Difference between revisions of "September 30, 2023"
(Created page with "= RC Meeting Information = Current RC: Iuliia Skorodumina No RC meeting today = Useful Links = * [https://misportal.jlab.org/mis/physics/shiftSchedule/index.cfm?experiment...") |
|||
(3 intermediate revisions by the same user not shown) | |||
Line 1: | Line 1: | ||
+ | [https://hallcweb.jlab.org/wiki/index.php/RC_Daily_Meetings:_NPS Back to the calendar] | ||
= RC Meeting Information = | = RC Meeting Information = | ||
Line 15: | Line 16: | ||
= Summary = | = Summary = | ||
− | We | + | We started '''Friday Day''' shift (09/29) in Controlled access to repair dead NPS channels. The repair was completed around 11 am and now both problematic channels are fixed (https://logbooks.jlab.org/entry/4189240). Then we proceeded to our last elastic setting. |
− | + | There wasn't much beam during the rest of the '''Friday Day''' shift (https://logbooks.jlab.org/entry/4189168). During the Swing shift the beam was unstable, too (https://logbooks.jlab.org/entry/4189555). The accelerator is still unable to deliver beam to Hall A without tripping BLMs. Delivery to Hall C is fine, but the troubleshooting of Hall A is impeding delivery to us (see https://logbooks.jlab.org/entry/4189370 and https://logbooks.jlab.org/entry/4189538). | |
− | |||
− | |||
− | + | At about 4am MCC gave up delivering to Hall A and we got stable beam towards the rest of the '''Owl''' shift (https://logbooks.jlab.org/entry/4189574). We were able to complete the last elastic setting at around 9am and now changing configuration to proceed to optics measurement. | |
− | + | The accelerator plans to continue troubleshooting issues with the beam delivery to Hall A and puts it as the highest priority for now. For this reason, it is unlikely that we can expect stable beam over the weekend. | |
− | + | There will be no RC meetings over the weekend. | |
− | = | + | = Run plan = |
− | Hall | + | The run plan is available here: https://hallcweb.jlab.org/wiki/index.php/Short_Term_Run-Plan |
+ | |||
+ | = Accelerator status = | ||
+ | |||
+ | The accelerator plans to continue troubleshooting issues with the beam delivery to Hall A and puts it as the highest priority for now. Stable beam delivery to Hall C over the weekend is unlikely. |
Latest revision as of 08:17, 3 October 2023
RC Meeting Information
Current RC: Iuliia Skorodumina
No RC meeting today
Useful Links
Summary
We started Friday Day shift (09/29) in Controlled access to repair dead NPS channels. The repair was completed around 11 am and now both problematic channels are fixed (https://logbooks.jlab.org/entry/4189240). Then we proceeded to our last elastic setting.
There wasn't much beam during the rest of the Friday Day shift (https://logbooks.jlab.org/entry/4189168). During the Swing shift the beam was unstable, too (https://logbooks.jlab.org/entry/4189555). The accelerator is still unable to deliver beam to Hall A without tripping BLMs. Delivery to Hall C is fine, but the troubleshooting of Hall A is impeding delivery to us (see https://logbooks.jlab.org/entry/4189370 and https://logbooks.jlab.org/entry/4189538).
At about 4am MCC gave up delivering to Hall A and we got stable beam towards the rest of the Owl shift (https://logbooks.jlab.org/entry/4189574). We were able to complete the last elastic setting at around 9am and now changing configuration to proceed to optics measurement.
The accelerator plans to continue troubleshooting issues with the beam delivery to Hall A and puts it as the highest priority for now. For this reason, it is unlikely that we can expect stable beam over the weekend.
There will be no RC meetings over the weekend.
Run plan
The run plan is available here: https://hallcweb.jlab.org/wiki/index.php/Short_Term_Run-Plan
Accelerator status
The accelerator plans to continue troubleshooting issues with the beam delivery to Hall A and puts it as the highest priority for now. Stable beam delivery to Hall C over the weekend is unlikely.