= Accelerator status =
 
= Accelerator status =
* Trip rate 10/hr (about half of it form RF trips)
+
* Trip rates 10/hr (about half of it form RF trips)
 
* Maintenance + Beam study on Wednesday
 
* Maintenance + Beam study on Wednesday
  
Line 48: Line 48:
 
= Current Issues =
 
= Current Issues =
 
* NPS crate #2 drops occasionally
 
* NPS crate #2 drops occasionally
* BTA with low current -  
+
* BTA with low current - https://logbooks.jlab.org/entry/4256075
 
+
** Helper script: go_bta_config
  
 
= Planned Access to the Hall =
 
= Planned Access to the Hall =

Latest revision as of 09:57, 26 February 2024

RC Meeting Information

RC Daily Meetings are at 11:00 (am) via Zoom and in person in the counting house meeting room (2nd floor)

Useful Links

Hall status

  • SHMS hut AC unit tripped off since Saturday
    • coupled to LCW system, tripped off when LCW went down
    • Facilities reset the AC unit
    • Crate temperatures not monitored, Bill is working on it
  • NPS crate #2 drops occasionally:
    • Not much reported recently, taking 30min runs (restarting a new run more often) seems helping

Accelerator status

  • Trip rates 10/hr (about half of it form RF trips)
  • Maintenance + Beam study on Wednesday

Current Run Plan

Notices in Effect for Shift Crew

Current Issues

Planned Access to the Hall

Special Requests

  • Guard house work till Friday. Pay attention to the sign and follow the directions around there when coming to the accelerator site.