Compton Analysis

From PolWiki
Revision as of 15:08, 6 November 2012 by Cornejo (talk | contribs) (→‎Pass2)
Jump to navigationJump to search

Compton Analysis

The goal of this page is to document all related issues with the analysis of the Compton data from both runs.

Run I

November 2010 to May 2011

RUN II

November 2011 to May 2012

Pass2

Pass 2 officially started on Monday November 5. Here is the status of where run ranges stand (by week)

Week# Date Start Run Range Rootfile Status Macro Status Comment
1 11/20/2011 - Not started Not started Initial threading of beam through chicane 11/25
2 11/27/2011 - Not started Not started
3 12/04/2011 - Not started Not started
4 12/11/2011 - Not started Not started
5 12/18/2011 - Not started Not started
6 12/25/2011 - Not started Not started Winter break shutdown. Test runs only
7 01/01/2012 - Not started Not started
8 01/08/20121 - Not started Not started
9 01/15/2012 - Not started Not started
10 01/22/2012 - Not started Not started
11 01/29/2012 - Not started Not started
12 02/05/2012 - Not started Not started
13 02/12/2012 - Not started Not started
14 02/19/2012 - Not started Not started
15 02/26/2012 - Not started Not started
16 03/04/2012 - Not started Not started
17 03/11/2012 - Not started Not started
18 03/18/2012 - Not started Not started
19 03/25/2012 - Not started Not started
20 04/01/2012 - Not started Not started
21 04/08/2012 24973 - 25116 Producing Not started Partial 879MeV running
22 04/15/2012 25117 - 25221 Producing Not started 879MeV running
23 04/22/2012 25222 - 25223 Producing Not started 3GeV running, mostly test runs
24 04/29/2012 25224 - 25316 Producing Not started
25 05/06/2012 25317 - 25541 Producing Not started
26 05/13/2012 25542 - 25561 In Silo Not started Last week!