= Accelerator Status =
 
= Accelerator Status =
  
The issue with Hall A BLM trips still persists. From the yesterday studies, the conclusion was made that the 4th pass separator is likely responsible for that (https://logbooks.jlab.org/entry/4142824). Unfortunately, this is not an easy fix and the repair work will realistically take a day and a half. The repair is scheduled for next Tuesday (March 7). For the weekend, it was decided that Halls B, C, and D will be getting beam, while Hall A will wait until Tuesday's repair.
+
The issue with Hall A BLM trips still persists. From Friday's studies, the conclusion was made that the 4th pass separator is likely responsible for that (https://logbooks.jlab.org/entry/4142824). Unfortunately, this is not an easy fix and the repair work will realistically take a day and a half. The repair is scheduled for next Tuesday (March 7). For the weekend, it was decided that Halls B, C, and D will be getting beam, while Hall A will wait until Tuesday's repair.
  
 
= Current Run Plan =
 
= Current Run Plan =
 
The plan is to continue taking production data for the Pm=800 MeV/c at the highest possible current.
 
The plan is to continue taking production data for the Pm=800 MeV/c at the highest possible current.

Revision as of 07:49, 5 March 2023

Return to the calendar.

RC Meeting Information

Current RC: Iuliia Skorodumina.

No RC meeting today.

Summary

Accelerator Status

The issue with Hall A BLM trips still persists. From Friday's studies, the conclusion was made that the 4th pass separator is likely responsible for that (https://logbooks.jlab.org/entry/4142824). Unfortunately, this is not an easy fix and the repair work will realistically take a day and a half. The repair is scheduled for next Tuesday (March 7). For the weekend, it was decided that Halls B, C, and D will be getting beam, while Hall A will wait until Tuesday's repair.

Current Run Plan

The plan is to continue taking production data for the Pm=800 MeV/c at the highest possible current.