Log entry time 16:04:56 on October 20,2010

Entry number 201701

keyword=Day Shift summary

08:15 --- moved target to 1% aluminum to start Neutral axis study
08:55 --- Qtor is not on. Unable to ramp it up due to a FAULT. Unable to reset from Counting House. Control
led access for Joe to reset it manually.
09:40 --- back from controlled access. Qtor is at 8921A.
09:46 --- Resume Neutral axis study on Al-1%.
09:54 --- Change of plan: Josh is doing beam modulation study. We will do the neutral axis study when he is
done.
09:59 --- Silviu and Joe asked for an escorted controlled access to run some tests on the target temperatur
e controller.
10:57 --- Controlled access done.
11:15 --- cdaql6 crashed ==> we cannot resume the beam modulation study.
11:42 --- cdaql6 is back. Asked for beam. No beam due to injector problem.
12:45 --- MCC is ready to send beam. Josh resumed the beam modulation study
15:30 --- trigger supervisor problem.