Difference between revisions of "Simona's parting notes"
From HallCWiki
Jump to navigationJump to search (Created page with "= RC Meeting Information = <b> RC Daily Meetings are at 4:15 PM, 2nd floor Counting House Meeting Room </b> <b> Wed. Aug 5 2020. </b> * No beam to Hall C since the storm dow...") |
|||
Line 20: | Line 20: | ||
== Recent polarization measurements == | == Recent polarization measurements == | ||
− | * Target polarization looks great: | + | * Target polarization looks great: https://logbooks.jlab.org/entry/3820866 |
= Current Run Plan = | = Current Run Plan = |
Latest revision as of 15:08, 5 August 2020
RC Meeting Information
RC Daily Meetings are at 4:15 PM, 2nd floor Counting House Meeting Room
Wed. Aug 5 2020.
- No beam to Hall C since the storm down
- Our counting house was staffed on the promise of getting beam; we've seen not even one squirt since Aug. 4th 1 am!
- Here is a link to my RC report for the 1:30 meeting which clearly shows that Hall C is not given the priority it needs
- After discussions between RC and spokespeople and then spokespeople and the Hall leader and then Hall leader and PD the plan is for Ops to finish up 1 pass beam delivery to B (2 shifts), do the pass change for B (and A), establish the 5 pass machine by delivering beam to Hall C - 30 muA stable and to B and D ans then bring A on line.
General updates
- On the hall side all looks good
Pending problem
- No beam
Recent polarization measurements
- Target polarization looks great: https://logbooks.jlab.org/entry/3820866
Current Run Plan
Normal Production running
- Prerequisites
- Make sure operational restrictions are followed.
- Make sure the raster size is correct (4-4.5)
- Monitor beam parameters/configuration very often and post an entry like this at the beginning of your shift and when run conditions have changed
- Running on cell targets: raster always ON (4-4.5, size will be determined by the scraping checks), orbit locks ON, current ramp rate 1 muA/sec
- Always take 120Hz of EDTM
- Fill the BTA with realistic numbers. If the desired beam current is not delivered prorate your ABUs!
- Change the IHWP every 4 hours when running on glass cells
- Run plan
- Harp scans with 3H07 A and B
- If profile looks good, production on 3He
Notes for tomorrow's 7:45 meeting
- C has priority over A per Thia's e-mail
- C needs 30 muA now
Future
- After ~ 10 days of running Hall C will go to 1 pass for ~3 days
Hall Access
- Tuesday is maintenance day on the Ops side; perfect time for me and the techs to remove the SoLID Cher detector package from between the HMS and beamline
When there is a down:
- If the down is 2+ hours call Simona: she will check with the RC to see if there is an opportunity for work in the Hall (SoLID Cherenkov parasitic test)
Notices in Effect for Shift Crew
- Policy for CANS-related hall status change: Make a logbook entry when the hall goes in, or comes out of laser-controlled access.
- Magnet policies
- Spectrometer GUI (
go_magnets
) should always be visible on Shift Leader computer, hcdesk3 - HMS Q1 must be ramped down in 50A steps in all cases
- Do not ramp HMS Q2 to zero, only go to 10A and then switch off power.
- If any of the Spectrometers magnets trip, take a screenshot of the PSU window and check the hall for smoke or water with the camera before resetting the interlock and post it to hclog.
- Spectrometer GUI (
- Inform the RC of any access that the Target Team requires. The RC will coordinate with RadCon to make everything run smoothly.
- Please make sure that the orbit locks are enabled and the beam does not drift from its nominal position.
- Ramp rate lock instructions are here and added to checklist[1]
Planned Accelerator Configuration Changes
- Bluejeans remote connection information:
To join the Meeting: https://bluejeans.com/861439920 To join via Room System: Video Conferencing System: bjn.vc -or-199.48.152.152 Meeting ID : 861439920 To join via phone : 1) Dial: +1.408.740.7256 (US (San Jose)) +1.888.240.2560 (US Toll Free)) +1.408.317.9253 (US (Primary, San Jose)) (see all numbers - http://bluejeans.com/numbers) 2) Enter Conference ID : 861439920