Difference between revisions of "December 4, 2023"
From HallCWiki
Jump to navigationJump to search(One intermediate revision by the same user not shown) | |||
Line 15: | Line 15: | ||
= Current Status = | = Current Status = | ||
* Hall is in Controlled Access. | * Hall is in Controlled Access. | ||
− | |||
* Calorimeter work will commence this afternoon. | * Calorimeter work will commence this afternoon. | ||
Line 24: | Line 23: | ||
= Notices in Effect for Shift Crew = | = Notices in Effect for Shift Crew = | ||
− | * | + | * TO and SL are cancelled. TO on Tuesday day is on standby. |
= Current Issues = | = Current Issues = |
Latest revision as of 08:14, 4 December 2023
RC Meeting Information
RC Daily Meetings are at 11:00 (am) via Zoom and in person in the counting house meeting room (2nd floor)
- Zoom remote connection information: https://logbooks.jlab.org/entry/4229331
Useful Links
Current Status
- Hall is in Controlled Access.
- Calorimeter work will commence this afternoon.
Current Run Plan
- When we know about beam, we will re-condense the cryogenic target. It will be about 4-6 hours before we can use the cryogenics in beam after that.
- The initial gun injector work is complete. Now they are working on the beam spot and size coming out from the injector beamline.
- Estimate is beam to the Halls on swing shift Tuesday. Will revise this tomorrow at the 9am meeting.
Notices in Effect for Shift Crew
- TO and SL are cancelled. TO on Tuesday day is on standby.
Current Issues
Planned Accesses to the Hall
- Calorimeter work