Difference between revisions of "RC meeting and Run Plan, Tuesday Nov 6"

From HallCWiki
Jump to: navigation, search
 
(2 intermediate revisions by the same user not shown)
Line 8: Line 8:
  
 
*(Beam Returns)
 
*(Beam Returns)
*Kin16.7A (stay on LH2 while MCC tests 60uA running, then run LD2 and dummy)
 
 
*Kin16.6  (finish up Dummy and LH2)
 
*Kin16.6  (finish up Dummy and LH2)
 +
*<s>Kin16.7  (NOTE: NOT 16.7A!!!)</s>
 +
*Kin16.7A
  
 
SHMS POLARITY CHANGE
 
SHMS POLARITY CHANGE
  
 +
*<s>Kin15.7  (NOTE: NOT 15.7A!!!) </s>
 +
*Kin15.7A
 
*Kin15.6
 
*Kin15.6
 
*Kin15.4A
 
*Kin15.4A
*Kin15.7A
 
 
  
 
==Reminders==
 
==Reminders==
Line 28: Line 29:
 
==Planned access to the hall==
 
==Planned access to the hall==
 
* Mark: escorted access to reset crate during RF Recovery
 
* Mark: escorted access to reset crate during RF Recovery
** Andy: possibly join
 

Latest revision as of 09:16, 7 November 2018

Back to List

Status

  • Down for System Recovery (~4hrs) today, should be up and running again this afternoon
  • In the midst of Kin Group 16 (three points only)

Time-Ordered Run Plan

  • (Beam Returns)
  • Kin16.6 (finish up Dummy and LH2)
  • Kin16.7 (NOTE: NOT 16.7A!!!)
  • Kin16.7A

SHMS POLARITY CHANGE

  • Kin15.7 (NOTE: NOT 15.7A!!!)
  • Kin15.7A
  • Kin15.6
  • Kin15.4A

Reminders

  • Take one HMS monitoring run each shift
  • For all settings, for each target, split the desired charge between three runs
  • Listed currents are estimates. For runs at less than 60uA, increase current until SHMS singles rates are between 400k-500k.

Issues

Planned access to the hall

  • Mark: escorted access to reset crate during RF Recovery