    Log entry time 00:08:18 on July 16, 1999

    Entry number 14295

    keyword=Beam Time Accounting
    Hall C

    7/15/1999 1600-2400
    Experiment #: E96-003
    Shift Leader: Arrington/gao
    Shift Workers: Day, Piercy, Sawafta

    16001700180019002000210022002300Total Time
    Acceptable Beam
    in Use
    0.00000 0.00000 0.00000 0. 0. 0. 5.0 1.0 1.08333333333333
    Beam Available
    but Not in Use
    0.0000 0.00000 0.00000 0. 0.5 0.5 55.0 0 1.91666666666667
    Beam Not Available
    or Unacceptable
    1.00000 1.00000 1.00000 1. 0.5 0.5 0 0 5
    Accelerator Con-
    figuration Chage
    0.00000 0.00000 0.00000 0 0 0 0 0 0
    Experiment
    Ready
    0.00000 0.00000 0.00000 0. 0. 0.5 1.0 1.0 2.5
    Planned Config-
    uration Change
    1.00000 1.00000 1.00000 1. 1. 0.5 0 0 5.5
    Unplanned
    Experiment Down
    0.00000 0.00000 0.00000 0 0 0 0 00
    Hall not
    ready reasons
    Target 1. 1.0 1.0 0 0 0 0 0 3
    HMS 0 0 0 1.0 1.0 0.5 0 0 2.5
    SOS 0 0 0 0 0 0 0 0 0
    Data Acq 0 0 0 0 0 0 0 0 0
    Other 0 0 0 0 0 0 0 0 0

    Comments: Hall was open to liquify target for first few hours, then another ~2hrs in order to get people in to lower the cerenkov pressure. Harp scan was done after the beam is back.

    Data Entry by: Arrington/gao