Jump to navigationJump to search (Created page with "* '''General''' ** No hall lockup tonight ** Beam is possible, Tuesday night, but not likely. Will not cancel shifts until certain though ** Issues with the upstream beamline...") |
|||
Line 2: | Line 2: | ||
** No hall lockup tonight | ** No hall lockup tonight | ||
− | ** Beam is possible | + | ** Beam is possible Tuesday night, but not likely. Will not cancel shifts until certain though. |
− | ** Issues with the upstream beamline vacuum. Ion | + | ** Issues with the upstream beamline vacuum. Ion pumps not yet on |
** Still work to be done in hall before ready for lockup | ** Still work to be done in hall before ready for lockup | ||
− | ** Need to look into merging the KAON | + | ** Need to look into merging the KAON-LT shift instruction with existing instructions on the wiki |
+ | ** New procedure for "on call" - will need to update list on wiki to reflect new on-call list | ||
Line 14: | Line 15: | ||
* '''SHMS''' | * '''SHMS''' | ||
** HGC at 1 atm of C4F8O | ** HGC at 1 atm of C4F8O | ||
+ | ** No bubbles at exit of DC1, but gas seems to be flowing | ||
* '''HMS''' | * '''HMS''' | ||
Line 20: | Line 22: | ||
* '''DAQ''' | * '''DAQ''' | ||
+ | ** Hall B will be running in "delayed helicity reporting" - likely not an issue |
Revision as of 16:23, 20 August 2018
- General
- No hall lockup tonight
- Beam is possible Tuesday night, but not likely. Will not cancel shifts until certain though.
- Issues with the upstream beamline vacuum. Ion pumps not yet on
- Still work to be done in hall before ready for lockup
- Need to look into merging the KAON-LT shift instruction with existing instructions on the wiki
- New procedure for "on call" - will need to update list on wiki to reflect new on-call list
- Target
- Scattering chamber leak repaired over the weekend (big thanks to Dave Meekins, Chris Keith, and Walter Kellner for coming in)
- Target cooldown underway
- SHMS
- HGC at 1 atm of C4F8O
- No bubbles at exit of DC1, but gas seems to be flowing
- HMS
- Cerenkov window repaired and installed
- Cerenkov at 0.45 atm, C4F8O
- DAQ
- Hall B will be running in "delayed helicity reporting" - likely not an issue