keyword=Beam: daily plan

There was a spot move on Sunday morning (12min). Stable beam over the weekend with some exceptions.

Beam studies tomorrow will start around 9am (<8h). MCC will only perform tests in the injector and they do not need the halls. During this time there will be an access in HC to set-up the HV lines for the qweak lumi tests (~1h). If anyone else needs to go into the hall let me know.

Run plan: Take data with as high as possible stable (trip rate <15/h) beam. Beam current 75uA