(Created page with "= RC Meeting Information = <b> RC Daily Meetings are at 11:00 (am) via Zoom and in person in the counting house meeting room (2nd floor) </b> * Zoom remote connection informa...")
 
 
(10 intermediate revisions by the same user not shown)
Line 6: Line 6:
 
= Useful Links =
 
= Useful Links =
  
* [https://misportal.jlab.org/mis/physics/shiftSchedule/index.cfm?experimentRunId=HALLC-XEM2 Shift Signup ('''Read only''')]
+
* [https://misportal.jlab.org/mis/physics/shiftSchedule/index.cfm?experimentRunId=DVCS-NPS-2023 Shift Signup ('''Read only''')]
** [https://misportal.jlab.org/mis/apps/physics/shiftSchedule/index.cfm?experimentRunId=HALLC-XEM2 Shift Signup]
+
** [https://misportal.jlab.org/mis/apps/physics/shiftSchedule/index.cfm?experimentRunId=DVCS-NPS-2023 Shift Signup]
  
 
* [https://hallcweb.jlab.org/live_status/snapshots_controls/ Hall-C Controls]
 
* [https://hallcweb.jlab.org/live_status/snapshots_controls/ Hall-C Controls]
Line 14: Line 14:
  
 
= Current Status =
 
= Current Status =
*
+
* Finished 3, 1-hour runs at 5 pass elastic settings
 +
* Attempted arc energy measurement, BCM calibration yesterday: not completed
 +
* Restarted HMS high momentum optics
 +
* HMS high momentum optics data taking underway
  
 
= Current Run Plan =
 
= Current Run Plan =
*
+
* Short term run plan: https://hallcweb.jlab.org/wiki/index.php/Short_Term_Run-Plan
 +
* HMS high momentum optics at P_HMS=-6.117 GeV and -5.639 GeV
 +
* Arc energy measurement this morning
 +
* Moller measurement Thursday? Hall A is planning one also
 +
* BCM calibration Thursday or Friday?
  
 
= Notices in Effect for Shift Crew =
 
= Notices in Effect for Shift Crew =
Line 23: Line 30:
  
 
= Current Issues =
 
= Current Issues =
*
+
* MQF3M01 (small Moller quad) remote control not working
 +
* 3 channels missing in calorimeter
  
 
= Planned Accesses to the Hall =
 
= Planned Accesses to the Hall =
*
+
* Controlled Access tomorrow (Wednesday) during day shift
 +
** Repair MQF3M01 power supply/polarity switch (DC power)
 +
** Check NDX detector location
 +
** Repair three missing channels in calorimeter, replace more cables (?)
  
 
= Planned Accelerator Configuration Changes =
 
= Planned Accelerator Configuration Changes =

Latest revision as of 08:52, 19 September 2023

RC Meeting Information

RC Daily Meetings are at 11:00 (am) via Zoom and in person in the counting house meeting room (2nd floor)

Useful Links

Current Status

  • Finished 3, 1-hour runs at 5 pass elastic settings
  • Attempted arc energy measurement, BCM calibration yesterday: not completed
  • Restarted HMS high momentum optics
  • HMS high momentum optics data taking underway

Current Run Plan

Notices in Effect for Shift Crew

Current Issues

  • MQF3M01 (small Moller quad) remote control not working
  • 3 channels missing in calorimeter

Planned Accesses to the Hall

  • Controlled Access tomorrow (Wednesday) during day shift
    • Repair MQF3M01 power supply/polarity switch (DC power)
    • Check NDX detector location
    • Repair three missing channels in calorimeter, replace more cables (?)

Planned Accelerator Configuration Changes

Special Requests