Compton Meeting, September 21, 2011
From PolWiki
Jump to navigationJump to search
Agenda
Laser
- Cavity upgrade progress
Photon Detector
- LED system
- Cooling system update
Electron Detector
- Analysis update - dependence on dipole B-field knowledge
- QWAD work
- Installation progress
DAQ
- BPM/V2F issue (I think Juan Carlos checked it)
Simulation
- There is no end in sight to Dave's procrastination
Miscellaneous
- New cables pulled - (still) not terminated
Other stuff
- Dave G. out of town next week - you're on your own.