A) 8:30am: Polarized beam is terminated. Full Survey of the Hall (RadCon). Hall stays in Controlled Access.  
+
A) Monday 8:30am: Polarized beam is terminated. Full Survey of the Hall (RadCon). Hall stays in Controlled Access.
  
B) 9:30:Open target enclosure (4 plastic panels): 3 or 4 Hall C Techs+ RadCon+Jian-Ping
+
B) 9:20 Put Hall in Controlled Access: Jian-Ping
  
C1) 10:30: EPR calibration in both longitudinal  and transverse: Jian-Ping+EPR expert(s)+RadCon
+
C) 9:30:Open target enclosure (4 plastic panels): 3 or 4 Hall C Techs+ RadCon+Jian-Ping
  
C2) 11:30 Remove Dutch and the target ladder: Arun, Todd, Jian-Ping, one target student+Radcon (1 or 2)
+
D) 10:30 Replace EPR fiber bundle: Junhao + Jian-Ping + RadCon
 +
 
 +
E) 11:30 EPR calibration in both longitudinal and transverse
 +
 
 +
F) 13:20 Laser off, fibers LO/TO, hall out of laser control access: Jian-ping
 +
 
 +
G) 13:30 Remove Dutch and the target ladder: Arun, Todd, 1 target student + Radcon
  
 
<font color="red">
 
<font color="red">
D) 13:00 Put Hall in Last Controlled Access: Jian-Ping
+
H) 15:20 Put Hall in Laser Controlled Access: Jian-Ping
  
E) 13:10 Laser polarization measurement: Junhao,Todd+Radcon
+
J) 15:30 Laser polarization measurement: Junhao,Todd+Radcon
  
F) 13:10 Out of Last Controlled Access: Jian-Ping
+
K) 17:20 Laser off, LO/TO fibers, Out of Laser Controlled Access: Jian-Ping
 
</font>
 
</font>
  
G) 15:00 Replace EPR fiber bundle: 1 target expert+Jian-Ping+RadCon
+
L) 17:30 Install Big Brother: Arun, Todd +1 +RadCon
  
H) 16:00 Install Big Brother: Arun, Todd, Bill, Jian-Ping+RadCon
+
M) 18:30 Install target ladder/Ref. Cell connection: Arun, Todd +1, +RadCon
  
I) 17:00 Install target ladder/Ref. Cell connection: Arun, Todd, Bill, Jian-Ping+RadCon
+
N) 19:30 Set-up RTDs and other connections: Arun, Bill, +RadCon
  
J) 18:00 Set-up RTDs and other connections: Arun, Bill, Jian-Ping+RadCon
+
O) 20:30 Alignment check: Arun +1 +RadCon
 
 
K) 19:00 Alignment check: Arun, Bill, Jian-Ping+RadCon
 
  
 
<font color="red">
 
<font color="red">
L) 21:00 Put Hall in Last Controlled Access: Jian-Ping
+
P) 21:20 Put Hall in Laser Controlled Access: Jian-Ping
  
M) 21:00 Laser alignement/spot: Jian-Ping+Target experts+Radcon
+
Q) 21:30 Laser alignment/spot: Jian-Ping+1+ Radcon
  
N) 23:00 Out of Last Controlled Access: Jian-Ping
+
R) Tuesday 00:30 am Out of Laser Controlled Access: Jian-Ping
 
</font>
 
</font>
  
Oa) 23:00 put back the target enclosures, and close Hall for data taking overnight on ref. cell: 3 Techs+RadCon.
 
  
or
+
S) Backout checklist: Jian-ping
 +
 
 +
T) Pumping up and testings: TBD
  
Ob) 23:00 Start polarizing the target for target check overnight
+
U) Tuesday 7:00 am put back the target enclosures:  3 Techs+ RadCon.
  
P) Tuesday 7:00am close the target if it had not been done. Then target polarimetry calibrations and tests.
+
V) Close Hall (backout checklist) for data taking on ref. cell: TBD
  
Q) Tuesday ??:??am/pm: Take unpolarized beam on Ref. cell until Wednesday 8:00am (a separate run plan is being prepared for this period.)
+
---
  
 
In parallel to the above, other tasks need to be done Monday. They should be organized when enough access keys are available (who is in the Hall will be written in the counting room  white board).
 
In parallel to the above, other tasks need to be done Monday. They should be organized when enough access keys are available (who is in the Hall will be written in the counting room  white board).

Revision as of 14:38, 7 February 2020

Plan for Dutch → Big Brother target change

Hall Status: Controlled Access, if possible. Red fonts show when the Hall will be in Laser Controlled Access.

Tentative plan

A) Monday 8:30am: Polarized beam is terminated. Full Survey of the Hall (RadCon). Hall stays in Controlled Access.

B) 9:20 Put Hall in Controlled Access: Jian-Ping

C) 9:30:Open target enclosure (4 plastic panels): 3 or 4 Hall C Techs+ RadCon+Jian-Ping

D) 10:30 Replace EPR fiber bundle: Junhao + Jian-Ping + RadCon

E) 11:30 EPR calibration in both longitudinal and transverse

F) 13:20 Laser off, fibers LO/TO, hall out of laser control access: Jian-ping

G) 13:30 Remove Dutch and the target ladder: Arun, Todd, 1 target student + Radcon

H) 15:20 Put Hall in Laser Controlled Access: Jian-Ping

J) 15:30 Laser polarization measurement: Junhao,Todd+Radcon

K) 17:20 Laser off, LO/TO fibers, Out of Laser Controlled Access: Jian-Ping

L) 17:30 Install Big Brother: Arun, Todd +1 +RadCon

M) 18:30 Install target ladder/Ref. Cell connection: Arun, Todd +1, +RadCon

N) 19:30 Set-up RTDs and other connections: Arun, Bill, +RadCon

O) 20:30 Alignment check: Arun +1 +RadCon

P) 21:20 Put Hall in Laser Controlled Access: Jian-Ping

Q) 21:30 Laser alignment/spot: Jian-Ping+1+ Radcon

R) Tuesday 00:30 am Out of Laser Controlled Access: Jian-Ping


S) Backout checklist: Jian-ping

T) Pumping up and testings: TBD

U) Tuesday 7:00 am put back the target enclosures: 3 Techs+ RadCon.

V) Close Hall (backout checklist) for data taking on ref. cell: TBD

---

In parallel to the above, other tasks need to be done Monday. They should be organized when enough access keys are available (who is in the Hall will be written in the counting room white board).

a) Rotation stage/camera: Ethan (Jack), Brad

b) Kepco power supply swap/fix/work: Bill

c) Replace the 2 old flowmeters for the nitrogen cooling jets lines with 2 new ones: Andy (Jack)

List of relevant persons with contact email

  • RadCon:
    • Keith Welch <welch@jlab.org>,
    • David Hamlette <hamlette@jlab.org>;
  • Hall leadership:
    • Cynthia (Thia) Keppel <keppel@jlab.org>;
    • Stephen Wood <saw@jlab.org>;
  • Work Coordinator: Walter Kellner <kellner@jlab.org>;
  • Run Coordinator: Alexandre Deur <deurpam@jlab.org>
  • PDL: Greg Smith <smithg@jlab.org>;
  • Experiment/Target leadership:
    • Jian-Ping Chen <jpchen@jlab.org>;
    • Xiaochao Zheng <xiaochao@jlab.org>;
    • Averett, Todd D <tdaver@wm.edu>;
    • Brad Sawatzky <brads@jlab.org>;
  • Engineers/Technical
    • Jack Segal <segal@jlab.org>;
    • Steven Lassiter <lassiter@jlab.org>;
    • Ethan Becker <ethanb@jlab.org>;
    • Andrew Kenyon <kenyon@jlab.org>;
  • Target experts
    • Arun Tadepalli <arunts@jlab.org>;
    • William Henry <wmhenry@jlab.org>;
    • Melanie Rehfuss <mrehfuss@jlab.org>;
    • Mingyu Chen <mingyu@jlab.org>;
    • Junhao Chen <jhchen@jlab.org>;
    • Murchhana Roy <mroy@jlab.org>.