Difference between revisions of "To Do List, Assignments"
From HallCWiki
Jump to navigationJump to searchLine 14: | Line 14: | ||
− | *** '''Production Run Plan''' - ''' | + | *** '''Production Run Plan''' - '''Simona''' |
**** Choice of kinematics | **** Choice of kinematics | ||
Line 28: | Line 28: | ||
− | *** '''Non-production run plan''' | + | *** '''Non-production run plan''' - ''' Eric, Simona, Thia, Ioana''' |
**** Elastics | **** Elastics | ||
Line 36: | Line 36: | ||
− | *** '''Online analysis coordination''' - '''Simona | + | *** '''Online analysis coordination''' - '''Simona''' |
**** Calibrations codes ready | **** Calibrations codes ready | ||
Line 45: | Line 45: | ||
− | *** ''' Items needed for efficient running''' | + | *** ''' Items needed for efficient running''' - '''Simona, Eric, Thia, Ioana''' |
**** Shift checklist: create/post on wiki | **** Shift checklist: create/post on wiki | ||
Line 51: | Line 51: | ||
**** Run sheets: create/post on wiki | **** Run sheets: create/post on wiki | ||
− | **** Post run plan on wiki - ''' | + | **** Post run plan on wiki - '''Simona''' |
**** Post on wiki procedures/how to's (+ most common problems and how to solve them) for: | **** Post on wiki procedures/how to's (+ most common problems and how to solve them) for: | ||
− | ***** HV operation | + | ***** HV operation - ''''S. Malace''' |
***** Beam restoration: BeO, harp scan, C-hole run, bull's eye scan etc. | ***** Beam restoration: BeO, harp scan, C-hole run, bull's eye scan etc. | ||
***** CODA running | ***** CODA running | ||
***** Change of spectrometers momenta | ***** Change of spectrometers momenta | ||
− | ***** Change of | + | ***** Change of spectrometers angle |
***** Online histograms monitoring | ***** Online histograms monitoring | ||
+ | |||
+ | |||
+ | ** ''''While running:'''' | ||
+ | |||
+ | |||
+ | *** Make sure shifts are staffed - '''All''' | ||
+ | |||
+ | *** Make sure we have run coordinators - '''All''' | ||
+ | |||
+ | *** One spokesperson (at least) should be in the counting house most of the time to follow progress of running or fill in shifts, if needed - '''Simona, Eric, Ioana (we rotate)''' | ||
+ | |||
+ | *** Make sure the online analysis progresses so we can make decisions on the fly about changes in the run plan - '''Simona''' (and all) | ||
+ | |||
+ | |||
+ | ** ''''After running:'''' | ||
+ | |||
+ | |||
+ | *** Offline analysis coordination: includes organizing/chairing weekly meetings, establishing analysis task and timeline, making sure analysis progresses according to the plan and ensuring that the analysis is properly documented - '''Simona (primary), Eric (back-up)''' | ||
+ | |||
+ | *** Organizing Collaboration meetings (at JLab) which involve spokespeople, students from the other commissioning experiments (probably one a month in the beginning) - '''All, we rotate''' | ||
+ | |||
+ | *** Ensure maximum physics output from data- '''All''' |
Revision as of 14:54, 11 May 2016
- Spokespeople for E12-10-002
- Simona Malace - spokesperson, contact
- Eric Christy - spokesperson
- Thia Keppel - spokesperson
- Ioana Niculescu - spokesperson
- To Do List/Assignments
- 'In preparation for running:'
- Production Run Plan - Simona
- Choice of kinematics
- Radiative corrections calculation
- Charge-symmetric background calculation
- Pion rates calculation
- Estimation of detector rates
- Summary of trigger setup: trigger configuration, thresholds for various detectors
- Trigger rates
- Order of kinematic production running
- Coordinate with Dave Gaskell for combined E12-10-002/E12-10-008 running
- Non-production run plan - Eric, Simona, Thia, Ioana
- Elastics
- BCM calibrations
- Luminosity scans
- What else?
- Online analysis coordination - Simona
- Calibrations codes ready
- Codes to monitor quality of data online: check deadtimes, efficiencies and quality of calibrations
- Hcana working and ready for online replay
- MC ready to produce acceptance corrections
- Cross sections code ready for online cross section
- Items needed for efficient running - Simona, Eric, Thia, Ioana
- Shift checklist: create/post on wiki
- Run sheets: create/post on wiki
- Post run plan on wiki - Simona
- Post on wiki procedures/how to's (+ most common problems and how to solve them) for:
- HV operation - 'S. Malace
- Beam restoration: BeO, harp scan, C-hole run, bull's eye scan etc.
- CODA running
- Change of spectrometers momenta
- Change of spectrometers angle
- Online histograms monitoring
- 'While running:'
- Make sure shifts are staffed - All
- Make sure we have run coordinators - All
- One spokesperson (at least) should be in the counting house most of the time to follow progress of running or fill in shifts, if needed - Simona, Eric, Ioana (we rotate)
- Make sure the online analysis progresses so we can make decisions on the fly about changes in the run plan - Simona (and all)
- 'After running:'
- Offline analysis coordination: includes organizing/chairing weekly meetings, establishing analysis task and timeline, making sure analysis progresses according to the plan and ensuring that the analysis is properly documented - Simona (primary), Eric (back-up)
- Organizing Collaboration meetings (at JLab) which involve spokespeople, students from the other commissioning experiments (probably one a month in the beginning) - All, we rotate
- Ensure maximum physics output from data- All