Difference between revisions of "F2 Large x runplan: February 2019"
From HallCWiki
Jump to navigationJump to searchLine 6: | Line 6: | ||
! fast raster: || 2x2mm | ! fast raster: || 2x2mm | ||
|- | |- | ||
− | ! | + | ! targets || 10 cm LH2, 10 cm LD2 10 cm Dummy, C, 10B4C, 11B4C |
+ | |- | ||
+ | | trigger || ELREAL | ||
|- | |- | ||
! SHMS collimator: || COLLIMATOR | ! SHMS collimator: || COLLIMATOR | ||
Line 12: | Line 14: | ||
! SHMS trigger: || ELREAL for physics data taking | ! SHMS trigger: || ELREAL for physics data taking | ||
|- | |- | ||
− | ! SHMS angle/momentum: || 13.11 deg / -8.5 GeV/c | + | ! SHMS angle/momentum: || 13.11 deg / -8.5 GeV/c |
|- | |- | ||
|} | |} |
Revision as of 17:10, 14 February 2019
- Conditions: SHMS only.
beam current (uA): | 50 uA |
---|---|
fast raster: | 2x2mm |
targets | 10 cm LH2, 10 cm LD2 10 cm Dummy, C, 10B4C, 11B4C |
trigger | ELREAL |
SHMS collimator: | COLLIMATOR |
SHMS trigger: | ELREAL for physics data taking |
SHMS angle/momentum: | 13.11 deg / -8.5 GeV/c |
Goal is to obtain ~5000 electrons in the range 1.5<x<1.9 for each production target.
- Take ~1-2 hours of LH2 data to verify the position of the elastic peak at x=1. If not at x=1, correct count estimates to account for this.
- Take data on C,10B4C, 11BC at 50 uA. Each target should take about 2.2 hours at 50 uA
- Take LD2 data for 4 hours at 50 uA.
- Take dummy data for at least 1 hours at 40 uA.