User name leacock

Log entry time 16:42:34 on January 13, 2011

Entry number 214257

keyword=day shift summary

SL -- John Leacock, TO -- Charles Davis, 3rd -- Josh Magee

SUMMARY: Started shift with QTOR tripped. Ended shift with QTOR tripped. Some BCM work was done by Dave Mack on BCM1,2 and Keith Cole and Trent Allison worked on BCM5,6. I have no reports on the results though. We had a look at the data from last night and have some preliminary results on the position sensitivies as a function of raster.

INTEGRATED CHARGE == 0.0000000 C

DETAILS:

0800 -- asked for survey so Joe can fix QTOR

0850 -- Joe is here, ready to fix QTOR

0930 -- Survey complete, Joe and Leckey to hall to fix QTOR

0950 -- QTOR PLC is not working

0200 -- QTOR PS shielding in progress

0400 -- End of shift, no updates