Electron Detector

From PolWiki
Revision as of 03:03, 19 November 2010 by Narayan (talk | contribs)
Jump to navigationJump to search

Standard Running Procedure

with the previous beam activity ongoing (parasitically)

  • Turn ON High Voltages to the e-detector
    • take a quick run to check DAQ functionality
    • check analyzer functionality
  • on any cdaq machine, type StripTool and pull up strip chart of the epics variables of the 4 Hall-C Chicane BPMs
    • 3P01A (IPM3P01A.XPOS , IPM3PO1A.YPOS)
    • 3P02A (IPM3P02A.XPOS , IPM3PO2A.YPOS)
    • 3P02B (IPM3P02B.XPOS , IPM3PO2B.YPOS)
    • 3P03A (IPM3P03A.XPOS , IPM3PO3A.YPOS)

Request beam to be set through the chicane and verify the same

  • Check Chicane view: on any cdaq machine type edmmonticello, from the Monticello screen
    • open Magnets -> Magnet Commander
      • 3C -> Compton Combo
      • In this Hall C Compton Control screen, the REQUESTED and ACTUAL current readbacks should be ~104 A
    • open BPM -> BPM Overview
      • open Absolute -> on the Hall C column from the left bottom of this screen
      • BPM 3P01A, 3P02A, 3P02B and 3P03A should have finite non-zero read back

Request beam to be taken off, for lowering the e-detector

  • Lower the e-detector to a position in accordance with current run plan
    • Motion mechanism [[1]]
      • begin with the program Go Home
      • jog to the intended position
courtesy: Thanks to Dave Gaskell for the motivation to organize this information

Request beam according to the intended run plan

Diamond strip electron detector

Test Box

Shielded Flex Cables

Q-Weak Amplifier Discriminator

Low Voltage Power supply for QWAD

e-Detector Motion System

e-Detector Assembly