== Onsite Personnel ==
 
== Onsite Personnel ==
 
  NOTE: I'm not 100% sure what restrictions on 'visitor' access may be imposed by the Lab.
 
  NOTE: I'm not 100% sure what restrictions on 'visitor' access may be imposed by the Lab.
 +
** Confirm travel plans in advance to help minimize 2 week quarantine on arrival! **
 +
** Make sure your training and Site Visit status is still current to avoid delays. **
  
Make sure your training and Site Visit status is still current to avoid delays.
+
*; Stationed here w/ polhe3 as a priority
 
 
* Stationed here w/ polhe3 as a priority
 
 
** Brad, JP, Junhao, Mingyu, Bill, Arun
 
** Brad, JP, Junhao, Mingyu, Bill, Arun
 
** David Flay is new staff hire -- did thesis on 6 GeV d2n measurement!
 
** David Flay is new staff hire -- did thesis on 6 GeV d2n measurement!
 
** Carlos Y (new Hall C postdoc) will be able to help by June
 
** Carlos Y (new Hall C postdoc) will be able to help by June
  
* Offsite, but not too far away:
+
*; Offsite, but not too far away:
 
** [W&M] Todd, + 2 grad students (for shifts), post-doc (can RC)
 
** [W&M] Todd, + 2 grad students (for shifts), post-doc (can RC)
 
** [UVa] Xiaochao, Jixie, Gordon?, Chris J  
 
** [UVa] Xiaochao, Jixie, Gordon?, Chris J  
  
* Offsite, but plan to return when we know dates
+
*; Offsite, but plan to return when we know dates
 
** Murchhana
 
** Murchhana
 
** Melanie
 
** Melanie
  
 
== Tasks to complete before we get back on-site ==
 
== Tasks to complete before we get back on-site ==
* '''These will likely require OSPs''' to be written up and approved:
+
*; '''These will likely require OSPs''' to be written up and approved:
 
** Remove/replace target enclosure panels
 
** Remove/replace target enclosure panels
 
** Laser/optics work on the target platform
 
** Laser/optics work on the target platform
Line 27: Line 27:
  
 
== Pre-beam Target Work ==
 
== Pre-beam Target Work ==
* '''We have (tentatively) agreed to rotate the HMS to 20 degrees (kin C) and start running with the HMS at that angle'''.  (The SHMS will remain at its current 11 degree 'Kin X'.)  This will allow the SOLID Prototype folks to get their small-angle test completed with minimal impact on our production running.  (They will setup at small angle and do all their checkout tests well before beam.)
+
*; '''We have (tentatively) agreed to rotate the HMS to 20 degrees (kin C) and start running with the HMS at that angle'''.  (The SHMS will remain at its current 11 degree 'Kin X'.)  This will allow the SOLID Prototype folks to get their small-angle test completed with minimal impact on our production running.  (They will setup at small angle and do all their checkout tests well before beam.)
 
** I (Brad) think this sounds OK, but everyone should think through what we need to do and '''let us know if there is anything that would require moving the HMS in to small angles, even temporarily!, during our pre-beam setup!'''
 
** I (Brad) think this sounds OK, but everyone should think through what we need to do and '''let us know if there is anything that would require moving the HMS in to small angles, even temporarily!, during our pre-beam setup!'''
  
* Update / verify Run plan as needed: [[D2n_kinematics|d2n Run Plan]]
+
*; Update / verify Run plan as needed: [[D2n_kinematics|d2n Run Plan]]
  
* Restore items noted in [https://logbooks.jlab.org/entry/3809218 HCLOG 3809218] when site access is restored. [Brad]
+
*; Restore items noted in [https://logbooks.jlab.org/entry/3809218 HCLOG 3809218] when site access is restored. [Brad]
  
* Order spectrum analyzer for transverse configuration ASAP [Junhao]
+
*; Order spectrum analyzer for transverse configuration ASAP [Junhao]
  
* Laser status? [Junhao, JP]
+
*; Laser status? [Junhao, JP]
 
** One laser needs repair (Junhao will follow up on whether we should/can ship it to Raytum?)
 
** One laser needs repair (Junhao will follow up on whether we should/can ship it to Raytum?)
 
** Three new lasers require modifications/updates to our existing laser control software.  These changes must be integrated with the existing EPICS logging that has been added to the our laser control software. [Junhao will follow-up on this]
 
** Three new lasers require modifications/updates to our existing laser control software.  These changes must be integrated with the existing EPICS logging that has been added to the our laser control software. [Junhao will follow-up on this]
  
* Test Kepco in current mode (Bill)
+
*; Test Kepco in current mode (Bill)
 
** New power supply is now on-site at JLab
 
** New power supply is now on-site at JLab
 
** New filter (for 180 Hz) to install for current mode operation fix. Can always go to voltage mode if it doesn't work.
 
** New filter (for 180 Hz) to install for current mode operation fix. Can always go to voltage mode if it doesn't work.
 
** Establish/verify a known-good production mode
 
** Establish/verify a known-good production mode
  
* AnywhereUSB bridge : Contact with Target readbacks through AnywhereUSB USB bridge still drop out on occasion
+
*; AnywhereUSB bridge : Contact with Target readbacks through AnywhereUSB USB bridge still drop out on occasion
 
** Description of situation during A1n run:
 
** Description of situation during A1n run:
 
*** At first, we fixed a network problem raised by Ethan. And this decreased the frequency of the drop out
 
*** At first, we fixed a network problem raised by Ethan. And this decreased the frequency of the drop out
 
*** Later, there are two senarios for the drop out. For the first senario which happened more frequently, after the device dropped out, we just need to close the individual labview programs with the devices dropped out and wait for the device to come back then reopen the program. If the device do not show up in the first senario, then we need to close the Labview and restart the computer.
 
*** Later, there are two senarios for the drop out. For the first senario which happened more frequently, after the device dropped out, we just need to close the individual labview programs with the devices dropped out and wait for the device to come back then reopen the program. If the device do not show up in the first senario, then we need to close the Labview and restart the computer.
  
* Prep a new target cell [Chris J., Todd?, Arun]
+
*; Prep a new target cell [Chris J., Todd?, Arun]
 
** Chris working on characterizing Tommy and Butterball -- needs to get back in his Lab to wrap things up.
 
** Chris working on characterizing Tommy and Butterball -- needs to get back in his Lab to wrap things up.
 
** Will plan to get things finalized by early June
 
** Will plan to get things finalized by early June
 
** Do we need any hardware at JLab to have a cell ready [Arun]
 
** Do we need any hardware at JLab to have a cell ready [Arun]
  
* NMR issues
+
*; NMR issues
 
** Hardware issues?
 
** Hardware issues?
 
** NMR Calibration Constants : Verify that calibration constants and input values associated with NMR and other polarimetry are consistent and will be correct when the software is restarted  
 
** NMR Calibration Constants : Verify that calibration constants and input values associated with NMR and other polarimetry are consistent and will be correct when the software is restarted  
Line 61: Line 61:
 
*** Add list of calibration runs and what constants apply to what production runs here: [[PolHe3_Polarization_Measurements]]
 
*** Add list of calibration runs and what constants apply to what production runs here: [[PolHe3_Polarization_Measurements]]
  
* pNMR issues
+
*; pNMR issues
 
** Hardware : Check pNMR instruments to make sure they working properly.  Fixes?
 
** Hardware : Check pNMR instruments to make sure they working properly.  Fixes?
 
** pNMR System Check: Follow procedure in [https://logbooks.jlab.org/entry/3797950]
 
** pNMR System Check: Follow procedure in [https://logbooks.jlab.org/entry/3797950]
 
** pNMR Online analysis: Using Labview program to analysis pNMR FID signal (see [https://logbooks.jlab.org/entry/3807141]); Need to create a archived EPICS variable to record polarization measurement results from pNMR. (might need Brad’s help)
 
** pNMR Online analysis: Using Labview program to analysis pNMR FID signal (see [https://logbooks.jlab.org/entry/3807141]); Need to create a archived EPICS variable to record polarization measurement results from pNMR. (might need Brad’s help)
  
* EPR problems : [https://logbooks.jlab.org/entry/3793821] saw some progress on Tuesday [https://logbooks.jlab.org/entry/3796852], but issues remain.
+
*; EPR problems : [https://logbooks.jlab.org/entry/3793821] saw some progress on Tuesday [https://logbooks.jlab.org/entry/3796852], but issues remain.
 
** Tentative plan now is to continue the d2n program by replacing the photo-diode that is placed directly on the pumping chamber (we have many spares).  
 
** Tentative plan now is to continue the d2n program by replacing the photo-diode that is placed directly on the pumping chamber (we have many spares).  
 
** It would be good to write up a procedure to streamline this replacement procedure for us and RadCon
 
** It would be good to write up a procedure to streamline this replacement procedure for us and RadCon
 
** Maybe design a new mount for the photodiode replacing the old mount designed for the fiber bundle
 
** Maybe design a new mount for the photodiode replacing the old mount designed for the fiber bundle
  
* Target Lasers :
+
*; Target Lasers :
 
** Check laser power and wavelength
 
** Check laser power and wavelength
 
** Check laser alignment
 
** Check laser alignment
Line 77: Line 77:
 
** Software validation (verify EPICS integration; control wavelength on new lasers)
 
** Software validation (verify EPICS integration; control wavelength on new lasers)
  
* Target work:
+
*; Target work:
 
** '''Clean all optics (remove dust, etc)'''
 
** '''Clean all optics (remove dust, etc)'''
 
** NMR checkout/fixes
 
** NMR checkout/fixes
Line 84: Line 84:
  
 
== Pending Issues ==
 
== Pending Issues ==
* Fix the epics variable for target field angleThis is the PV which is calculated from the coils currents that is in the startOfRun entries. It needs a new formula since we changes the coil orientation (Bill)
+
*; Fix the EPICS variable calculation for target field angle [Bill]
* Verify that all other EPICS channels are present and are still being archived [Brad]
+
** This is the PV which is calculated from the coils currents that is in the startOfRun entries.
* Look at trigger related signals on the scope under high load (reftime extra pules, FADC reftime-shaper pileup?, NGC noise/rate questions) [Brad]
+
** It needs a new formula since we changes the coil orientation
 +
 
 +
*; Verify that all other EPICS channels are present and are still being archived [Brad]
 +
 
 +
*; Look at trigger related signals on the scope under high load (reftime extra pules, FADC reftime-shaper pileup?, NGC noise/rate questions) [Brad]
 
** investigate FADC 'blocking' artifact (pulse pile-up, undershoot, weirdness?) for SHMS NGC PMT0, reftime shapers
 
** investigate FADC 'blocking' artifact (pulse pile-up, undershoot, weirdness?) for SHMS NGC PMT0, reftime shapers
  
* Target Ladder software must throw an error on a 'voltage' readback mismatch! [https://logbooks.jlab.org/entry/3808208] -- Ethan working on this
+
*; Target Ladder software must throw an error on a 'voltage' readback mismatch! [https://logbooks.jlab.org/entry/3808208] -- Ethan working on this
  
* '''Get 3H07B Harp repaired''' [https://logbooks.jlab.org/entry/3806597] [https://logbooks.jlab.org/entry/3806573]; and a puzzle [https://logbooks.jlab.org/entry/3807995]
+
*; Get 3H07B Harp repaired [https://logbooks.jlab.org/entry/3806597] [https://logbooks.jlab.org/entry/3806573]; and a puzzle [https://logbooks.jlab.org/entry/3807995]
 
** This is being pursued by Brad, Thia, et al.  Still trying to make sure it gets on EES/IC's pre-beam repair list.
 
** This is being pursued by Brad, Thia, et al.  Still trying to make sure it gets on EES/IC's pre-beam repair list.
  
* https://logbooks.jlab.org/entry/3807201 Has Arun's note about the unfortunate reference cell alignment vs. the rest of the target ladder.
+
*; 2mm reference cell offset
 +
** <font color=red>'''Is there a way to shift the reference cell position before beam starts?'''</font>
 +
** [https://logbooks.jlab.org/entry/3807201 Arun's HCLOG 3807201] about the unfortunate reference cell alignment vs. the rest of the target ladder.
 
** NOTE: '''"Shift Leader must request a beam that is shifted horizontally to the beam left side by 2 mm to prevent scraping."'''
 
** NOTE: '''"Shift Leader must request a beam that is shifted horizontally to the beam left side by 2 mm to prevent scraping."'''
** '''Is there a way to shift the reference cell position before beam starts?'''
 
 
  
* iochc10 issues : Green now: Rebooted 3/2/20 with Dave Gaskell assistance.  OPs wished to reboot hung iochc10 [https://logbooks.jlab.org/entry/3795636], noted in December as well [https://logbooks.jlab.org/entry/3745818]
+
*; iochc10 issues : Green now: Rebooted 3/2/20 with Dave Gaskell assistance.  OPs wished to reboot hung iochc10 [https://logbooks.jlab.org/entry/3795636], noted in December as well [https://logbooks.jlab.org/entry/3745818]
 
** Confirm relevant procedures have been updated at MCC (Gaskell, Paul V.?)
 
** Confirm relevant procedures have been updated at MCC (Gaskell, Paul V.?)
 
** This runs the Moller cryo controls and should not be rebooted without expert oversight (does not impact operations).  D. Gaskell is looking into getting this addressed properly with OPs.
 
** This runs the Moller cryo controls and should not be rebooted without expert oversight (does not impact operations).  D. Gaskell is looking into getting this addressed properly with OPs.
  
* Compton related items in Hall C beam steer-up procedure still cause confusion between MCC and Shift Crew -- Gaskell?
+
*; Compton related items in Hall C beam steer-up procedure still cause confusion between MCC and Shift Crew -- Gaskell?
 
** Procedures need to be updated at MCC
 
** Procedures need to be updated at MCC
  
* Verify that inputs to 'Scale32'/G0 scalers (ie ROC5) are > 10ns in width. (Brad, Steve)
+
*; Verify that inputs to 'Scale32'/G0 scalers (ie ROC5) are > 10ns in width. (Brad, Steve)
 
** replace the G0 scalers with something newer/better (SIS38xx or similar)
 
** replace the G0 scalers with something newer/better (SIS38xx or similar)
  
* Online analysis software ready to go?  (Sylvester?, Brad)
+
*; Online analysis software ready to go?  (Sylvester?, Brad)
 
** Most should be fine, but are we missing any 'physics' plots?
 
** Most should be fine, but are we missing any 'physics' plots?
  
Line 116: Line 120:
  
 
=== Techs w/ RadCon [Todd (or designate) for cooling jets] ===
 
=== Techs w/ RadCon [Todd (or designate) for cooling jets] ===
* Turn on turbos for downstream beamline
+
*; Turn on turbos for downstream beamline
* Turn on turbos for SHMS and HMS spectrometer vacuums
+
 
* Remove the guards on the SHMS and HMS entrance windows (verify)
+
*; Turn on turbos for SHMS and HMS spectrometer vacuums
* Remove the guards on the both upstream and downstream beamline windows (verify)
+
 
* Ensure the beamline window cooling jets are in position and on (verify)
+
*; Remove the guards on the SHMS and HMS entrance windows (verify)
* Ensure the target window cooling jets are in position and on (verify)
+
 
* ??
+
*; Remove the guards on the both upstream and downstream beamline windows (verify)
 +
 
 +
*; Ensure the beamline window cooling jets are in position and on (verify)
 +
 
 +
*; Ensure the target window cooling jets are in position and on (verify)
 +
 
 +
*; ??
  
 
===Miscellaneous===
 
===Miscellaneous===
* [Gaskell] Moller magnet cooldown
+
*; [Gaskell] Moller magnet cooldown
* [RadCon, RC] RadCon checklist
+
 
* [Gaskell] Beamline checklist
+
*; [RadCon, RC] RadCon checklist
* [Brad] Detector/DAQ checklist
+
 
* [Walter] Hall checklist
+
*; [Gaskell] Beamline checklist
* [OPS, RC] Schedule hot checkout of Hall C arc magnets/power-supplies
+
 
* [OPS, RC] Verify all relevant FSDs that may have been masked for the down are known about and ready to unmasked when appropriate
+
*; [Brad] Detector/DAQ checklist
* [Lassiter] Enable all spectrometer magnet supplies, restore production settings for Cryo
+
 
* [Brad] Double check that rotation is enabled in the GUIs for both spectrometers
+
*; [Walter] Hall checklist
* [Brad] Ramp all SHMS and HMS magnets to something modest (quick check), or to first kinematic.  For example:
+
 
 +
*; [OPS, RC] Schedule hot checkout of Hall C arc magnets/power-supplies
 +
 
 +
*; [OPS, RC] Verify all relevant FSDs that may have been masked for the down are known about and ready to unmasked when appropriate
 +
 
 +
*; [Lassiter] Enable all spectrometer magnet supplies, restore production settings for Cryo
 +
 
 +
*; [Brad] Double check that rotation is enabled in the GUIs for both spectrometers
 +
 
 +
*; [Brad] Ramp all SHMS and HMS magnets to something modest (quick check), or to first kinematic.  For example:
 
**  SHMS: 11.0deg, 7.5 GeV/c
 
**  SHMS: 11.0deg, 7.5 GeV/c
 
**  HMS: 13.5deg, 4.2 GeV/c
 
**  HMS: 13.5deg, 4.2 GeV/c
 
** NOTE: Coordinate with the target group on the appropriate HB setting so we don't interfere with any target pumping.
 
** NOTE: Coordinate with the target group on the appropriate HB setting so we don't interfere with any target pumping.
* [Techs, Brad?] Do a final check to ensure that there are no potential issues with remote spectrometer rotation
+
 
* Restart main alarm handler (resets masked channels)
+
*; [Techs, Brad?] Do a final check to ensure that there are no potential issues with remote spectrometer rotation
* Restart target alarm handler (if needed)
+
 
* ??
+
*; Restart main alarm handler (resets masked channels)
 +
 
 +
*; Restart target alarm handler (if needed)
 +
 
 +
*; ??

Revision as of 13:11, 26 May 2020

Onsite Personnel

NOTE: I'm not 100% sure what restrictions on 'visitor' access may be imposed by the Lab.
** Confirm travel plans in advance to help minimize 2 week quarantine on arrival! **
** Make sure your training and Site Visit status is still current to avoid delays. **
  • Stationed here w/ polhe3 as a priority
    • Brad, JP, Junhao, Mingyu, Bill, Arun
    • David Flay is new staff hire -- did thesis on 6 GeV d2n measurement!
    • Carlos Y (new Hall C postdoc) will be able to help by June
  • Offsite, but not too far away
    • [W&M] Todd, + 2 grad students (for shifts), post-doc (can RC)
    • [UVa] Xiaochao, Jixie, Gordon?, Chris J
  • Offsite, but plan to return when we know dates
    • Murchhana
    • Melanie

Tasks to complete before we get back on-site

  • These will likely require OSPs to be written up and approved
    • Remove/replace target enclosure panels
    • Laser/optics work on the target platform
    • Laser/optics work in the CH laser room (?)
    • Mounting a new cell (not an immediate task) [RadCon involvement too]
    • Install collimator for 1-pass running
    • EPR photo diode replacement?

Pre-beam Target Work

  • We have (tentatively) agreed to rotate the HMS to 20 degrees (kin C) and start running with the HMS at that angle. (The SHMS will remain at its current 11 degree 'Kin X'.) This will allow the SOLID Prototype folks to get their small-angle test completed with minimal impact on our production running. (They will setup at small angle and do all their checkout tests well before beam.)
    • I (Brad) think this sounds OK, but everyone should think through what we need to do and let us know if there is anything that would require moving the HMS in to small angles, even temporarily!, during our pre-beam setup!
  • Restore items noted in HCLOG 3809218 when site access is restored. [Brad]
  • Order spectrum analyzer for transverse configuration ASAP [Junhao]
  • Laser status? [Junhao, JP]
    • One laser needs repair (Junhao will follow up on whether we should/can ship it to Raytum?)
    • Three new lasers require modifications/updates to our existing laser control software. These changes must be integrated with the existing EPICS logging that has been added to the our laser control software. [Junhao will follow-up on this]
  • Test Kepco in current mode (Bill)
    • New power supply is now on-site at JLab
    • New filter (for 180 Hz) to install for current mode operation fix. Can always go to voltage mode if it doesn't work.
    • Establish/verify a known-good production mode
  • AnywhereUSB bridge
    Contact with Target readbacks through AnywhereUSB USB bridge still drop out on occasion
    • Description of situation during A1n run:
      • At first, we fixed a network problem raised by Ethan. And this decreased the frequency of the drop out
      • Later, there are two senarios for the drop out. For the first senario which happened more frequently, after the device dropped out, we just need to close the individual labview programs with the devices dropped out and wait for the device to come back then reopen the program. If the device do not show up in the first senario, then we need to close the Labview and restart the computer.
  • Prep a new target cell [Chris J., Todd?, Arun]
    • Chris working on characterizing Tommy and Butterball -- needs to get back in his Lab to wrap things up.
    • Will plan to get things finalized by early June
    • Do we need any hardware at JLab to have a cell ready [Arun]
  • NMR issues
    • Hardware issues?
    • NMR Calibration Constants : Verify that calibration constants and input values associated with NMR and other polarimetry are consistent and will be correct when the software is restarted
  • pNMR issues
    • Hardware : Check pNMR instruments to make sure they working properly. Fixes?
    • pNMR System Check: Follow procedure in [6]
    • pNMR Online analysis: Using Labview program to analysis pNMR FID signal (see [7]); Need to create a archived EPICS variable to record polarization measurement results from pNMR. (might need Brad’s help)
  • EPR problems
    [8] saw some progress on Tuesday [9], but issues remain.
    • Tentative plan now is to continue the d2n program by replacing the photo-diode that is placed directly on the pumping chamber (we have many spares).
    • It would be good to write up a procedure to streamline this replacement procedure for us and RadCon
    • Maybe design a new mount for the photodiode replacing the old mount designed for the fiber bundle
  • Target Lasers
    • Check laser power and wavelength
    • Check laser alignment
    • Implement another laser spectrometer for transverse polarization
    • Software validation (verify EPICS integration; control wavelength on new lasers)
  • Target work
    • Clean all optics (remove dust, etc)
    • NMR checkout/fixes
    • EPR checkout/fixes
    • Spin up curves for all 4 polarization directions, configurations

Pending Issues

  • Fix the EPICS variable calculation for target field angle [Bill]
    • This is the PV which is calculated from the coils currents that is in the startOfRun entries.
    • It needs a new formula since we changes the coil orientation
  • Verify that all other EPICS channels are present and are still being archived [Brad]
  • Look at trigger related signals on the scope under high load (reftime extra pules, FADC reftime-shaper pileup?, NGC noise/rate questions) [Brad]
    • investigate FADC 'blocking' artifact (pulse pile-up, undershoot, weirdness?) for SHMS NGC PMT0, reftime shapers
  • Target Ladder software must throw an error on a 'voltage' readback mismatch! [10] -- Ethan working on this
  • Get 3H07B Harp repaired [11] [12]; and a puzzle [13]
    • This is being pursued by Brad, Thia, et al. Still trying to make sure it gets on EES/IC's pre-beam repair list.
  • 2mm reference cell offset
    • Is there a way to shift the reference cell position before beam starts?
    • Arun's HCLOG 3807201 about the unfortunate reference cell alignment vs. the rest of the target ladder.
    • NOTE: "Shift Leader must request a beam that is shifted horizontally to the beam left side by 2 mm to prevent scraping."
  • iochc10 issues
    Green now: Rebooted 3/2/20 with Dave Gaskell assistance. OPs wished to reboot hung iochc10 [14], noted in December as well [15]
    • Confirm relevant procedures have been updated at MCC (Gaskell, Paul V.?)
    • This runs the Moller cryo controls and should not be rebooted without expert oversight (does not impact operations). D. Gaskell is looking into getting this addressed properly with OPs.
  • Compton related items in Hall C beam steer-up procedure still cause confusion between MCC and Shift Crew -- Gaskell?
    • Procedures need to be updated at MCC
  • Verify that inputs to 'Scale32'/G0 scalers (ie ROC5) are > 10ns in width. (Brad, Steve)
    • replace the G0 scalers with something newer/better (SIS38xx or similar)
  • Online analysis software ready to go? (Sylvester?, Brad)
    • Most should be fine, but are we missing any 'physics' plots?

Pre-beam punchlist

Copied from pre-beam punchlist done just before MC6 shutdown. Some items should be completed but require verification/confirmation.

Techs w/ RadCon [Todd (or designate) for cooling jets]

  • Turn on turbos for downstream beamline
  • Turn on turbos for SHMS and HMS spectrometer vacuums
  • Remove the guards on the SHMS and HMS entrance windows (verify)
  • Remove the guards on the both upstream and downstream beamline windows (verify)
  • Ensure the beamline window cooling jets are in position and on (verify)
  • Ensure the target window cooling jets are in position and on (verify)
  • ??

Miscellaneous

  • [Gaskell] Moller magnet cooldown
  • [RadCon, RC] RadCon checklist
  • [Gaskell] Beamline checklist
  • [Brad] Detector/DAQ checklist
  • [Walter] Hall checklist
  • [OPS, RC] Schedule hot checkout of Hall C arc magnets/power-supplies
  • [OPS, RC] Verify all relevant FSDs that may have been masked for the down are known about and ready to unmasked when appropriate
  • [Lassiter] Enable all spectrometer magnet supplies, restore production settings for Cryo
  • [Brad] Double check that rotation is enabled in the GUIs for both spectrometers
  • [Brad] Ramp all SHMS and HMS magnets to something modest (quick check), or to first kinematic. For example
    • SHMS: 11.0deg, 7.5 GeV/c
    • HMS: 13.5deg, 4.2 GeV/c
    • NOTE: Coordinate with the target group on the appropriate HB setting so we don't interfere with any target pumping.
  • [Techs, Brad?] Do a final check to ensure that there are no potential issues with remote spectrometer rotation
  • Restart main alarm handler (resets masked channels)
  • Restart target alarm handler (if needed)
  • ??