== Discussion Topics == | == Discussion Topics == | ||
1. Hall C target ladder still missing some targets required by CaFe PAC45. (Holly/Larry) | 1. Hall C target ladder still missing some targets required by CaFe PAC45. (Holly/Larry) | ||
+ | |||
* Target ladder will need to be modified, potentially adding a second ladder to accommodate for all targets. D. Meekins will need to be contacted to discuss this. See [https://hallcweb.jlab.org/wiki/index.php/Hall_C_Target_Ladder Hall C Target Ladder] | * Target ladder will need to be modified, potentially adding a second ladder to accommodate for all targets. D. Meekins will need to be contacted to discuss this. See [https://hallcweb.jlab.org/wiki/index.php/Hall_C_Target_Ladder Hall C Target Ladder] | ||
2. CaFe SIMC simulation updates (Dien) ? | 2. CaFe SIMC simulation updates (Dien) ? | ||
− | * Dien reviewed what have been done in the rate estimation for the proposal | + | |
+ | * Dien reviewed what have been done in the rate estimation for the proposal | ||
+ | |||
* The SIMC simulation used the D2 distribution for both Hall A and Hall C luminosity => Calculating the ratio "r". Then obtained the C12 simulation from Hall C by scaling the C12 data from hall A to the ratio "r" . In the end there the rate estimation for Ca40 and Ca48 in Hall C was obtained by using the C12 hall C from previous step. So no scaling factor to go from C12 -> Ca40 and Ca48 were applied yet. | * The SIMC simulation used the D2 distribution for both Hall A and Hall C luminosity => Calculating the ratio "r". Then obtained the C12 simulation from Hall C by scaling the C12 data from hall A to the ratio "r" . In the end there the rate estimation for Ca40 and Ca48 in Hall C was obtained by using the C12 hall C from previous step. So no scaling factor to go from C12 -> Ca40 and Ca48 were applied yet. | ||
3. CaFe-Online repository development update? (Carlos) | 3. CaFe-Online repository development update? (Carlos) | ||
+ | |||
* Will meet tomorrow with Stephen Kay (U. Regina post-doc on PION-LT) to discuss changes/updates that were implemented to a version of the Hall C analyzer during the current PION-LT run period, but still need to be added to the official Hall C HCANA analyzer code. | * Will meet tomorrow with Stephen Kay (U. Regina post-doc on PION-LT) to discuss changes/updates that were implemented to a version of the Hall C analyzer during the current PION-LT run period, but still need to be added to the official Hall C HCANA analyzer code. | ||
+ | |||
* Asked Hall B (Maurik Holtrop) for the python source code currently being used in Hall B to generate the interactive graph that keeps track go the total beam charge, trigger rates, etc. on a run basis over the course of an experiment. See, e.g. [https://wiki.jlab.org/clas12-run/index.php/File:RGM_monitoring_nov_22.png RGM Online Monitoring] | * Asked Hall B (Maurik Holtrop) for the python source code currently being used in Hall B to generate the interactive graph that keeps track go the total beam charge, trigger rates, etc. on a run basis over the course of an experiment. See, e.g. [https://wiki.jlab.org/clas12-run/index.php/File:RGM_monitoring_nov_22.png RGM Online Monitoring] |
Latest revision as of 10:41, 22 November 2021
Discussion Topics
1. Hall C target ladder still missing some targets required by CaFe PAC45. (Holly/Larry)
- Target ladder will need to be modified, potentially adding a second ladder to accommodate for all targets. D. Meekins will need to be contacted to discuss this. See Hall C Target Ladder
2. CaFe SIMC simulation updates (Dien) ?
- Dien reviewed what have been done in the rate estimation for the proposal
- The SIMC simulation used the D2 distribution for both Hall A and Hall C luminosity => Calculating the ratio "r". Then obtained the C12 simulation from Hall C by scaling the C12 data from hall A to the ratio "r" . In the end there the rate estimation for Ca40 and Ca48 in Hall C was obtained by using the C12 hall C from previous step. So no scaling factor to go from C12 -> Ca40 and Ca48 were applied yet.
3. CaFe-Online repository development update? (Carlos)
- Will meet tomorrow with Stephen Kay (U. Regina post-doc on PION-LT) to discuss changes/updates that were implemented to a version of the Hall C analyzer during the current PION-LT run period, but still need to be added to the official Hall C HCANA analyzer code.
- Asked Hall B (Maurik Holtrop) for the python source code currently being used in Hall B to generate the interactive graph that keeps track go the total beam charge, trigger rates, etc. on a run basis over the course of an experiment. See, e.g. RGM Online Monitoring