Difference between revisions of "Electron Detector"
From PolWiki
Jump to navigationJump to searchLine 18: | Line 18: | ||
*** open '''Absolute''' -> on the Hall C column from the left bottom of this screen | *** open '''Absolute''' -> on the Hall C column from the left bottom of this screen | ||
*** BPM '''3P01A''', '''3P02A''', '''3P02B''' and '''3P03A''' should have finite non-zero read back | *** BPM '''3P01A''', '''3P02A''', '''3P02B''' and '''3P03A''' should have finite non-zero read back | ||
+ | * Check compton rates from the photon detector (typically 600 per uA per second) | ||
===Request beam to be taken off, for lowering the e-detector=== | ===Request beam to be taken off, for lowering the e-detector=== |
Revision as of 03:40, 19 November 2010
Standard Running Procedure
with the previous beam activity ongoing (parasitically)
- Turn ON High Voltages to the e-detector
- take a quick run to check DAQ functionality
- check analyzer functionality
- on any cdaq machine, type StripTool and pull up strip chart of the epics variables of the 4 Hall-C Chicane BPMs
- 3P01A (IPM3P01A.XPOS , IPM3PO1A.YPOS)
- 3P02A (IPM3P02A.XPOS , IPM3PO2A.YPOS)
- 3P02B (IPM3P02B.XPOS , IPM3PO2B.YPOS)
- 3P03A (IPM3P03A.XPOS , IPM3PO3A.YPOS)
Request beam to be set through the chicane and verify the same
- Check Chicane view: on any cdaq machine type edmmonticello, from the Monticello screen
- open Magnets -> Magnet Commander
- 3C -> Compton Combo
- In this Hall C Compton Control screen, the REQUESTED and ACTUAL current readbacks should be ~104 A
- open BPM -> BPM Overview
- open Absolute -> on the Hall C column from the left bottom of this screen
- BPM 3P01A, 3P02A, 3P02B and 3P03A should have finite non-zero read back
- open Magnets -> Magnet Commander
- Check compton rates from the photon detector (typically 600 per uA per second)
Request beam to be taken off, for lowering the e-detector
- Lower the e-detector to a position in accordance with current run plan
- Motion mechanism [[1]]
- begin with the program Go Home
- jog to the intended position
- Motion mechanism [[1]]
Current Run Plan
Backout Procedure
- Turn OFF HV
- Retract the detector to position defined as Go Home
- Retract further to position defined as Garage
- make hclog entry to inform completion of the intended studies, with any quick conclusion which are obvious
- courtesy: Thanks to Dave Gaskell for the motivation to organize this information