+ | '''Saturday Day (03/04).''' The shift started with the Accelerator issues. 2L26-5 ioc went down (https://logbooks.jlab.org/entry/4143137). At around 12:30 the issue was fixed, but in about two hours, the same ioc went down again (https://logbooks.jlab.org/entry/4143225). No beam for the rest of the shift. Day Shift summary: https://logbooks.jlab.org/entry/4143131 . | ||
+ | |||
+ | '''Saturday Swing (03/04).''' The beam resumed about 7pm and since then was quite stable. We were taking production data at 60 uA. Swing Shift summary: https://logbooks.jlab.org/entry/4143261 . | ||
+ | |||
+ | '''Sunday Owl (03/05).''' We were taking data overnight at 60 uA. A quiet and productive shift with large ABU: https://logbooks.jlab.org/entry/4143493 . | ||
+ | |||
+ | For the current setting (Pm=800 MeV/c), we have collected a total of 9655 mC integrated charge out of the planned 15696 mC, which corresponds to 62%. | ||
= Accelerator Status = | = Accelerator Status = | ||
− | The issue with Hall A BLM trips still persists. From | + | The issue with Hall A BLM trips still persists. From Friday's studies, the conclusion was made that the 4th pass separator is likely responsible for that (https://logbooks.jlab.org/entry/4142824). Unfortunately, this is not an easy fix and the repair work will realistically take a day and a half. The repair is scheduled for next Tuesday (March 7). For the weekend, it was decided that Halls B, C, and D will be getting beam, while Hall A will wait until Tuesday's repair. |
= Current Run Plan = | = Current Run Plan = | ||
The plan is to continue taking production data for the Pm=800 MeV/c at the highest possible current. | The plan is to continue taking production data for the Pm=800 MeV/c at the highest possible current. |
Latest revision as of 08:54, 5 March 2023
Return to the calendar.
RC Meeting Information
Current RC: Iuliia Skorodumina.
No RC meeting today.
Summary
Saturday Day (03/04). The shift started with the Accelerator issues. 2L26-5 ioc went down (https://logbooks.jlab.org/entry/4143137). At around 12:30 the issue was fixed, but in about two hours, the same ioc went down again (https://logbooks.jlab.org/entry/4143225). No beam for the rest of the shift. Day Shift summary: https://logbooks.jlab.org/entry/4143131 .
Saturday Swing (03/04). The beam resumed about 7pm and since then was quite stable. We were taking production data at 60 uA. Swing Shift summary: https://logbooks.jlab.org/entry/4143261 .
Sunday Owl (03/05). We were taking data overnight at 60 uA. A quiet and productive shift with large ABU: https://logbooks.jlab.org/entry/4143493 .
For the current setting (Pm=800 MeV/c), we have collected a total of 9655 mC integrated charge out of the planned 15696 mC, which corresponds to 62%.
Accelerator Status
The issue with Hall A BLM trips still persists. From Friday's studies, the conclusion was made that the 4th pass separator is likely responsible for that (https://logbooks.jlab.org/entry/4142824). Unfortunately, this is not an easy fix and the repair work will realistically take a day and a half. The repair is scheduled for next Tuesday (March 7). For the weekend, it was decided that Halls B, C, and D will be getting beam, while Hall A will wait until Tuesday's repair.
Current Run Plan
The plan is to continue taking production data for the Pm=800 MeV/c at the highest possible current.