 156154 05/13/08 14:52 pking Beam positions and current for checklist.
  • 156153 05/13/08 14:51 cdaq End of Run 70326:
  • 156152 05/13/08 14:03 cdaq Run 70326: GEp-III high Q2, 100uA, ps1=1000 ps2=500 ps3=99999 ps4=2000, ps5=1, FPP=3.0V BigCal_thr=230mV
  • 156151 05/13/08 14:02 cdaq End of Run 70325:
  • 156150 05/13/08 13:13 cdaq Run 70325: GEp-III high Q2, 100uA, ps1=1000 ps2=500 ps3=99999 ps4=2000, ps5=1, FPP=3.0V BigCal_thr=230mV
  • 156149 05/13/08 13:11 cdaq End of Run 70324:
  • 156148 05/13/08 12:49 Nuruzzaman Cluster Histograms
  • 156147 05/13/08 12:22 W. Luo Updated ADC threshold of ROC11 with run 70323
  • 156146 05/13/08 12:19 cdaq Run 70324: GEp-III high Q2, 100uA, ps1=1000 ps2=500 ps3=99999 ps4=2000, ps5=1, FPP=3.0V BigCal_thr=230mV
  • 156145 05/13/08 12:17 cdaq End of Run 70323:
  • 156144 05/13/08 12:06 W. Luo Pedestal of 4 channels of BigCal shifted
  • 156143 05/13/08 11:58 Nuruzzaman Coincidence time of HMS is matching now
  • 156142 05/13/08 11:54 Nuruzzaman BigCal ADC hits
  • 156141 05/13/08 11:44 pking Increased beam current to 100 uA for run 70323
  • 156140 05/13/08 11:40 cdaq Run 70323: GEp-III high Q2, 90uA, ps1=1000 ps2=500 ps3=99999 ps4=2000, ps5=1, FPP=3.0V BigCal_thr=230mV
  • 156139 05/13/08 11:39 cdaq End of Run 70322:
  • 156138 05/13/08 11:26 Nuruzzaman FPP Histogram
  • 156137 05/13/08 11:24 Nuruzzaman Histograms are matching exactly
  • 156136 05/13/08 11:09 W. Luo Updated "golden run" to 70322 for online replay
  • 156135 05/13/08 10:49 pking Changed ps4 to 2000 before run 70322
  • 156134 05/13/08 10:46 cdaq Run 70322: GEp-III high Q2, 90uA, ps1=1000 ps2=500 ps3=99999 ps4=2000, ps5=1, FPP=3.0V BigCal_thr=230mV
  • 156133 05/13/08 10:45 cdaq End of Run 70321:
  • 156132 05/13/08 10:44 L. Zhu target: screenshot
  • 156131 05/13/08 10:43 Nuruzzaman Coincidence time of HMS shited
  • 156130 05/13/08 10:41 Nuruzzaman histograms of run#70321
  • 156129 05/13/08 10:34 W. Luo Replaced cable 37CD come out of 2nd sum module to trigger tdc.
  • 156128 05/13/08 10:30 pking Beam is at 90 uA; start running
  • 156127 05/13/08 10:27 cdaq Run 70321: GEp-III high Q2, 90uA, ps1=1000 ps2=500 ps3=99999 ps4=200, ps5=1, FPP=3.0V BigCal_thr=230mV
  • 156126 05/13/08 10:08 pking Wei is out of the hall; setting the hall back for beam
  • 156125 05/13/08 09:55 pking MCC is done with RF recovery; Wei is still in the hall.
  • 156124 05/13/08 09:38 pking The hall survey is complete; Wei is going in
  • 156123 05/13/08 09:11 cdaq End of Run 70320:
  • 156122 05/13/08 09:10 cdaq Run 70320: BigCal LED run
  • 156121 05/13/08 08:46 pking We will have an controlled access
  • 156120 05/13/08 08:44 pkng Checked with MCC; still expect to be bringing beam back around 09:00
  • 156119 05/13/08 08:05 cdaq Beam Time Accounting
  • 156118 05/13/08 07:41 Dutta RF recovery time moved up
  • 156117 05/13/08 07:21 Dutta Owl Shift Summary
  • 156116 05/13/08 07:16 cdaq End of Run 70319:
  • 156115 05/13/08 06:49 cdaq Run 70319: GEp-III high Q2, 90uA, ps1=1000 ps2=500 ps3=99999 ps4=200, ps5=1, FPP=3.0V BigCal_thr=230mV
  • 156114 05/13/08 06:47 cdaq End of Run 70318:
  • 156113 05/13/08 05:58 cdaq Run 70318: GEp-III high Q2, 90uA, ps1=1000 ps2=500 ps3=99999 ps4=200, ps5=1, FPP=3.0V BigCal_thr=230mV
  • 156112 05/13/08 05:54 cdaq End of Run 70317:
  • 156111 05/13/08 05:41 Lassiter Q1 problems
  • 156110 05/13/08 05:22
  • 156109 05/13/08 05:10 Dutta Beam is back
  • 156108 05/13/08 05:08 cdaq Run 70317: GEp-III high Q2, 90uA, ps1=1000 ps2=500 ps3=99999 ps4=200, ps5=1, FPP=3.0V BigCal_thr=230mV
  • 156107 05/13/08 04:47 Dutta Q1 fixed
  • 156106 05/13/08 04:28 Dutta Update
  • 156105 05/13/08 03:44 Phil Carter Target: screenshot
  • 156104 05/13/08 00:01 cdaq Beam Time Accounting
  • Monday

  • 156103 05/12/08 23:30 saw Rebooting from codamaster
  • 156102 05/12/08 23:24 Huber Restarting codamaster when ROC reboot fails
  • 156101 05/12/08 23:20 Huber Swing shift summary
  • 156100 05/12/08 22:44 cdaq End of Run 70315:
  • 156099 05/12/08 22:43 cdaq Run 70315: cosmic
  • 156098 05/12/08 22:39 M Jonesq problems resetting rocs from rebootpanel
  • 156097 05/12/08 22:34 M Jones Had to power cycle roc11
  • 156096 05/12/08 22:26 cdaq End of Run 70314:
  • 156095 05/12/08 22:25 cdaq Run 70314: cosmic
  • 156094 05/12/08 21:43 Huber Various issues
  • 156093 05/12/08 21:34 jinhuang Target: 4K flow rise observed when HMS Interlock is Actived
  • 156092 05/12/08 21:11 jinhuang Target: JT Valve to 15%; HPH to 190W
  • 156091 05/12/08 21:01 jinhuang Target: Expected No Beam for 1hour, Closing JT Valve
  • 156090 05/12/08 20:25 Huber Run 70312 is bad
  • 156089 05/12/08 20:22 cdaq Run 70313: GEp-III high Q2, 99uA, ps1=1000 ps2=500 ps3=99999 ps4=200, ps5=1, FPP=3.0V BigCal_thr=230mV
  • 156088 05/12/08 20:20 jinhuang Target: ScreenShot at 100uA
  • 156087 05/12/08 20:18 cdaq End of Run 70312:
  • 156086 05/12/08 20:13 cdaq Run 70312: GEp-III high Q2, 99uA, ps1=1000 ps2=500 ps3=99999 ps4=200, ps5=1, FPP=3.0V BigCal_thr=230mV
  • 156085 05/12/08 20:10 cdaq End of Run 70311:
  • 156084 05/12/08 19:59 Huber All seems happy at 90uA
  • 156083 05/12/08 19:59 Huber BigCal gains at 90uA
  • 156082 05/12/08 19:04 cdaq Run 70311: GEp-III high Q2, 90uA, ps1=1000 ps2=500 ps3=99999 ps4=200, ps5=1, FPP=3.0V BigCal_thr=230mV
  • 156081 05/12/08 18:33 cdaq End of Run 70310:
  • 156080 05/12/08 18:14 jinhuang Target: JT Valve to 35-36%, 90uA ScreenShot
  • 156079 05/12/08 18:11 Huber Now authorized for up to 100uA
  • 156078 05/12/08 18:11 cdaq Run 70310: GEp-III high Q2, 90uA, ps1=1000 ps2=500 ps3=99999 ps4=200, ps5=1, FPP=3.0V BigCal_thr=230mV
  • 156077 05/12/08 18:07 cdaq End of Run 70309:
  • 156076 05/12/08 17:18 jinhuang Target: JT Valve Back to 33%
  • 156075 05/12/08 17:10 cdaq Run 70309: GEp-III high Q2, 80uA, ps1=1000 ps2=500 ps3=99999 ps4=200, ps5=1, FPP=3.0V BigCal_thr=230mV
  • 156074 05/12/08 17:08 cdaq End of Run 70308:
  • 156073 05/12/08 17:03 jinhuang Tareget: JT Valve to 35%. HPH to 180W@80uA
  • 156072 05/12/08 16:57 jinhuang Target: ScreenShot & Opening JT Valve
  • 156071 05/12/08 16:57 pking Short shift summary from day shift
  • 156070 05/12/08 16:13 M Jones The change in H1 and C1 rate is due to trigger change on Thursday
  • 156069 05/12/08 16:12 cdaq Run 70308: GEp-III high Q2, 80uA, ps1=1000 ps2=500 ps3=99999 ps4=200, ps5=1, FPP=3.0V BigCal_thr=230mV
  • 156068 05/12/08 16:11 cdaq End of Run 70307:
  • 156067 05/12/08 16:03 cdaq Beam Time Accounting
  • 156066 05/12/08 16:01 Huber ATTENTION for those who want to enter the Hall
  • 156065 05/12/08 15:54 pking Beam screens for checklist
  • 156064 05/12/08 15:53 pking H1 and C1 rates have changed since last week
  • 156063 05/12/08 15:20 cdaq Run 70307: GEp-III high Q2, 80uA, ps1=1000 ps2=500 ps3=99999 ps4=200, ps5=1, FPP=3.0V BigCal_thr=230mV
  • 156062 05/12/08 15:18 cdaq End of Run 70306:
  • 156061 05/12/08 14:50 pking Target: screens with 80 uA
  • 156060 05/12/08 14:34 horn Moller summary and mini spin dance result
  • 156059 05/12/08 14:30 cdaq Run 70306: GEp-III high Q2, 80uA, ps1=1000 ps2=500 ps3=99999 ps4=200, ps5=1, FPP=3.0V BigCal_thr=230mV
  • 156058 05/12/08 14:23 pking Target: LH2 target is in.
  • 156057 05/12/08 14:16 pking Target: Moving back to 20cm LH2
  • 156056 05/12/08 14:02 horn Moller done
  • 156055 05/12/08 13:51 cdaq End of Run 70305:
  • 156054 05/12/08 13:39 cdaq Moller Run 70305: Moller HWP=IN, Wien angle=-33.53 deg
  • 156053 05/12/08 13:38 cdaq End of Run 70304:
  • 156052 05/12/08 13:28 cdaq Moller Run 70304: Moller HWP=IN, Wien angle=-33.53 deg
  • 156051 05/12/08 13:17 cdaq End of Run 70303:
  • 156050 05/12/08 13:09 cdaq Moller Run 70303: Moller HWP=IN, Wien angle=-3.53 deg
  • 156049 05/12/08 13:08 cdaq End of Run 70302:
  • 156048 05/12/08 13:00 cdaq Moller Run 70302: Moller HWP=IN, Wien angle=-3.53 deg
  • 156047 05/12/08 13:00 cdaq End of Run 70301:
  • 156046 05/12/08 12:48 cdaq Moller Run 70301: Moller HWP=IN, Wien angle=-3.53 deg
  • 156045 05/12/08 12:34 cdaq End of Run 70300:
  • 156044 05/12/08 12:29 cdaq Moller Run 70300: Moller HWP=IN, Wien angle=-3.53 deg
  • 156043 05/12/08 12:22 cdaq End of Run 70299:
  • 156042 05/12/08 12:14 cdaq Moller Run 70299: Moller HWP=IN, Wien angle=-23.53 deg
  • 156041 05/12/08 12:13 cdaq End of Run 70298:
  • 156040 05/12/08 12:03 cdaq Moller Run 70298: Moller HWP=IN, Wien angle=-23.53 deg
  • 156039 05/12/08 12:02 cdaq End of Run 70297:
  • 156038 05/12/08 11:58 cdaq Moller Run 70297: Moller HWP=IN, Wien angle=-23.53 deg
  • 156037 05/12/08 11:31 cdaq End of Run 70296:
  • 156036 05/12/08 11:22 cdaq Moller Run 70296: Moller HWP=IN, Wien angle=-13.53 deg
  • 156035 05/12/08 11:21 cdaq End of Run 70295:
  • 156034 05/12/08 11:09 cdaq Moller Run 70295: Moller HWP=IN, Wien angle=-13.53 deg
  • 156033 05/12/08 11:09 cdaq End of Run 70294:
  • 156032 05/12/08 11:03 pking Target: Reloaded alarm limits
  • 156031 05/12/08 10:59 cdaq Moller Run 70294: Moller HWP=IN, Wien angle=-13.53 deg
  • 156030 05/12/08 10:56 cdaq End of Run 70293:
  • 156029 05/12/08 10:54 cdaq Moller Run 70293: Moller HWP=IN, Wien angle=-13.53 deg
  • 156028 05/12/08 10:18 pking Target: Target is in empty position.
  • 156027 05/12/08 10:10 cdaq End of Run 70292:
  • 156026 05/12/08 10:10 cdaq Moller Run 70292: Moller DAQ test
  • 156025 05/12/08 10:02 pking Target: Moving to empty target for Moller measurement.
  • 156024 05/12/08 09:58 cdaq End of Run 70291:
  • 156023 05/12/08 09:56 cdaq Run 70291: GEp-III high Q2, 80uA, ps1=1000 ps2=500 ps3=99999 ps4=200, ps5=1, FPP=3.0V BigCal_thr=230mV
  • 156022 05/12/08 09:54 cdaq End of Run 70290:
  • 156021 05/12/08 09:03 cdaq Run 70290: GEp-III high Q2, 80uA, ps1=1000 ps2=500 ps3=99999 ps4=200, ps5=1, FPP=3.0V BigCal_thr=230mV
  • 156020 05/12/08 08:59 pking Target: screens at beginning of the shift
  • 156019 05/12/08 08:56 pking Beam current was 80 uA for run 70289
  • 156018 05/12/08 08:54 cdaq End of Run 70289:
  • 156017 05/12/08 08:22 cdaq Run 70289: GEp-III high Q2, 10uA, ps1=1000 ps2=500 ps3=99999 ps4=200, ps5=1, FPP=3.0V BigCal_thr=230mV
  • 156016 05/12/08 08:21 cdaq Beam Time Accounting
  • 156015 05/12/08 08:21 cdaq End of Run 70288:
  • 156014 05/12/08 08:19 Dutta Owl Shift Summary
  • 156013 05/12/08 07:54 Nuruzzaman fpp wire hits coming back to normal
  • 156012 05/12/08 07:46 Nuruzzaman BigCal gains getting normal
  • 156011 05/12/08 07:43 Nuruzzaman Histograms getting back to normal
  • 156010 05/12/08 07:36 Dutta ps4 changed back to 200
  • 156009 05/12/08 07:34 cdaq Run 70288: GEp-III high Q2, 10uA, ps1=1000 ps2=500 ps3=99999 ps4=200, ps5=1, FPP=3.0V BigCal_thr=230mV
  • 156008 05/12/08 07:31 cdaq End of Run 70287:
  • 156007 05/12/08 07:31 cdaq Run 70287: GEp-III high Q2, 10uA, ps1=1000 ps2=500 ps3=99999 ps4=1, ps5=1, FPP=3.0V BigCal_thr=230mV
  • 156006 05/12/08 07:21 Nuruzzaman Ethane Gas cylinder oppned
  • 156005 05/12/08 07:20 cdaq End of Run 70286:
  • 156004 05/12/08 06:50 Dutta Q1 crash
  • 156003 05/12/08 06:48 Nuruzzaman Screen shot of BCM
  • 156002 05/12/08 06:45 Nuruzzaman Screen shot of BPM
  • 156001 05/12/08 06:37 cdaq Run 70286: GEp-III high Q2, 10uA, ps1=1000 ps2=500 ps3=99999 ps4=1, ps5=1, FPP=3.0V BigCal_thr=230mV
  • 156000 05/12/08 06:14 cdaq End of Run 70285:
  • 155999 05/12/08 06:05 piskunov target
  • 155998 05/12/08 06:05 cdaq Run 70285: GEp-III high Q2, 10uA, ps1=1000 ps2=500 ps3=99999 ps4=1, ps5=1, FPP=3.0V BigCal_thr=230mV
  • 155997 05/12/08 05:41 cdaq End of Run 70284:
  • 155996 05/12/08 05:40 piskunov target
  • 155995 05/12/08 05:31 cdaq Run 70284: GEp-III high Q2, 10uA, ps1=1000 ps2=500 ps3=99999 ps4=1, ps5=1, FPP=3.0V BigCal_thr=230mV
  • 155994 05/12/08 05:19
  • 155993 05/12/08 05:13 cdaq End of Run 70283:
  • 155992 05/12/08 04:14 cdaq Run 70283: GEp-III high Q2, 10uA, ps1=1000 ps2=500 ps3=99999 ps4=1, ps5=1, FPP=3.0V BigCal_thr=230mV
  • 155991 05/12/08 04:13 cdaq End of Run 70282:
  • 155990 05/12/08 04:12 cdaq Run 70282: GEp-III high Q2, 10uA, ps1=1000 ps2=500 ps3=99999 ps4=1, ps5=1, FPP=3.0V BigCal_thr=230mV
  • 155989 05/12/08 04:11 Dutta ROC 13 crashed again
  • 155988 05/12/08 03:11 Dutta ROC13 CRASHED
  • 155987 05/12/08 03:09 cdaq Run 70281: GEp-III high Q2, 10uA, ps1=1000 ps2=500 ps3=99999 ps4=1, ps5=1, FPP=3.0V BigCal_thr=230mV
  • 155986 05/12/08 02:58 dutta ROC13 problem and gepscope screengrab
  • 155985 05/12/08 02:36 piskunov target
  • 155984 05/12/08 01:53 cdaq Run 70280: GEp-III high Q2, 10uA, ps1=1000 ps2=500 ps3=99999 ps4=1, ps5=1, FPP=3.0V BigCal_thr=230mV
  • 155983 05/12/08 01:36 cdaq End of Run 70279:
  • 155982 05/12/08 01:07 Nuruzzaman fpp wire hits increased
  • 155981 05/12/08 01:02 Nuruzzaman HSCIN timing shifted
  • 155980 05/12/08 00:54 cdaq Run 70279: GEp-III high Q2, 10uA, ps1=1000 ps2=500 ps3=99999 ps4=1, ps5=1, FPP=3.0V BigCal_thr=230mV
  • 155979 05/12/08 00:50 cdaq End of Run 70278:
  • 155978 05/12/08 00:27 piskunov target
  • 155977 05/12/08 00:03 cdaq Run 70278: GEp-III high Q2, 10uA, ps1=1000 ps2=500 ps3=99999 ps4=1, ps5=1, FPP=3.0V BigCal_thr=230mV
  • 155976 05/12/08 00:01 cdaq Beam Time Accounting
  • Sunday

  • 155975 05/11/08 23:59 cdaq End of Run 70277:
  • 155974 05/11/08 23:52 Huber BigCal gain
  • 155973 05/11/08 23:28 cdaq Run 70277: GEp-III high Q2, 10uA, ps1=1000 ps2=500 ps3=99999 ps4=1, ps5=1, FPP=3.0V BigCal_thr=230mV
  • 155972 05/11/08 23:27 cdaq End of Run 70276:
  • 155971 05/11/08 22:40 cdaq Run 70276: GEp-III high Q2, 10uA, ps1=1000 ps2=500 ps3=99999 ps4=1, ps5=1, FPP=3.0V BigCal_thr=230mV
  • 155970 05/11/08 22:39 cdaq End of Run 70275:
  • 155969 05/11/08 22:13 Huber PS4 now =1
  • 155968 05/11/08 21:53 cdaq Run 70275: GEp-III high Q2, 10uA, ps1=1000 ps2=500 ps3=99999 ps4=1, ps5=1, FPP=3.0V BigCal_thr=230mV
  • 155967 05/11/08 21:47 cdaq End of Run 70274:
  • 155966 05/11/08 21:41 cdaq Run 70274: GEp-III high Q2, 10uA, ps1=1000 ps2=500 ps3=99999 ps4=1, ps5=1, FPP=3.0V BigCal_thr=230mV
  • 155965 05/11/08 21:39 cdaq End of Run 70273:
  • 155964 05/11/08 21:28 W. Luo BigCal 4AB is normal now, but 37CD get bad again
  • 155963 05/11/08 20:56 jmaxwell Target: Target Screenshot after beam back
  • 155962 05/11/08 20:44 cdaq Run 70273: GEp-III high Q2, 10uA, ps1=1000 ps2=500 ps3=99999 ps4=200 ps5=1, FPP=3.0V BigCal_thr=230mV
  • 155961 05/11/08 20:40 cdaq End of Run 70272:
  • 155960 05/11/08 20:38 cdaq Run 70272: GEp-III high Q2, 10uA, ps1=1000 ps2=500 ps3=99999 ps4=200 ps5=1, FPP=3.0V BigCal_thr=230mV
  • 155959 05/11/08 20:37 jmaxwell Target: Moved to 20cm LH2
  • 155958 05/11/08 20:10 Huber Beam status
  • 155957 05/11/08 18:29 Huber Still waiting for beam
  • 155956 05/11/08 16:55 Huber Experiment ready
  • 155955 05/11/08 15:50 smithg Target: Cooldown finished. Moved to MT tgt.
  • 155954 05/11/08 15:48 bhovik Prescale factors
  • 155953 05/11/08 15:46 cdaq End of Run 70271:
  • 155952 05/11/08 15:43 pking DAQ test runs 70270 and 70271; trouble with ROC13?
  • 155951 05/11/08 15:37 cdaq Run 70271: DAQ test; cosmic
  • 155950 05/11/08 15:18 bhovik Beam Access
  • 155949 05/11/08 15:14 cdaq End of Run 70270:
  • 155948 05/11/08 15:10 cdaq Run 70270: cosmic
  • 155947 05/11/08 14:15 smithg Target: Transitioned to cold return
  • 155946 05/11/08 12:44 smithg Target: Started to open JT
  • 155945 05/11/08 12:12 bhovik Magnet current set values
  • 155944 05/11/08 11:32 smithg Target: Started cooldown
  • 155943 05/11/08 09:33 cdaq Beam Time Accounting
  • 155942 05/11/08 09:27 cdaq Run 70269: cosmic
  • 155941 05/11/08 05:19
  • Saturday

  • 155940 05/10/08 17:21 kenyon vacuum &c.
  • 155939 05/10/08 16:48 kenyon Reset clean power and gas system after fire alarm
  • 155937 05/10/08 12:17 saw Counting house door
  • 155936 05/10/08 05:22
  • 155935 05/10/08 01:35
  • Friday

  • 155934 05/09/08 14:44 smithg Target: plot of vacuum over past week
  • 155933 05/09/08 13:19 cdaq End of Run 70268:
  • 155932 05/09/08 13:16 cdaq Run 70268: BigCal LED run with PS3=1
  • 155931 05/09/08 13:15 cdaq End of Run 70267:
  • 155930 05/09/08 13:14 cdaq Run 70267: BigCal LED run
  • 155929 05/09/08 10:22 bhovik Cancelling Shifts !!!
  • 155928 05/09/08 09:42 Bosted Target vacuum alarm
  • 155927 05/09/08 09:40 BostedT Target: turned off fan and heater
  • 155926 05/09/08 09:32 Fowler HMS Magnets
  • 155925 05/09/08 09:04 Bosted Target warming up
  • 155924 05/09/08 08:41 Bosted Target warm up
  • 155923 05/09/08 08:04 cdaq Beam Time Accounting
  • 155922 05/09/08 06:44 silviu Target: sc vacuum update, alarm reset
  • 155921 05/09/08 06:27 silviu Target: fan stop, ioc reboot, tgt screens shot, acc vacuum
  • 155920 05/09/08 04:37
  • 155919 05/09/08 03:52 silviu target: sc vacuum
  • 155918 05/09/08 02:15 silviu Target: sc vacuum fit update
  • 155917 05/09/08 01:01 Perdrisat Stopping data taking, why?
  • 155916 05/09/08 01:00 Perdrisat Stopping data taking, why?
  • 155915 05/09/08 00:24 smithg Target: vacuum decision
  • 155914 05/09/08 00:24 Rondon Shift summary
  • 155913 05/09/08 00:08 cdaq Beam Time Accounting
  • Thursday

  • 155912 05/08/08 23:50 jinhuang Target: JT Valve to 14-15%
  • 155911 05/08/08 23:47 Rondon Experiment update
  • 155910 05/08/08 23:40 jinhuang Target: ScreenShot, start closing JT Valve
  • 155909 05/08/08 23:39 ccbutu@jlab. Target: Target going down!
  • 155908 05/08/08 23:12 Rondon Target and beam options
  • 155907 05/08/08 22:57 jinhuang Target: Another Jump on target vacuum pressure
  • 155906 05/08/08 22:52 Rondon Beam update
  • 155905 05/08/08 21:55 Rondon Beam update
  • 155904 05/08/08 19:20 Rondon Beam may be restored in one hour
  • 155903 05/08/08 18:00 jinhuang Target: Jump on Target Vac Pressure Observed
  • 155902 05/08/08 17:48 jinhuang target: JT valve setting recovered
  • 155901 05/08/08 17:38 jinhuang Target: halfway to normal JT valve setting
  • 155900 05/08/08 17:33 cdaq End of Run 70266:
  • 155899 05/08/08 17:32 cdaq Run 70266: cosmic
  • 155898 05/08/08 17:29 jinhuang Target: screenshot
  • 155897 05/08/08 17:17 puckett changed gpbeam in KINEMATICS.db from 5.714 to 5.712 starting with run 69975
  • 155896 05/08/08 16:56 cdaq End of Run 70265:
  • 155895 05/08/08 16:55 cdaq Run 70265: SANE test, pulser in bigcal as trigger
  • 155894 05/08/08 16:50 puckett more database updates--changed bigcal_height and gbeam_yoff
  • 155893 05/08/08 16:47 cdaq End of Run 70264:
  • 155892 05/08/08 16:47 cdaq Run 70264: SANE test, pulser trigger
  • 155891 05/08/08 16:46 cdaq End of Run 70263:
  • 155890 05/08/08 16:42 cdaq Run 70263: SANE test, pulser trigger
  • 155889 05/08/08 16:40 cdaq End of Run 70262:
  • 155888 05/08/08 16:33 cdaq Run 70262: SANE test, pulser trigger
  • 155887 05/08/08 16:26 puckett replay database updates
  • 155886 05/08/08 16:14 M Jones Change HMS S1S0X1 trigger
  • 155884 05/08/08 16:11 M Jones Measured S0 disc threshold at 25mV
  • 155883 05/08/08 16:07 cdaq Beam Time Accounting
  • 155881 05/08/08 14:49 W. Luo Turn off BigCal LED system
  • 155880 05/08/08 14:48 cdaq End of Run 70261:
  • 155879 05/08/08 14:46 cdaq Run 70261: BigCal LED run
  • 155878 05/08/08 14:38 cdaq End of Run 70260:
  • 155877 05/08/08 14:36 cdaq Run 70260: BigCal LED run
  • 155876 05/08/08 14:29 cdaq End of Run 70259:
  • 155875 05/08/08 14:27 cdaq Run 70259: BigCal LED run
  • 155874 05/08/08 14:27 L. Zhu work on the stairway--done
  • 155873 05/08/08 14:13 cdaq End of Run 70258:
  • 155872 05/08/08 14:11 cdaq Run 70258: BigCal LED run
  • 155871 05/08/08 14:06 L. Zhu target: screenshot
  • 155870 05/08/08 14:03 cdaq End of Run 70257:
  • 155869 05/08/08 14:02 cdaq Run 70257: BigCal LED run
  • 155868 05/08/08 13:53 puckett updated Analyzer CVS and main Analyzer directory on cdaq--compiling and testing
  • 155867 05/08/08 13:52 cdaq End of Run 70256:
  • 155866 05/08/08 13:50 cdaq Run 70256: BigCal LED run
  • 155865 05/08/08 13:41 cdaq End of Run 70255:
  • 155864 05/08/08 13:40 cdaq Run 70255: BigCal LED run
  • 155863 05/08/08 13:39 silviu Target: sc vacuum fit update
  • 155862 05/08/08 13:39 cdaq End of Run 70254:
  • 155861 05/08/08 13:38 cdaq Run 70254: BigCal LED run
  • 155860 05/08/08 13:14 cdaq End of Run 70253:
  • 155859 05/08/08 13:12 cdaq Run 70253: BigCal LED run
  • 155858 05/08/08 12:26 M JOnes Replaced Delay module with 32ns cable
  • 155857 05/08/08 11:40 L. Zhu target: vacuum plot
  • 155856 05/08/08 11:36 L. Zhu HMS magnets off
  • 155855 05/08/08 11:30 cdaq End of Run 70252:
  • 155854 05/08/08 11:28 cdaq Run 70252: BigCal LED run
  • 155853 05/08/08 11:14 cdaq End of Run 70251:
  • 155852 05/08/08 11:12 cdaq Run 70251: BigCal LED run
  • 155851 05/08/08 10:57 L. Zhu bigcal survey done
  • 155850 05/08/08 10:40 pking/ W. Lu The "extra" HV crate has been installed in the rack
  • 155849 05/08/08 10:21 L. Zhu Restricted Access
  • 155848 05/08/08 10:09 meekins Scattering chamber leak
  • 155847 05/08/08 09:38 W. Luo Turn off BigCal HV to move the extra crate to the rack
  • 155846 05/08/08 09:35 W. Luo Decrease HV on (04,09) by 400v
  • 155845 05/08/08 09:24 cdaq End of Run 70250:
  • 155844 05/08/08 09:23 cdaq Run 70250: BigCal LED run
  • 155843 05/08/08 08:16 cdaq End of Run 70249:
  • 155842 05/08/08 08:15 cdaq Run 70249: BigCal LED run
  • 155841 05/08/08 08:04 cdaq Beam Time Accounting
  • 155840 05/08/08 07:55 jmaxwell Owl Shift Summary, 5/8/08
  • 155839 05/08/08 07:08 J Mulholland Target: JT Valve closed during beam studies
  • 155838 05/08/08 06:56 cdaq End of Run 70248:
  • 155837 05/08/08 06:11 cdaq Run 70248: GEp-III high Q2, Production Run, ps1=1000 ps2=500 ps3=99999 ps4=200 ps5=1, FPP=3.0V BigCal_thr=230mV
  • 155836 05/08/08 06:10 cdaq End of Run 70247:
  • 155835 05/08/08 05:56 J Mulholland Target: Vacuum plots (leveling off?)
  • 155834 05/08/08 05:20
  • 155833 05/08/08 04:55 cdaq Run 70247: GEp-III high Q2, Production Run, ps1=1000 ps2=500 ps3=99999 ps4=200 ps5=1, FPP=3.0V BigCal_thr=230mV
  • 155832 05/08/08 04:54 cdaq End of Run 70246:
  • 155831 05/08/08 03:45 J Mulholland Target: Vacuum Pressure
  • 155830 05/08/08 03:43 J Mulholland Target: Strip charts of event
  • 155829 05/08/08 03:42 J Mulholland Target: IOC Reboot-- PID loop failure?
  • 155828 05/08/08 03:41 cdaq Run 70246: GEp-III high Q2, Production Run, ps1=1000 ps2=500 ps3=99999 ps4=200 ps5=1, FPP=3.0V BigCal_thr=230mV
  • 155827 05/08/08 03:36 cdaq End of Run 70245:
  • 155826 05/08/08 03:04 cdaq Run 70245: GEp-III high Q2, Production Run, ps1=1000 ps2=500 ps3=99999 ps4=200 ps5=1, FPP=3.0V BigCal_thr=230mV
  • 155825 05/08/08 03:03 cdaq End of Run 70244:
  • 155824 05/08/08 02:02 cdaq Run 70244: GEp-III high Q2, Production Run, ps1=1000 ps2=500 ps3=99999 ps4=200 ps5=1, FPP=3.0V BigCal_thr=230mV
  • 155823 05/08/08 02:01 cdaq End of Run 70243:
  • 155822 05/08/08 01:27 cdaq Run 70243: GEp-III high Q2, Production Run, ps1=1000 ps2=500 ps3=99999 ps4=200 ps5=1, FPP=3.0V BigCal_thr=230mV
  • 155821 05/08/08 01:26 cdaq End of Run 70242:
  • 155820 05/08/08 00:29 cdaq Run 70242: GEp-III high Q2, Production Run, ps1=1000 ps2=500 ps3=99999 ps4=200 ps5=1, FPP=3.0V BigCal_thr=230mV
  • 155819 05/08/08 00:28 cdaq End of Run 70241:
  • 155818 05/08/08 00:07 J Mulholland Target: GUI snapshot and Vacuum plot
  • 155817 05/08/08 00:02 cdaq Beam Time Accounting
  • 155816 05/08/08 00:00 Rondon Shift summary
  • Wednesday

  • 155815 05/07/08 23:32 jinhuang Target: status and vacuum screenshot
  • 155814 05/07/08 23:32 cdaq Run 70241: GEp-III high Q2, Production Run, ps1=1000 ps2=500 ps3=99999 ps4=200 ps5=1, FPP=3.0V BigCal_thr=230mV
  • 155813 05/07/08 23:29 cdaq End of Run 70240:
  • 155812 05/07/08 22:30 cdaq Run 70240: GEp-III high Q2, Production Run, ps1=1000 ps2=500 ps3=99999 ps4=200 ps5=1, FPP=3.0V BigCal_thr=230mV
  • 155811 05/07/08 22:29 cdaq End of Run 70239:
  • 155810 05/07/08 21:58 Rondon Chamber vacuum projections
  • 155809 05/07/08 21:29 cdaq Run 70239: GEp-III high Q2, Production Run, ps1=1000 ps2=500 ps3=99999 ps4=200 ps5=1, FPP=3.0V BigCal_thr=230mV
  • 155808 05/07/08 21:28 cdaq End of Run 70238:
  • 155807 05/07/08 20:28 cdaq Run 70238: GEp-III high Q2, Production Run, ps1=1000 ps2=500 ps3=99999 ps4=200 ps5=1, FPP=3.0V BigCal_thr=230mV
  • 155806 05/07/08 20:27 cdaq End of Run 70237:
  • 155805 05/07/08 19:45 jinhuang Target: ScreenShot
  • 155804 05/07/08 19:44 Tomasi BPM and BCM
  • 155803 05/07/08 19:31 cdaq Run 70237: GEp-III high Q2, Production Run, ps1=1000 ps2=500 ps3=99999 ps4=200 ps5=1, FPP=3.0V BigCal_thr=230mV
  • 155802 05/07/08 19:30 cdaq End of Run 70236:
  • 155801 05/07/08 19:23 Rondon Target: Expert on call phone number
  • 155800 05/07/08 18:34 cdaq Run 70236: GEp-III high Q2, Production Run, ps1=1000 ps2=500 ps3=99999 ps4=200 ps5=1, FPP=3.0V BigCal_thr=230mV
  • 155799 05/07/08 18:32 cdaq End of Run 70235:
  • 155798 05/07/08 18:01 silviu Target: target vacuum brief
  • 155797 05/07/08 17:44 Rondon Correction to run start entry for run 70235
  • 155796 05/07/08 17:34 cdaq Run 70235: GEp-III high Q2, Production Run, ps1=1000 ps2=500 ps3=99999 ps4=200 ps5=1, FPP=3.0V BigCal_thr=230mV; S0 HV -25V, S1 -40V
  • 155795 05/07/08 17:32 cdaq End of Run 70234:
  • 155794 05/07/08 17:29 Egle, Mehdi After changing HV settings for run 70234
  • 155793 05/07/08 17:26 cdaq Run 70234: GEp-III high Q2, Production Run, ps1=1000 ps2=500 ps3=99999 ps4=200 ps5=1, FPP=3.0V BigCal_thr=230mV; S0 HV -25V, S1 -40V
  • 155792 05/07/08 17:23 Rondon Target operators: pleas log scattering chamber vacuum EPICS plot
  • 155791 05/07/08 17:17 cdaq End of Run 70233:
  • 155790 05/07/08 17:14 Egle, Mehdi Changing high voltage from Run 70233 to Run 70234
  • 155789 05/07/08 17:11 cdaq Run 70233: GEp-III high Q2, Production Run, ps1=1000 ps2=500 ps3=99999 ps4=200 ps5=1, FPP=3.0V BigCal_thr=230mV
  • 155788 05/07/08 17:03 cdaq Beam Time Accounting
  • 155787 05/07/08 16:53 jinhuang target vacuum
  • 155786 05/07/08 16:52 jinhuang Target Vacuum
  • 155785 05/07/08 16:20 cdaq Run 70233: GEp-III high Q2, Production Run, ps1=1000 ps2=500 ps3=99999 ps4=200 ps5=1, FPP=3.0V BigCal_thr=230mV
  • 155784 05/07/08 16:18 cdaq End of Run 70232:
  • 155783 05/07/08 16:00 Higinbotham Shift Summary
  • 155782 05/07/08 15:56 Jonathan Mil Target SS
  • 155781 05/07/08 15:15 cdaq End of Run 70231:
  • 155780 05/07/08 14:05 cdaq Run 70231: GEp-III high Q2, Production Run, ps1=1000 ps2=500 ps3=99999 ps4=200 ps5=1, FPP=3.0V BigCal_thr=230mV
  • 155779 05/07/08 13:59 cdaq End of Run 70230:
  • 155778 05/07/08 13:11 cdaq Run 70230: GEp-III high Q2, Production Run, ps1=1000 ps2=500 ps3=99999 ps4=200 ps5=1, FPP=3.0V BigCal_thr=230mV
  • 155777 05/07/08 13:06 cdaq End of Run 70229:
  • 155776 05/07/08 12:13 cdaq Run 70229: GEp-III high Q2, Production Run, ps1=1000 ps2=500 ps3=99999 ps4=200 ps5=1, FPP=3.0V BigCal_thr=230mV
  • 155775 05/07/08 12:12 cdaq End of Run 70228:
  • 155774 05/07/08 11:21 cdaq Run 70228: GEp-III high Q2, Production Run, ps1=1000 ps2=500 ps3=99999 ps4=200 ps5=1, FPP=3.0V BigCal_thr=230mV
  • 155773 05/07/08 11:18 cdaq End of Run 70227:
  • 155772 05/07/08 11:14 bhovik Changing by 25V S0
  • 155771 05/07/08 11:09 bhovik Next HV change on S1X and S1Y
  • 155770 05/07/08 11:09 bhovik Next HV change on S1X and S1Y
  • 155769 05/07/08 11:08 bhovik Next HV change on S1X and S1Y
  • 155768 05/07/08 10:48 cdaq Run 70227: GEp-III high Q2, Production Run, ps1=1000 ps2=500 ps3=99999 ps4=200 ps5=1, FPP=3.0V BigCal_thr=230mV
  • 155767 05/07/08 10:25 cdaq End of Run 70226:
  • 155766 05/07/08 10:22 Jonathan Mil Target Vacuum
  • 155765 05/07/08 09:31 cdaq Run 70226: GEp-III high Q2, Production Run, ps1=1000 ps2=500 ps3=99999 ps4=200 ps5=1, FPP=3.0V BigCal_thr=230mV
  • 155764 05/07/08 09:22 cdaq End of Run 70225:
  • 155763 05/07/08 09:22 bhovik PART3 S1X and S1Y HV
  • 155762 05/07/08 09:21 bhovik PART 2 S1X and S1Y HV
  • 155761 05/07/08 09:20 bhovik S1X and S1Y HV before change PART1
  • 155760 05/07/08 09:02 cdaq Run 70225: GEp-III high Q2, Production Run, ps1=1000 ps2=500 ps3=99999 ps4=200 ps5=1, FPP=3.0V BigCal_thr=230mV
  • 155759 05/07/08 08:44 cdaq End of Run 70224:
  • 155758 05/07/08 08:44 Bosted Target Scatt Chmbr Vacuum
  • 155757 05/07/08 08:00 cdaq Beam Time Accounting
  • 155756 05/07/08 07:59 jmaxwell Owl Shift Summary, 5/7/2008
  • 155755 05/07/08 07:40 cdaq Run 70224: GEp-III high Q2, Production Run, ps1=1000 ps2=500 ps3=99999 ps4=200 ps5=1, FPP=3.0V BigCal_thr=230mV
  • 155754 05/07/08 07:39 cdaq End of Run 70223:
  • 155753 05/07/08 06:40 cdaq Run 70223: GEp-III high Q2, Production Run, ps1=1000 ps2=500 ps3=99999 ps4=200 ps5=1, FPP=3.0V BigCal_thr=230mV
  • 155752 05/07/08 06:38 cdaq End of Run 70222:
  • 155751 05/07/08 06:23 jmaxwell VESDA Faults
  • 155750 05/07/08 06:03 cdaq Run 70222: GEp-III high Q2, Production Run, ps1=1000 ps2=500 ps3=99999 ps4=200 ps5=1, FPP=3.0V BigCal_thr=230mV
  • 155749 05/07/08 06:02 cdaq End of Run 70221:
  • 155748 05/07/08 05:21
  • 155747 05/07/08 05:02 J Mulholland Target: IOC Reboot
  • 155746 05/07/08 04:58 cdaq Run 70221: GEp-III high Q2, Production Run, ps1=1000 ps2=500 ps3=99999 ps4=200 ps5=1, FPP=3.0V BigCal_thr=230mV
  • 155745 05/07/08 04:58 cdaq End of Run 70220:
  • 155744 05/07/08 04:28 cdaq Run 70220: GEp-III high Q2, Production Run, ps1=1000 ps2=500 ps3=99999 ps4=200 ps5=1, FPP=3.0V BigCal_thr=230mV
  • 155743 05/07/08 04:27 cdaq End of Run 70219:
  • 155742 05/07/08 03:28 cdaq Run 70219: GEp-III high Q2, Production Run, ps1=1000 ps2=500 ps3=99999 ps4=200 ps5=1, FPP=3.0V BigCal_thr=230mV
  • 155741 05/07/08 03:28 cdaq End of Run 70218:
  • 155740 05/07/08 02:31 cdaq Run 70218: GEp-III high Q2, Production Run, ps1=1000 ps2=500 ps3=99999 ps4=200 ps5=1, FPP=3.0V BigCal_thr=230mV
  • 155739 05/07/08 02:30 cdaq End of Run 70217:
  • 155738 05/07/08 01:29 cdaq Run 70217: GEp-III high Q2, Production Run, ps1=1000 ps2=500 ps3=99999 ps4=200 ps5=1, FPP=3.0V BigCal_thr=230mV
  • 155737 05/07/08 01:28 cdaq End of Run 70216:
  • 155736 05/07/08 00:52 J Mulholland Target: Transient HPH Alarms
  • 155735 05/07/08 00:29 cdaq Run 70216: GEp-III high Q2, Production Run, ps1=1000 ps2=500 ps3=99999 ps4=200 ps5=1, FPP=3.0V BigCal_thr=230mV
  • 155734 05/07/08 00:28 cdaq End of Run 70215:
  • 155733 05/07/08 00:14 cdaq Beam Time Accounting
  • 155732 05/07/08 00:07 J Mulholland Target: Snapshot of GUI and Vacuum Plot
  • 155731 05/07/08 00:04 kohlm summary swing shift 2008/05/06
  • Tuesday

  • 155730 05/06/08 23:32 kohlm roc13 crashed again
  • 155729 05/06/08 23:26 cdaq Run 70215: GEp-III high Q2, Production Run, ps1=1000 ps2=500 ps3=99999 ps4=200 ps5=1, FPP=3.0V BigCal_thr=230mV
  • 155728 05/06/08 23:08 adaniel Target: scattering chamber
  • 155727 05/06/08 23:04 kohlm roc13 crashed
  • 155726 05/06/08 23:01 kohlm Beam: bpm/bcm end of swing
  • 155725 05/06/08 22:58 Soloviev Analysis: Time shift big_cal vs HMS
  • 155724 05/06/08 22:51 Soloviev Analysis: Time shift big_cal vs HMS
  • 155723 05/06/08 22:48 cdaq Run 70214: GEp-III high Q2, Production Run, ps1=1000 ps2=500 ps3=99999 ps4=200 ps5=1, FPP=3.0V BigCal_thr=230mV
  • 155722 05/06/08 22:09 kohlm VESDA alarm
  • 155721 05/06/08 22:06 cdaq Run 70213: GEp-III high Q2, Production Run, ps1=1000 ps2=500 ps3=99999 ps4=200 ps5=1, FPP=3.0V BigCal_thr=230mV
  • 155720 05/06/08 21:54 cdaq End of Run 70212:
  • 155719 05/06/08 21:44 cdaq Run 70212: GEp-III high Q2, Production Run, ps1=1000 ps2=500 ps3=99999 ps4=200 ps5=1, FPP=3.0V BigCal_thr=230mV
  • 155718 05/06/08 21:43 cdaq End of Run 70211:
  • 155717 05/06/08 20:45 cdaq Run 70211: GEp-III high Q2, Production Run, ps1=1000 ps2=500 ps3=99999 ps4=200 ps5=1, FPP=3.0V BigCal_thr=230mV
  • 155716 05/06/08 20:43 cdaq End of Run 70210:
  • 155715 05/06/08 19:44 cdaq Run 70210: GEp-III high Q2, Production Run, ps1=1000 ps2=500 ps3=99999 ps4=200 ps5=1, FPP=3.0V BigCal_thr=230mV
  • 155714 05/06/08 19:42 cdaq End of Run 70209:
  • 155713 05/06/08 19:30 adaniel Target: update on vacuum issue
  • 155712 05/06/08 18:47 cdaq Run 70209: GEp-III high Q2, Production Run, ps1=1000 ps2=500 ps3=99999 ps4=200 ps5=1, FPP=3.0V BigCal_thr=230mV
  • 155711 05/06/08 18:47 cdaq End of Run 70208:
  • 155710 05/06/08 17:50 cdaq Run 70208: GEp-III high Q2, Production Run, ps1=1000 ps2=500 ps3=99999 ps4=200 ps5=1, FPP=3.0V BigCal_thr=230mV
  • 155709 05/06/08 17:49 cdaq End of Run 70207:
  • 155708 05/06/08 17:23 smithg Target: Actions to take if vacuum exceeds 1x10^-5 Torr. Also some repair time estimates.
  • 155707 05/06/08 16:51 cdaq Run 70207: GEp-III high Q2, Production Run, ps1=1000 ps2=500 ps3=99999 ps4=200 ps5=1, FPP=3.0V BigCal_thr=230mV
  • 155706 05/06/08 16:50 cdaq End of Run 70206:
  • 155705 05/06/08 16:11 adaniel Target: gui
  • 155704 05/06/08 15:57 Higinbotham Shift Summary
  • 155703 05/06/08 15:54 Rondon BPM and BCM
  • 155702 05/06/08 15:53 cdaq Run 70206: GEp-III high Q2, Production Run, ps1=1000 ps2=500 ps3=99999 ps4=200 ps5=1, FPP=3.0V BigCal_thr=230mV
  • 155701 05/06/08 15:51 cdaq End of Run 70205:
  • 155700 05/06/08 15:26 Higinbotham ROC13 Hang
  • 155699 05/06/08 15:20 W. Luo Change golden run to 70204 for all the online replay GUI
  • 155698 05/06/08 14:56 cdaq Run 70205: GEp-III high Q2, Production Run, ps1=1000 ps2=500 ps3=99999 ps4=200 ps5=1, FPP=3.0V BigCal_thr=230mV
  • 155697 05/06/08 14:47 Rondon Small spike in BigCal trigger is gone
  • 155696 05/06/08 14:28 Rondon Increased HMS S0 HV by 25 V
  • 155695 05/06/08 14:23 cdaq Run 70204: GEp-III high Q2, Production Run, ps1=1000 ps2=500 ps3=99999 ps4=200 ps5=1, FPP=3.0V BigCal_thr=230mV
  • 155694 05/06/08 14:20 cdaq End of Run 70203:
  • 155693 05/06/08 13:43 Rondon HMS vs BigCal coin timing after HMS timing shift
  • 155692 05/06/08 13:31 Rondon HMS timing change starting run 70203
  • 155691 05/06/08 13:15 L. Zhu Target: screenshot
  • 155690 05/06/08 13:13 Higinbotham Beam Back
  • 155689 05/06/08 13:12 cdaq Run 70203: GEp-III high Q2, Production Run, ps1=1000 ps2=500 ps3=99999 ps4=200 ps5=1, FPP=3.0V BigCal_thr=230mV
  • 155688 05/06/08 13:01 cdaq End of Run 70202:
  • 155687 05/06/08 13:01 cdaq Run 70202: cosmic
  • 155686 05/06/08 12:56 W. Luo Checked signal from 4AB
  • 155685 05/06/08 12:28 smithg Target: Status of vacuum leak: bad news
  • 155684 05/06/08 12:24 cdaq End of Run 70201:
  • 155683 05/06/08 12:23 cdaq Run 70201: sane adc test
  • 155682 05/06/08 12:22 cdaq End of Run 70200:
  • 155681 05/06/08 12:16 cdaq Run 70200: sane adc test
  • 155680 05/06/08 12:12 cdaq Run 70199: sane adc test
  • 155679 05/06/08 12:11 W. Luo Load new HV from hv_70029.new, calibration using run 70158-70198
  • 155678 05/06/08 11:40 kenyon Water by SOS and vacuum
  • 155677 05/06/08 11:35 Fowler HMS Spectrometer rotation gui reset
  • 155676 05/06/08 11:16 L. Zhu target: vacuum
  • 155675 05/06/08 10:15 Higinbotham Scattering Chamber Gate Values
  • 155674 05/06/08 10:15 Rondon Radiation levels at BigCal
  • 155673 05/06/08 10:08 Higinbotham Controlled Access
  • 155672 05/06/08 09:27 Fowler Dipole Ln2 level and JT4
  • 155671 05/06/08 09:21 Fowler Q2 Hall probe
  • 155670 05/06/08 09:02 cdaq End of Run 70198:
  • 155669 05/06/08 08:24 cdaq Beam Time Accounting
  • 155668 05/06/08 08:16 Fowler Cell phone number
  • 155667 05/06/08 08:03 cdaq Run 70198: GEp-III high Q2, Production Run, ps1=1000 ps2=500 ps3=99999 ps4=200 ps5=1, FPP=3.0V BigCal_thr=230mV
  • 155666 05/06/08 08:02 cdaq End of Run 70197:
  • 155665 05/06/08 07:55 A. Puckett Owl shift summary 05/06
  • 155664 05/06/08 07:30 puckett LN2 @ 36%--beam studies today during day shift
  • 155663 05/06/08 07:11 J Mulholland Target: Alarms off-- loop 2
  • 155662 05/06/08 07:03 JMulholland Target : IOC Reboot
  • 155661 05/06/08 06:54 cdaq Run 70197: GEp-III high Q2, Production Run, ps1=1000 ps2=500 ps3=99999 ps4=200 ps5=1, FPP=3.0V BigCal_thr=230mV
  • 155660 05/06/08 06:48 cdaq End of Run 70196:
  • 155659 05/06/08 06:36 puckett what is the cell phone number?
  • 155658 05/06/08 06:27 Lassiter LN2 of the Dipole
  • 155657 05/06/08 06:19 jmaxwell BCM, BPM Screenshot
  • 155656 05/06/08 06:14 J Mulholland Target: HPH alarm
  • 155655 05/06/08 06:10 puckett HMS LN2 level now falling faster--please respond
  • 155654 05/06/08 05:54 puckett new development on HMS Dipole JT4 alarm--new status indicator lit up
  • 155653 05/06/08 05:42 cdaq Run 70196: GEp-III high Q2, Production Run, ps1=1000 ps2=500 ps3=99999 ps4=200 ps5=1, FPP=3.0V BigCal_thr=230mV
  • 155652 05/06/08 05:41 cdaq End of Run 70195:
  • 155651 05/06/08 05:17 puckett Dipole LN2 53% and dropping at 4%/hour
  • 155650 05/06/08 04:32 cdaq Run 70195: GEp-III high Q2, Production Run, ps1=1000 ps2=500 ps3=99999 ps4=200 ps5=1, FPP=3.0V BigCal_thr=230mV
  • 155649 05/06/08 04:31 cdaq End of Run 70194:
  • 155648 05/06/08 04:24 puckett HMS Dipole LN2 level still falling--paged Steve Lassiter
  • 155647 05/06/08 03:38 puckett HMS Dipole LN2 level
  • 155646 05/06/08 03:25 cdaq Run 70194: GEp-III high Q2, Production Run, ps1=1000 ps2=500 ps3=99999 ps4=200 ps5=1, FPP=3.0V BigCal_thr=230mV
  • 155645 05/06/08 03:24 cdaq End of Run 70193:
  • 155644 05/06/08 03:08 puckett HMS Dipole valves "alarm"
  • 155643 05/06/08 02:37 puckett rebooted ROC12
  • 155642 05/06/08 02:15 cdaq Run 70193: GEp-III high Q2, Production Run, ps1=1000 ps2=500 ps3=99999 ps4=200 ps5=1, FPP=3.0V BigCal_thr=230mV
  • 155641 05/06/08 02:12 cdaq End of Run 70192:
  • 155640 05/06/08 02:11 cdaq Run 70192: GEp-III high Q2, Production Run, ps1=1000 ps2=500 ps3=99999 ps4=200 ps5=1, FPP=3.0V BigCal_thr=230mV
  • 155639 05/06/08 02:10 cdaq End of Run 70191:
  • 155638 05/06/08 00:58 cdaq Run 70191: GEp-III high Q2, Production Run, ps1=1000 ps2=500 ps3=99999 ps4=200 ps5=1, FPP=3.0V BigCal_thr=230mV
  • 155637 05/06/08 00:57 cdaq End of Run 70190:
  • 155636 05/06/08 00:02 J Mulholland Target: Beginning of Shift screenshot
  • 155635 05/06/08 00:01 cdaq Beam Time Accounting
  • 155634 05/06/08 00:00 pking Swing shift summary
  • Monday

  • 155633 05/05/08 23:43 cdaq Run 70190: GEp-III high Q2, Production Run, ps1=1000 ps2=500 ps3=99999 ps4=200 ps5=1, FPP=3.0V BigCal_thr=230mV
  • 155632 05/05/08 23:42 cdaq End of Run 70189:
  • 155631 05/05/08 22:24 cdaq Run 70189: GEp-III high Q2, Production Run, ps1=1000 ps2=500 ps3=99999 ps4=200 ps5=1, FPP=3.0V BigCal_thr=230mV
  • 155630 05/05/08 22:23 cdaq End of Run 70188:
  • 155629 05/05/08 21:12 cdaq Run 70188: GEp-III high Q2, Production Run, ps1=1000 ps2=500 ps3=99999 ps4=200 ps5=1, FPP=3.0V BigCal_thr=230mV
  • 155628 05/05/08 21:11 cdaq End of Run 70187:
  • 155626 05/05/08 20:26 Egle bpm/bcm run 70187
  • 155625 05/05/08 20:06 cdaq Run 70187: GEp-III high Q2, Production Run, ps1=1000 ps2=500 ps3=99999 ps4=200 ps5=1, FPP=3.0V BigCal_thr=230mV
  • 155624 05/05/08 20:04 cdaq End of Run 70186:
  • 155623 05/05/08 19:05 adaniel Target: screen shot
  • 155622 05/05/08 18:58 cdaq Run 70186: GEp-III high Q2, Production Run, ps1=1000 ps2=500 ps3=99999 ps4=200 ps5=1, FPP=3.0V BigCal_thr=230mV
  • 155621 05/05/08 18:50 pking Target: LH2 target going into beam
  • 155620 05/05/08 18:41 gaskell Moller backed out
  • 155619 05/05/08 18:33 horn/gaskell Moller summary
  • 155618 05/05/08 18:22 pking Orbits are being resteered.
  • 155617 05/05/08 18:14 cdaq End of Run 70185:
  • 155616 05/05/08 18:02 cdaq Moller Run 70185: Moller HWP=IN, Wien angle=-57 deg
  • 155615 05/05/08 18:02 cdaq End of Run 70184:
  • 155614 05/05/08 17:50 cdaq Moller Run 70184: Moller HWP=IN, Wien angle=-57 deg
  • 155613 05/05/08 17:40 horn/gaskell Moller Summary - so far
  • 155612 05/05/08 17:26 gaskell Wien angle will change
  • 155611 05/05/08 17:21 smithg Target: Sunday morning's fan event
  • 155610 05/05/08 17:17 pking HMS drift chamber HV tripped off; restored it.
  • 155609 05/05/08 16:54 cdaq End of Run 70183:
  • 155608 05/05/08 16:46 cdaq Moller Run 70183: Moller HWP=IN
  • 155607 05/05/08 16:37 cdaq End of Run 70182:
  • 155606 05/05/08 16:30 cdaq Moller Run 70182: Moller HWP=IN
  • 155605 05/05/08 16:29 cdaq End of Run 70181:
  • 155604 05/05/08 16:22 cdaq Moller Run 70181: Moller HWP=IN
  • 155603 05/05/08 16:22 cdaq End of Run 70180:
  • 155602 05/05/08 16:13 cdaq Moller Run 70180: Moller HWP=IN
  • 155601 05/05/08 16:11 cdaq End of Run 70179:
  • 155600 05/05/08 16:03 cdaq Beam Time Accounting
  • 155599 05/05/08 16:02 cdaq Moller Run 70179: Moller HWP=IN
  • 155598 05/05/08 16:01 cdaq End of Run 70178:
  • 155597 05/05/08 15:55 cdaq Moller Run 70178: Moller HWP=IN
  • 155596 05/05/08 15:54 cdaq End of Run 70177:
  • 155595 05/05/08 15:50 Higinbotham Shift Summary
  • 155594 05/05/08 15:47 cdaq Moller Run 70177: Moller HWP=IN
  • 155593 05/05/08 15:42 cdaq End of Run 70176:
  • 155592 05/05/08 15:42 cdaq Moller Run 70176: Moller tune test
  • 155591 05/05/08 13:09 gaskell Wien angle has been changed to -47 degrees
  • 155590 05/05/08 13:00 Jonathan Mil Target moved
  • 155589 05/05/08 12:59 cdaq End of Run 70175:
  • 155588 05/05/08 12:59 cdaq Moller Run 70175: Moller DAQ test
  • 155587 05/05/08 12:50 cdaq End of Run 70174:
  • 155586 05/05/08 12:34 cdaq Run 70174: GEp-III high Q2, Production Run, ps1=1000 ps2=500 ps3=99999 ps4=200 ps5=1, FPP=3.0V BigCal_thr=230mV
  • 155585 05/05/08 12:33 cdaq End of Run 70173:
  • 155584 05/05/08 11:32 cdaq Run 70173: GEp-III high Q2, Production Run, ps1=1000 ps2=500 ps3=99999 ps4=200 ps5=1, FPP=3.0V BigCal_thr=230mV
  • 155583 05/05/08 11:29 cdaq End of Run 70172:
  • 155582 05/05/08 11:28 cdaq Run 70172: GEp-III high Q2, Production Run, ps1=1000 ps2=500 ps3=99999 ps4=200 ps5=1, FPP=3.0V BigCal_thr=230mV
  • 155581 05/05/08 11:19 cdaq End of Run 70171:
  • 155580 05/05/08 10:14 cdaq Run 70171: GEp-III high Q2, Production Run, ps1=1000 ps2=500 ps3=99999 ps4=200 ps5=1, FPP=3.0V BigCal_thr=230mV
  • 155579 05/05/08 08:45 cdaq End of Run 70170:
  • 155578 05/05/08 08:26 cdaq Run 70170: GEp-III high Q2, Production Run, ps1=1000 ps2=500 ps3=99999 ps4=200 ps5=1, FPP=3.0V BigCal_thr=230mV
  • 155577 05/05/08 08:20 Bosted Scattering Chamber Vacuum
  • 155576 05/05/08 08:14 cdaq End of Run 70169:
  • 155575 05/05/08 08:02 cdaq Beam Time Accounting
  • 155574 05/05/08 07:52 puckett Owl shift summary, 5/5/08
  • 155573 05/05/08 07:45 M.M Target screenshot
  • 155572 05/05/08 07:10 cdaq Run 70169: GEp-III high Q2, Production Run, ps1=1000 ps2=500 ps3=99999 ps4=200 ps5=1, FPP=3.0V BigCal_thr=230mV
  • 155571 05/05/08 07:10 cdaq End of Run 70168:
  • 155570 05/05/08 06:07 cdaq Run 70168: GEp-III high Q2, Production Run, ps1=1000 ps2=500 ps3=99999 ps4=200 ps5=1, FPP=3.0V BigCal_thr=230mV
  • 155569 05/05/08 06:06 cdaq End of Run 70167:
  • 155568 05/05/08 05:17 M.M Target IOC reboot
  • 155567 05/05/08 05:00 cdaq Run 70167: GEp-III high Q2, Production Run, ps1=1000 ps2=500 ps3=99999 ps4=200 ps5=1, FPP=3.0V BigCal_thr=230mV
  • 155566 05/05/08 04:51 cdaq End of Run 70166:
  • 155565 05/05/08 03:45 cdaq Run 70166: GEp-III high Q2, Production Run, ps1=1000 ps2=500 ps3=99999 ps4=200 ps5=1, FPP=3.0V BigCal_thr=230mV
  • 155564 05/05/08 03:44 cdaq End of Run 70165:
  • 155563 05/05/08 03:34 S. Frullani BPM & BCM
  • 155562 05/05/08 02:41 cdaq Run 70165: GEp-III high Q2, Production Run, ps1=1000 ps2=500 ps3=99999 ps4=200 ps5=1, FPP=3.0V BigCal_thr=230mV
  • 155561 05/05/08 02:40 cdaq End of Run 70164:
  • 155560 05/05/08 01:38 cdaq Run 70164: GEp-III high Q2, Production Run, ps1=1000 ps2=500 ps3=99999 ps4=200 ps5=1, FPP=3.0V BigCal_thr=230mV
  • 155559 05/05/08 01:37 cdaq End of Run 70163:
  • 155558 05/05/08 00:34 cdaq Run 70163: GEp-III high Q2, Production Run, ps1=1000 ps2=500 ps3=99999 ps4=200 ps5=1, FPP=3.0V BigCal_thr=230mV
  • 155557 05/05/08 00:32 puckett MCC calls, beam is off, RF cavity restore, "few minutes" expected downtime
  • 155556 05/05/08 00:22 cdaq End of Run 70162:
  • 155555 05/05/08 00:14 cdaq Run 70162: GEp-III high Q2, Production Run, ps1=1000 ps2=500 ps3=99999 ps4=200 ps5=1, FPP=3.0V BigCal_thr=230mV
  • 155554 05/05/08 00:14 cdaq End of Run 70161:
  • 155553 05/05/08 00:00 cdaq Beam Time Accounting
  • 155552 05/05/08 00:00 pking Swing shift summary
  • Sunday

  • 155551 05/04/08 23:09 cdaq Run 70161: GEp-III high Q2, Production Run, ps1=1000 ps2=500 ps3=99999 ps4=200 ps5=1, FPP=3.0V BigCal_thr=230mV
  • 155550 05/04/08 23:08 cdaq End of Run 70160:
  • 155549 05/04/08 22:06 cdaq Run 70160: GEp-III high Q2, Production Run, ps1=1000 ps2=500 ps3=99999 ps4=200 ps5=1, FPP=3.0V BigCal_thr=230mV
  • 155548 05/04/08 22:06 cdaq End of Run 70159:
  • 155547 05/04/08 21:49 cdaq Run 70159: GEp-III high Q2, Production Run, ps1=1000 ps2=500 ps3=99999 ps4=200 ps5=1, FPP=3.0V BigCal_thr=230mV
  • 155546 05/04/08 21:48 cdaq End of Run 70158:
  • 155545 05/04/08 21:21 pking BCM and BPM screenshots for checklist
  • 155544 05/04/08 20:47 cdaq Run 70158: GEp-III high Q2, Production Run, ps1=1000 ps2=500 ps3=99999 ps4=200 ps5=1, FPP=3.0V BigCal_thr=230mV
  • 155543 05/04/08 20:47 cdaq End of Run 70157:
  • 155542 05/04/08 19:45 cdaq Run 70157: GEp-III high Q2, Production Run, ps1=1000 ps2=500 ps3=99999 ps4=200 ps5=1, FPP=3.0V BigCal_thr=230mV
  • 155541 05/04/08 19:44 cdaq End of Run 70156:
  • 155540 05/04/08 18:40 cdaq Run 70156: GEp-III high Q2, Production Run, ps1=1000 ps2=500 ps3=99999 ps4=200 ps5=1, FPP=3.0V BigCal_thr=230mV
  • 155539 05/04/08 18:39 cdaq End of Run 70155:
  • 155538 05/04/08 17:41 cdaq Run 70155: GEp-III high Q2, Production Run, ps1=1000 ps2=500 ps3=99999 ps4=200 ps5=1, FPP=3.0V BigCal_thr=230mV
  • 155537 05/04/08 17:40 cdaq End of Run 70154:
  • 155536 05/04/08 16:42 cdaq Run 70154: GEp-III high Q2, Production Run, ps1=1000 ps2=500 ps3=99999 ps4=200 ps5=1, FPP=3.0V BigCal_thr=230mV
  • 155535 05/04/08 16:41 cdaq End of Run 70153:
  • 155534 05/04/08 16:40 pking CHC needs more coffee filters
  • 155533 05/04/08 16:09 bogdanw shift summary
  • 155532 05/04/08 16:07 cdaq Beam Time Accounting
  • 155531 05/04/08 15:54 piskunov target snapshot
  • 155530 05/04/08 15:41 cdaq Run 70153: GEp-III high Q2, Production Run, ps1=1000 ps2=500 ps3=99999 ps4=200 ps5=1, FPP=3.0V BigCal_thr=230mV
  • 155529 05/04/08 15:31 cdaq End of Run 70152:
  • 155528 05/04/08 15:21 cdaq Run 70152: GEp-III high Q2, Production Run, ps1=1000 ps2=500 ps3=99999 ps4=200 ps5=1, FPP=3.0V BigCal_thr=230mV
  • 155527 05/04/08 15:19 cdaq End of Run 70151:
  • 155526 05/04/08 14:16 puckett no problem--check beam current at start of run
  • 155525 05/04/08 14:14 cdaq Run 70151: GEp-III high Q2, Production Run, ps1=1000 ps2=500 ps3=99999 ps4=200 ps5=1, FPP=3.0V BigCal_thr=230mV
  • 155524 05/04/08 14:13 cdaq End of Run 70150:
  • 155523 05/04/08 13:22 bogdanw bigcal and beam dump
  • 155522 05/04/08 13:21 cdaq Run 70150: GEp-III high Q2, Production Run, ps1=1000 ps2=500 ps3=99999 ps4=200 ps5=1, FPP=3.0V BigCal_thr=230mV
  • 155521 05/04/08 13:21 cdaq End of Run 70149:
  • 155520 05/04/08 13:16 egle bcm/bpm run70149
  • 155519 05/04/08 12:55 Egle Problem to Bigcal
  • 155518 05/04/08 12:14 cdaq Run 70149: GEp-III high Q2, Production Run, ps1=1000 ps2=500 ps3=99999 ps4=200 ps5=1, FPP=3.0V BigCal_thr=230mV
  • 155517 05/04/08 12:13 cdaq End of Run 70148:
  • 155516 05/04/08 11:09 cdaq Run 70148: GEp-III high Q2, Production Run, ps1=1000 ps2=500 ps3=99999 ps4=200 ps5=1, FPP=3.0V BigCal_thr=230mV
  • 155515 05/04/08 10:11 cdaq End of Run 70147:
  • 155514 05/04/08 09:51 cdaq Run 70147: GEp-III high Q2, Production Run, ps1=1000 ps2=500 ps3=99999 ps4=200 ps5=1, FPP=3.0V BigCal_thr=230mV
  • 155513 05/04/08 09:43 cdaq End of Run 70146:
  • 155512 05/04/08 08:31 cdaq Run 70146: GEp-III high Q2, Production Run, ps1=1000 ps2=500 ps3=99999 ps4=200 ps5=1, FPP=3.0V BigCal_thr=230mV
  • 155511 05/04/08 08:30 cdaq End of Run 70145:
  • 155510 05/04/08 08:20 piskunov target snapshot
  • 155509 05/04/08 08:03 cdaq Beam Time Accounting
  • 155508 05/04/08 07:52 puckett Owl Shift Summary for 5/4/08
  • 155507 05/04/08 07:30 cdaq Run 70145: GEp-III high Q2, Production Run, ps1=1000 ps2=500 ps3=99999 ps4=200 ps5=1, FPP=3.0V BigCal_thr=230mV
  • 155506 05/04/08 07:29 cdaq End of Run 70144:
  • 155505 05/04/08 06:57 Jonathan Mil BPM and BCM
  • 155504 05/04/08 06:32 puckett CW is back!
  • 155503 05/04/08 06:30 cdaq Run 70144: GEp-III high Q2, Production Run, ps1=1000 ps2=500 ps3=99999 ps4=200 ps5=1, FPP=3.0V BigCal_thr=230mV
  • 155502 05/04/08 05:25 puckett status
  • 155501 05/04/08 03:10 puckett ended run 70143 because beam off
  • 155500 05/04/08 03:08 cdaq End of Run 70143:
  • 155499 05/04/08 02:55 cdaq Run 70143: GEp-III high Q2, Production Run, ps1=1000 ps2=500 ps3=99999 ps4=200 ps5=1, FPP=3.0V BigCal_thr=230mV
  • 155498 05/04/08 02:55 cdaq End of Run 70142:
  • 155497 05/04/08 01:50 cdaq Run 70142: GEp-III high Q2, Production Run, ps1=1000 ps2=500 ps3=99999 ps4=200 ps5=1, FPP=3.0V BigCal_thr=230mV
  • 155496 05/04/08 01:50 cdaq End of Run 70141:
  • 155494 05/04/08 00:54 puckett back in business
  • 155493 05/04/08 00:47 cdaq Run 70141: GEp-III high Q2, Production Run, ps1=1000 ps2=500 ps3=99999 ps4=200 ps5=1, FPP=3.0V BigCal_thr=230mV
  • 155492 05/04/08 00:46 cdaq End of Run 70140:
  • 155491 05/04/08 00:46 cdaq Run 70140: test
  • 155490 05/04/08 00:44 puckett power-cycled ROC2 in the hut--
  • 155489 05/04/08 00:38 cdaq End of Run 70139:
  • 155488 05/04/08 00:35 cdaq Run 70139: GEp-III high Q2, Production Run, ps1=1000 ps2=500 ps3=99999 ps4=200 ps5=1, FPP=3.0V BigCal_thr=230mV
  • 155487 05/04/08 00:34 cdaq End of Run 70138:
  • 155486 05/04/08 00:32 cdaq Beam Time Accounting
  • 155485 05/04/08 00:32 Danagoulian Target
  • 155483 05/04/08 00:21 cdaq Run 70138: GEp-III high Q2, Cosmic Run, ps1=1 ps2=1 ps3=99999 ps4=200 ps5=1, FPP=3.0V BigCal_thr=230mV
  • Saturday

  • 155482 05/03/08 23:34 wendy BCM and BPM
  • 155481 05/03/08 23:19 W. Luo Check BigCal scaler is a good way to see if crate was off.
  • 155480 05/03/08 23:10 ejensen roc2 errors
  • 155479 05/03/08 23:08 saw ROC 2 not all modules converted error
  • 155478 05/03/08 22:44 cdaq Run 70137: GEp-III high Q2, Production Run, ps1=1000 ps2=500 ps3=99999 ps4=200 ps5=1, FPP=3.0V BigCal_thr=230mV
  • 155477 05/03/08 22:41 cdaq Run 70136: GEp-III high Q2, Production Run, ps1=1000 ps2=500 ps3=99999 ps4=200 ps5=1, FPP=3.0V BigCal_thr=230mV
  • 155476 05/03/08 22:38 cdaq End of Run 70135:
  • 155475 05/03/08 22:38 cdaq Run 70135: GEp-III high Q2, Production Run, ps1=1000 ps2=500 ps3=99999 ps4=200 ps5=1, FPP=3.0V BigCal_thr=230mV
  • 155474 05/03/08 22:31 cdaq End of Run 70134:
  • 155473 05/03/08 22:30 cdaq Run 70134: GEp-III high Q2, Production Run, ps1=1000 ps2=500 ps3=99999 ps4=200 ps5=1, FPP=3.0V BigCal_thr=230mV
  • 155472 05/03/08 22:27 cdaq End of Run 70133:
  • 155471 05/03/08 22:26 cdaq Run 70133: GEp-III high Q2, Production Run, ps1=1000 ps2=500 ps3=99999 ps4=200 ps5=1, FPP=3.0V BigCal_thr=230mV
  • 155470 05/03/08 22:20 cdaq End of Run 70131:
  • 155469 05/03/08 22:19 cdaq Run 70131: GEp-III high Q2, Production Run, ps1=1000 ps2=500 ps3=99999 ps4=200 ps5=1, FPP=3.0V BigCal_thr=230mV
  • 155468 05/03/08 22:18 cdaq End of Run 70130:
  • 155467 05/03/08 22:17 cdaq Run 70130: GEp-III high Q2, Production Run, ps1=1000 ps2=500 ps3=99999 ps4=200 ps5=1, FPP=3.0V BigCal_thr=230mV
  • 155466 05/03/08 22:16 cdaq End of Run 70129:
  • 155465 05/03/08 21:07 cdaq Run 70129: GEp-III high Q2, Production Run, ps1=1000 ps2=500 ps3=99999 ps4=200 ps5=1, FPP=3.0V BigCal_thr=230mV
  • 155464 05/03/08 21:06 cdaq End of Run 70128:
  • 155463 05/03/08 20:14 ejensen hv trip
  • 155462 05/03/08 19:55 cdaq Run 70128: GEp-III high Q2, Production Run, ps1=1000 ps2=500 ps3=99999 ps4=200 ps5=1, FPP=3.0V BigCal_thr=230mV
  • 155461 05/03/08 19:53 cdaq End of Run 70127:
  • 155460 05/03/08 18:49 cdaq Run 70127: GEp-III high Q2, Production Run, ps1=1000 ps2=500 ps3=99999 ps4=200 ps5=1, FPP=3.0V BigCal_thr=230mV
  • 155459 05/03/08 18:48 cdaq End of Run 70126:
  • 155458 05/03/08 17:38 cdaq Run 70126: GEp-III high Q2, Production Run, ps1=1000 ps2=500 ps3=99999 ps4=200 ps5=1, FPP=3.0V BigCal_thr=230mV
  • 155457 05/03/08 17:36 cdaq End of Run 70125:
  • 155456 05/03/08 16:37 cdaq Run 70125: GEp-III high Q2, Production Run, ps1=1000 ps2=500 ps3=99999 ps4=200 ps5=1, FPP=3.0V BigCal_thr=230mV
  • 155455 05/03/08 16:35 cdaq End of Run 70124:
  • 155454 05/03/08 16:31 adaniel Target screen shot
  • 155453 05/03/08 16:02 cdaq Beam Time Accounting
  • 155452 05/03/08 16:02 Abdellah Day Shift Summary
  • 155451 05/03/08 15:36 cdaq Run 70124: GEp-III high Q2, Production Run, ps1=1000 ps2=500 ps3=99999 ps4=200 ps5=1, FPP=3.0V BigCal_thr=230mV
  • 155450 05/03/08 15:35 cdaq End of Run 70123:
  • 155449 05/03/08 14:46 Egle BCM & BPM
  • 155448 05/03/08 14:35 cdaq Run 70123: GEp-III high Q2, Production Run, ps1=1000 ps2=500 ps3=99999 ps4=200 ps5=1, FPP=3.0V BigCal_thr=230mV
  • 155447 05/03/08 14:34 cdaq End of Run 70122:
  • 155446 05/03/08 13:15 cdaq Run 70122: GEp-III high Q2, Production Run, ps1=1000 ps2=500 ps3=99999 ps4=200 ps5=1, FPP=3.0V BigCal_thr=230mV
  • 155445 05/03/08 12:57 cdaq End of Run 70121:
  • 155444 05/03/08 12:43 silviu target fan stopped and ioc reboot
  • 155443 05/03/08 12:04 cdaq Run 70121: GEp-III high Q2, Production Run, ps1=1000 ps2=500 ps3=99999 ps4=200 ps5=1, FPP=3.0V BigCal_thr=230mV
  • 155442 05/03/08 12:02 Abdellah Run stopped
  • 155441 05/03/08 11:38 cdaq End of Run 70120:
  • 155440 05/03/08 10:34 cdaq Run 70120: GEp-III high Q2, Production Run, ps1=1000 ps2=500 ps3=99999 ps4=200 ps5=1, FPP=3.0V BigCal_thr=230mV
  • 155439 05/03/08 10:33 cdaq End of Run 70119:
  • 155438 05/03/08 09:30 cdaq Run 70119: GEp-III high Q2, Production Run, ps1=1000 ps2=500 ps3=99999 ps4=200 ps5=1, FPP=3.0V BigCal_thr=230mV
  • 155437 05/03/08 09:29 cdaq End of Run 70118:
  • 155436 05/03/08 08:33 silviu target screens
  • 155435 05/03/08 08:20 cdaq Run 70118: GEp-III high Q2, Production Run, ps1=1000 ps2=500 ps3=99999 ps4=200 ps5=1, FPP=3.0V BigCal_thr=230mV
  • 155434 05/03/08 08:18 cdaq End of Run 70117:
  • 155433 05/03/08 08:01 Phil Carter Owl shift summary
  • 155432 05/03/08 08:01 cdaq Beam Time Accounting
  • 155431 05/03/08 07:43 piskunov histogram presentation
  • 155430 05/03/08 07:19 Phil Carter bpm and bcm screens
  • 155429 05/03/08 07:16 cdaq Run 70117: GEp-III high Q2, Production Run, ps1=1000 ps2=500 ps3=99999 ps4=200 ps5=1, FPP=3.0V BigCal_thr=230mV
  • 155428 05/03/08 07:16 cdaq End of Run 70116:
  • 155427 05/03/08 06:03 cdaq Run 70116: GEp-III high Q2, Production Run, ps1=1000 ps2=500 ps3=99999 ps4=200 ps5=1, FPP=3.0V BigCal_thr=230mV
  • 155426 05/03/08 06:02 cdaq End of Run 70115:
  • 155425 05/03/08 05:00 cdaq Run 70115: GEp-III high Q2, Production Run, ps1=1000 ps2=500 ps3=99999 ps4=200 ps5=1, FPP=3.0V BigCal_thr=230mV
  • 155424 05/03/08 04:59 cdaq End of Run 70114:
  • 155423 05/03/08 04:01 Phil Carter ROC 13 crashed
  • 155422 05/03/08 03:47 cdaq Run 70114: GEp-III high Q2, Production Run, ps1=1000 ps2=500 ps3=99999 ps4=200 ps5=1, FPP=3.0V BigCal_thr=230mV
  • 155421 05/03/08 03:08 Phil Carter HV trip
  • 155420 05/03/08 02:55 cdaq Run 70113: GEp-III high Q2, Production Run, ps1=1000 ps2=500 ps3=99999 ps4=200 ps5=1, FPP=3.0V BigCal_thr=230mV
  • 155419 05/03/08 02:52 cdaq End of Run 70112:
  • 155418 05/03/08 02:18 cdaq Run 70112: GEp-III high Q2, Production Run, ps1=1000 ps2=500 ps3=99999 ps4=200 ps5=1, FPP=3.0V BigCal_thr=230mV
  • 155417 05/03/08 02:17 cdaq End of Run 70111:
  • 155416 05/03/08 01:22 Danagoulian Beam on target
  • 155415 05/03/08 01:17 Phil Carter beam is back
  • 155414 05/03/08 01:17 cdaq Run 70111: GEp-III high Q2, Production Run, ps1=1000 ps2=500 ps3=99999 ps4=200 ps5=1, FPP=3.0V BigCal_thr=230mV
  • 155413 05/03/08 00:29 Phil Carter Should have a beam in half an hour
  • 155412 05/03/08 00:04 Danagoulian Target status
  • 155411 05/03/08 00:04 Abdellah Swing Shift Summary
  • 155410 05/03/08 00:02 cdaq Beam Time Accounting
  • Friday

  • 155409 05/02/08 22:49 Abdellah beam off
  • 155408 05/02/08 22:45 cdaq End of Run 70110:
  • 155407 05/02/08 22:01 cdaq Run 70110: GEp-III high Q2, Production Run, ps1=1000 ps2=500 ps3=99999 ps4=200 ps5=1, FPP=3.0V BigCal_thr=230mV
  • 155406 05/02/08 22:00 cdaq End of Run 70109:
  • 155405 05/02/08 20:59 cdaq Run 70109: GEp-III high Q2, Production Run, ps1=1000 ps2=500 ps3=99999 ps4=200 ps5=1, FPP=3.0V BigCal_thr=230mV
  • 155404 05/02/08 20:58 cdaq End of Run 70108:
  • 155403 05/02/08 20:37 leonid BPM/BCM snapshots
  • 155402 05/02/08 19:56 cdaq Run 70108: GEp-III high Q2, Production Run, ps1=1000 ps2=500 ps3=99999 ps4=200 ps5=1, FPP=3.0V BigCal_thr=230mV
  • 155401 05/02/08 19:55 cdaq End of Run 70107:
  • 155400 05/02/08 18:35 cdaq Run 70107: GEp-III high Q2, Production Run, ps1=1000 ps2=500 ps3=99999 ps4=200 ps5=1, FPP=3.0V BigCal_thr=230mV
  • 155399 05/02/08 18:34 cdaq End of Run 70106:
  • 155398 05/02/08 17:36 cdaq Run 70106: GEp-III high Q2, Production Run, ps1=1000 ps2=500 ps3=99999 ps4=200 ps5=1, FPP=3.0V BigCal_thr=230mV
  • 155397 05/02/08 17:35 cdaq End of Run 70105:
  • 155396 05/02/08 16:59 W. Luo BigCal HV 32-1-9 was set to -500v, HV is correct for this channel
  • 155395 05/02/08 16:37 cdaq Run 70105: GEp-III high Q2, Production Run, ps1=1000 ps2=500 ps3=99999 ps4=200 ps5=1, FPP=3.0V BigCal_thr=230mV
  • 155394 05/02/08 16:36 cdaq End of Run 70104:
  • 155393 05/02/08 16:28 adaniel Target gui
  • 155392 05/02/08 16:01 cdaq Beam Time Accounting
  • 155391 05/02/08 15:58 ransome shift summary
  • 155390 05/02/08 15:37 cdaq Run 70104: GEp-III high Q2, Production Run, ps1=1000 ps2=500 ps3=99999 ps4=200 ps5=1, FPP=3.0V BigCal_thr=230mV
  • 155389 05/02/08 15:36 cdaq End of Run 70103:
  • 155388 05/02/08 14:35 ransome beam snapshot
  • 155387 05/02/08 14:33 cdaq Run 70103: GEp-III high Q2, Production Run, ps1=1000 ps2=500 ps3=99999 ps4=200 ps5=1, FPP=3.0V BigCal_thr=230mV
  • 155386 05/02/08 14:07 cdaq End of Run 70102:
  • 155385 05/02/08 13:37 cdaq Run 70102: GEp-III high Q2, Production Run, ps1=1000 ps2=500 ps3=99999 ps4=200 ps5=1, FPP=3.0V BigCal_thr=230mV
  • 155384 05/02/08 13:31 cdaq End of Run 70101:
  • 155383 05/02/08 12:54 cdaq Run 70101: GEp-III high Q2, Production Run, ps1=1000 ps2=500 ps3=99999 ps4=200 ps5=1, FPP=3.0V BigCal_thr=230mV
  • 155382 05/02/08 12:53 cdaq End of Run 70100:
  • 155381 05/02/08 11:43 cdaq Run 70100: GEp-III high Q2, Production Run, ps1=1000 ps2=500 ps3=99999 ps4=200 ps5=1, FPP=3.0V BigCal_thr=230mV
  • 155380 05/02/08 11:41 cdaq End of Run 70099:
  • 155379 05/02/08 10:59 smithg Target: Auto reload of beam current limits
  • 155378 05/02/08 10:34 cdaq Run 70099: GEp-III high Q2, Production Run, ps1=1000 ps2=500 ps3=99999 ps4=200 ps5=1, FPP=3.0V BigCal_thr=230mV
  • 155377 05/02/08 10:33 cdaq End of Run 70098:
  • 155376 05/02/08 09:24 cdaq Run 70098: GEp-III high Q2, Production Run, ps1=1000 ps2=500 ps3=99999 ps4=200 ps5=1, FPP=3.0V BigCal_thr=230mV
  • 155375 05/02/08 09:23 cdaq End of Run 70097:
  • 155374 05/02/08 08:20 cdaq Run 70097: GEp-III high Q2, Production Run, ps1=1000 ps2=500 ps3=99999 ps4=200 ps5=1, FPP=3.0V BigCal_thr=230mV
  • 155373 05/02/08 08:17 cdaq End of Run 70096:
  • 155372 05/02/08 08:07 gaskell Target screen shot
  • 155371 05/02/08 08:01 cdaq Beam Time Accounting
  • 155370 05/02/08 08:01 pking Owl shift summary.
  • 155369 05/02/08 07:10 cdaq Run 70096: GEp-III high Q2, Production Run, ps1=1000 ps2=500 ps3=99999 ps4=200 ps5=1, FPP=3.0V BigCal_thr=230mV
  • 155368 05/02/08 07:09 cdaq End of Run 70095:
  • 155367 05/02/08 06:26 pking Shift checklist BPM/BCM screenshots
  • 155366 05/02/08 06:12 Phil Carter Target: screenshot
  • 155365 05/02/08 06:07 cdaq Run 70095: GEp-III high Q2, Production Run, ps1=1000 ps2=500 ps3=99999 ps4=200 ps5=1, FPP=3.0V BigCal_thr=230mV
  • 155364 05/02/08 06:06 cdaq End of Run 70094:
  • 155363 05/02/08 05:25
  • 155362 05/02/08 04:44 cdaq Run 70094: GEp-III high Q2, Production Run, ps1=1000 ps2=500 ps3=99999 ps4=200 ps5=1, FPP=3.0V BigCal_thr=230mV
  • 155361 05/02/08 04:43 cdaq End of Run 70093:
  • 155360 05/02/08 03:41 cdaq Run 70093: GEp-III high Q2, Production Run, ps1=1000 ps2=500 ps3=99999 ps4=200 ps5=1, FPP=3.0V BigCal_thr=230mV
  • 155359 05/02/08 03:40 cdaq End of Run 70092:
  • 155358 05/02/08 02:35 cdaq Run 70092: GEp-III high Q2, Production Run, ps1=1000 ps2=500 ps3=99999 ps4=200 ps5=1, FPP=3.0V BigCal_thr=230mV
  • 155357 05/02/08 02:34 cdaq End of Run 70091:
  • 155356 05/02/08 02:12 Phil Carter Target: modified Gep07.alarms script
  • 155355 05/02/08 01:51 Phil Carter Target: IOC reboot
  • 155354 05/02/08 01:43 pking Closed electronics room exterior doors
  • 155353 05/02/08 01:31 cdaq Run 70091: GEp-III high Q2, Production Run, ps1=1000 ps2=500 ps3=99999 ps4=200 ps5=1, FPP=3.0V BigCal_thr=230mV
  • 155352 05/02/08 01:24 cdaq End of Run 70090:
  • 155351 05/02/08 00:48 pking Electronics room AC has been fixed
  • 155350 05/02/08 00:30 cdaq Run 70090: GEp-III high Q2, Production Run, ps1=1000 ps2=500 ps3=99999 ps4=200 ps5=1, FPP=3.0V BigCal_thr=230mV
  • 155349 05/02/08 00:28 cdaq End of Run 70089:
  • 155348 05/02/08 00:01 cdaq Beam Time Accounting
  • Thursday

  • 155347 05/01/08 23:59 Abdellah Swing Shift Summary
  • 155346 05/01/08 23:58 Abdellah Swing Shift Summary
  • 155345 05/01/08 23:25 cdaq Run 70089: GEp-III high Q2, Production Run, ps1=1000 ps2=500 ps3=99999 ps4=200 ps5=1, FPP=3.0V BigCal_thr=230mV
  • 155344 05/01/08 23:24 cdaq End of Run 70088:
  • 155343 05/01/08 22:24 cdaq Run 70088: GEp-III high Q2, Production Run, ps1=1000 ps2=500 ps3=99999 ps4=200 ps5=1, FPP=3.0V BigCal_thr=230mV
  • 155342 05/01/08 22:23 cdaq End of Run 70087:
  • 155341 05/01/08 22:14 Target: Screen snapshot at 22:15pm
  • 155340 05/01/08 21:39 ransome bpm scan
  • 155339 05/01/08 21:22 cdaq Run 70087: GEp-III high Q2, Production Run, ps1=1000 ps2=500 ps3=99999 ps4=200 ps5=1, FPP=3.0V BigCal_thr=230mV
  • 155338 05/01/08 21:21 cdaq End of Run 70086:
  • 155337 05/01/08 20:20 cdaq Run 70086: GEp-III high Q2, Production Run, ps1=1000 ps2=500 ps3=99999 ps4=200 ps5=1, FPP=3.0V BigCal_thr=230mV
  • 155336 05/01/08 20:18 cdaq End of Run 70085:
  • 155335 05/01/08 19:20 Abdellah gepscop1 fixed
  • 155334 05/01/08 19:15 cdaq Run 70085: GEp-III high Q2, Production Run, ps1=1000 ps2=500 ps3=99999 ps4=200 ps5=1, FPP=3.0V BigCal_thr=230mV
  • 155333 05/01/08 19:12 cdaq End of Run 70084:
  • 155332 05/01/08 18:29 puckett For gepscope, or ROC2/13, reboot of "Hall C Switch" is needed
  • 155331 05/01/08 18:13 cdaq Run 70084: GEp-III high Q2, Production Run, ps1=1000 ps2=500 ps3=99999 ps4=200 ps5=1, FPP=3.0V BigCal_thr=230mV
  • 155330 05/01/08 18:11 cdaq End of Run 70083:
  • 155329 05/01/08 18:07 puckett may need to reboot gep3 switch and/or hall C switch--end run before attempting!
  • 155328 05/01/08 17:59 abdellah gepscope1
  • 155327 05/01/08 17:11 cdaq Run 70083: GEp-III high Q2, Production Run, ps1=1000 ps2=500 ps3=99999 ps4=200 ps5=1, FPP=3.0V BigCal_thr=230mV
  • 155326 05/01/08 17:09 cdaq End of Run 70082:
  • 155325 05/01/08 16:15 yez Target: target sreenshot at the begining of night shift
  • 155324 05/01/08 16:11 cdaq Run 70082: GEp-III high Q2, Production Run, ps1=1000 ps2=500 ps3=99999 ps4=200 ps5=1, FPP=3.0V BigCal_thr=230mV
  • 155323 05/01/08 16:10 cdaq End of Run 70081:
  • 155322 05/01/08 16:01 cdaq Beam Time Accounting
  • 155321 05/01/08 16:01 gaskell Day shift summary
  • 155320 05/01/08 15:11 cdaq Run 70081: GEp-III high Q2, Production Run, ps1=1000 ps2=500 ps3=99999 ps4=200 ps5=1, FPP=3.0V BigCal_thr=230mV
  • 155319 05/01/08 15:11 cdaq End of Run 70080:
  • 155318 05/01/08 14:55 gaskell BPM/BCM
  • 155317 05/01/08 14:46 Louis as TO Target: IOC reboot
  • 155316 05/01/08 14:13 cdaq Run 70080: GEp-III high Q2, Production Run, ps1=1000 ps2=500 ps3=99999 ps4=200 ps5=1, FPP=3.0V BigCal_thr=230mV
  • 155315 05/01/08 14:12 cdaq End of Run 70079:
  • 155314 05/01/08 13:10 cdaq Run 70079: GEp-III high Q2, Production Run, ps1=1000 ps2=500 ps3=99999 ps4=200 ps5=1, FPP=3.0V BigCal_thr=230mV
  • 155313 05/01/08 13:09 cdaq End of Run 70078:
  • 155312 05/01/08 12:26 Louis as TO Target: Not aquiet baby today, a monster!
  • 155311 05/01/08 12:05 cdaq Run 70078: GEp-III high Q2, Production Run, ps1=1000 ps2=500 ps3=99999 ps4=200 ps5=1, FPP=3.0V BigCal_thr=230mV
  • 155310 05/01/08 11:22 cdaq End of Run 70077:
  • 155309 05/01/08 10:35 cdaq Run 70077: GEp-III high Q2, Production Run, ps1=1000 ps2=500 ps3=99999 ps4=200 ps5=1, FPP=3.0V BigCal_thr=230mV
  • 155308 05/01/08 10:14 cdaq End of Run 70076:
  • 155307 05/01/08 09:28 cdaq Run 70076: GEp-III high Q2, Production Run, ps1=1000 ps2=500 ps3=99999 ps4=200 ps5=1, FPP=3.0V BigCal_thr=230mV
  • 155306 05/01/08 09:14 gaskell tune beam to Hall C
  • 155305 05/01/08 09:08 cdaq End of Run 70075:
  • 155304 05/01/08 08:50 Louis as TO Target: Screen snapshot at beginnig of Day shift
  • 155303 05/01/08 08:24 cdaq Run 70075: GEp-III high Q2, Production Run, ps1=1000 ps2=500 ps3=99999 ps4=200 ps5=1, FPP=3.0V BigCal_thr=230mV
  • 155302 05/01/08 08:20 Phil Carter Target: changing defaults?
  • 155301 05/01/08 08:19 cdaq End of Run 70074:
  • 155300 05/01/08 08:18 pking Owl shift summary
  • 155299 05/01/08 08:01 cdaq Beam Time Accounting
  • 155298 05/01/08 07:18 cdaq Run 70074: GEp-III high Q2, Production Run, ps1=1000 ps2=500 ps3=99999 ps4=200 ps5=1, FPP=3.0V BigCal_thr=230mV
  • 155297 05/01/08 07:18 cdaq End of Run 70073:
  • 155296 05/01/08 06:40
  • 155295 05/01/08 06:37 Phil Carter Target: screenshot
  • 155294 05/01/08 06:21 cdaq Run 70073: GEp-III high Q2, Production Run, ps1=1000 ps2=500 ps3=99999 ps4=200 ps5=1, FPP=3.0V BigCal_thr=230mV
  • 155293 05/01/08 06:20 cdaq End of Run 70072:
  • 155292 05/01/08 05:23 cdaq Run 70072: GEp-III high Q2, Production Run, ps1=1000 ps2=500 ps3=99999 ps4=200 ps5=1, FPP=3.0V BigCal_thr=230mV
  • 155291 05/01/08 05:22 cdaq End of Run 70071:
  • 155290 05/01/08 05:02 pking gepscope shots before and after ROC13 power cycle
  • 155289 05/01/08 04:58 cdaq Run 70071: GEp-III high Q2, Production Run, ps1=1000 ps2=500 ps3=99999 ps4=200 ps5=1, FPP=3.0V BigCal_thr=230mV
  • 155288 05/01/08 04:52 cdaq End of Run 70070:
  • 155287 05/01/08 04:52 cdaq Run 70070: GEp-III high Q2, Production Run, ps1=1000 ps2=500 ps3=99999 ps4=200 ps5=1, FPP=3.0V BigCal_thr=230mV
  • 155286 05/01/08 04:49 cdaq Run 70069: GEp-III high Q2, Production Run, ps1=1000 ps2=500 ps3=99999 ps4=200 ps5=1, FPP=3.0V BigCal_thr=230mV
  • 155284 05/01/08 04:44 cdaq End of Run 70068:
  • 155283 05/01/08 04:44 cdaq Run 70068: GEp-III high Q2, Production Run, ps1=1000 ps2=500 ps3=99999 ps4=200 ps5=1, FPP=3.0V BigCal_thr=230mV
  • 155282 05/01/08 04:39 cdaq End of Run 70067:
  • 155281 05/01/08 04:39 cdaq Run 70067: GEp-III high Q2, Production Run, ps1=1000 ps2=500 ps3=99999 ps4=200 ps5=1, FPP=3.0V BigCal_thr=230mV
  • 155280 05/01/08 04:37 cdaq End of Run 70066:
  • 155279 05/01/08 04:37 cdaq Run 70066: GEp-III high Q2, Production Run, ps1=1000 ps2=500 ps3=99999 ps4=200 ps5=1, FPP=3.0V BigCal_thr=230mV
  • 155278 05/01/08 04:35 cdaq End of Run 70065:
  • 155277 05/01/08 04:13 pking Shift checklist screenshots
  • 155276 05/01/08 03:36 cdaq Run 70065: GEp-III high Q2, Production Run, ps1=1000 ps2=500 ps3=99999 ps4=200 ps5=1, FPP=3.0V BigCal_thr=230mV
  • 155275 05/01/08 03:35 cdaq End of Run 70064:
  • 155274 05/01/08 02:31 cdaq Run 70064: GEp-III high Q2, Production Run, ps1=1000 ps2=500 ps3=99999 ps4=200 ps5=1, FPP=3.0V BigCal_thr=230mV
  • 155273 05/01/08 02:30 cdaq End of Run 70063:
  • 155272 05/01/08 02:13 cdaq Run 70063: GEp-III high Q2, Production Run, ps1=1000 ps2=500 ps3=99999 ps4=200 ps5=1, FPP=3.0V BigCal_thr=230mV
  • 155271 05/01/08 02:12 cdaq End of Run 70062:
  • 155270 05/01/08 01:10 cdaq Run 70062: GEp-III high Q2, Production Run, ps1=1000 ps2=500 ps3=99999 ps4=200 ps5=1, FPP=3.0V BigCal_thr=230mV
  • 155269 05/01/08 01:09 cdaq End of Run 70061:
  • 155268 05/01/08 00:07 cdaq Run 70061: GEp-III high Q2, Production Run, ps1=1000 ps2=500 ps3=99999 ps4=200 ps5=1, FPP=3.0V BigCal_thr=230mV
  • 155267 05/01/08 00:06 cdaq End of Run 70060:
  • 155266 05/01/08 00:02 cdaq Beam Time Accounting
    Search this logbook:

    This file generated by /group/hallc/www/hallcweb/apps/logbooks/hclog/src/hclogscript version HC2.12
    If you have any comments or problems, please contact:
    Stephen A. Wood
    saw@jlab.org
    (757) 269-7367