Difference between revisions of "Hall C Weekly Meeting - March 4, 2013"

From HallCWiki
Jump to: navigation, search
(New page: Minutes Hall C Meeting 3/4/2013 *Walter Kellner **The SOS base frame was removed from the Hall. **Last bit of SOS rail was removed **The C-can and platform have been dismounted **The Hall...)
 
(Add Paul Brindza's notes)
 
Line 19: Line 19:
  
 
*Paul Brindza
 
*Paul Brindza
 +
**Design work in progress
 +
***Noble Gas Cerenkov (NGC) done waiting for UVA comments
 +
***Dipole Vacuum spool
 +
***Sieve slit and vacuum spools between HB-Q1
 +
***Moller Quad Coil Spec and Compton
 +
***HMS Data Cable Duct replacement design
 +
***Shield House door opener – motor, transmission, chain drive-mechanical design
 +
**SHMS
 +
***Q1 magnet yoke stacking started at SMI- JLAB visit
 +
***HB magnet helium vessel parts machining and bending
 +
***SHMS DC Power Supplies done ready for Factor Acceptance Test
 +
***Dipole- Preparations for 10 turn 1 meter trial coil
 +
***Bid of steel structure canceled- no qualified small businesses
  
 
*Bert Manzlak
 
*Bert Manzlak
 
**Reminds people to check with Walter or Andy before coming into hall
 
**Reminds people to check with Walter or Andy before coming into hall

Latest revision as of 16:29, 11 March 2013

Minutes Hall C Meeting 3/4/2013

  • Walter Kellner
    • The SOS base frame was removed from the Hall.
    • Last bit of SOS rail was removed
    • The C-can and platform have been dismounted
    • The Hall C crane is still down for repairs. Expected to be back in service this week. In the mean time a crane is being rented from Lockwood
    • The groundwater leak in the truck ramp has finally been fixed
    • There is still a bad leak near the labyrinth door
  • Mike Fowler
    • The SHMS rail installation is complete
    • The SHMS structure assembly is being sent out for rebidding. This will delay the SHMS structure assembly by a month.
  • Joe Beaufait (via email)
    • Spoke to engineering group for help with rerouting of G0 patch panel
    • G0 water cooled leads found. Are in good enough condition to reuse.
    • Clean power water issue reported as resolved by facilities, but Joe has not been able to get a report on what was actually done.
  • Paul Brindza
    • Design work in progress
      • Noble Gas Cerenkov (NGC) done waiting for UVA comments
      • Dipole Vacuum spool
      • Sieve slit and vacuum spools between HB-Q1
      • Moller Quad Coil Spec and Compton
      • HMS Data Cable Duct replacement design
      • Shield House door opener – motor, transmission, chain drive-mechanical design
    • SHMS
      • Q1 magnet yoke stacking started at SMI- JLAB visit
      • HB magnet helium vessel parts machining and bending
      • SHMS DC Power Supplies done ready for Factor Acceptance Test
      • Dipole- Preparations for 10 turn 1 meter trial coil
      • Bid of steel structure canceled- no qualified small businesses
  • Bert Manzlak
    • Reminds people to check with Walter or Andy before coming into hall