    Log entry time 07:53:19 on April 10, 1999

    Entry number 11727

    keyword=Beam Time Accounting
    Hall C

    4/10/1999 0000-0800
    Experiment #: E96-003
    Shift Leader: Ashot Gasparian
    Shift Workers: V. Tadevosian, G. Niculescu

    00000100020003000400050006000700Total Time
    Acceptable Beam
    in Use
    0.5 0.0 0.0 0.0 0.0 0.0 0.0 0.5 1
    Beam Available
    but Not in Use
    .5 1. 1 .75 .8 1. 1. .5 6.55
    Beam Not Available
    or Unacceptable
    0 0 0 .25 .2 0 0 0 0.45
    Accelerator Con-
    figuration Chage
    0 0 0 0 0 0 0 0 0
    Experiment
    Ready
    .5 0 0 0 0 0 0 .5 1
    Planned Config-
    uration Change
    0 0 0 0 0 0 0 0 0
    Unplanned
    Experiment Down
    .5 1 1 1 1 1 1 .57
    Hall not
    ready reasons
    Target 0 0 0 0 0 0 0 0 0
    HMS .5 1 1 1. 1 1 1 .5 7
    SOS 0 0 0 0 0 0 0 0 0
    Data Acq 0 0 0 .15 0 0 0 .25 0.4
    Other 0 0 0 0 0 0 0 0 0

    Comments: We had problems with the HMS dipole and Q3. We called P. Brindza, there was computer osftware problem. 7:30 we back. We lost 7 houres.

    Data Entry by: A. Gasparian