= Summary = | = Summary = | ||
*Work will begin on repairing the vacuum chamber: https://logbooks.jlab.org/entry/4270828 | *Work will begin on repairing the vacuum chamber: https://logbooks.jlab.org/entry/4270828 | ||
+ | *Target "warm up" on Friday: https://logbooks.jlab.org/entry/4270595 | ||
*Beamline pressure changed after target warmup: https://logbooks.jlab.org/entry/4270630 | *Beamline pressure changed after target warmup: https://logbooks.jlab.org/entry/4270630 | ||
*HMS Drift Chamber gas flow dropped to 0: https://logbooks.jlab.org/entry/4270782 | *HMS Drift Chamber gas flow dropped to 0: https://logbooks.jlab.org/entry/4270782 | ||
Line 24: | Line 25: | ||
= Plans= | = Plans= | ||
*NPS to 3.5 meters | *NPS to 3.5 meters | ||
+ | ** After last week’s discussion about adding the possibility of moving to an intermediate position of 3.5 meters, RADCON has signed off the proposed plan off drilling a new pinning hole at 3.5 meters. | ||
+ | **Joe Beaufait will lock out the sweep magnet later this morning and the techs will begin working on drill the new hole later this afternoon. |
Latest revision as of 09:56, 25 March 2024
RC Meeting Information
Current RC: Michael Nycz (mnycz@jlab.org)
RC Daily Meetings are at 11:00 (am) via Zoom and in person in the counting house meeting room (2nd floor)
- Zoom connection link: https://jlab-org.zoomgov.com/j/1617015555?pwd=L09IQ216dml6ZmM5ODExVjFsMX
- Meeting ID: 161 701 5555
- Passcode: 288953
Useful Links
- Short term run plan [1]
- Shift Signup (Read only)
- Hall-C Controls
- Hall-C Logbook
- MCC White Board
- Daily RC Reports
Summary
- Work will begin on repairing the vacuum chamber: https://logbooks.jlab.org/entry/4270828
- Target "warm up" on Friday: https://logbooks.jlab.org/entry/4270595
- Beamline pressure changed after target warmup: https://logbooks.jlab.org/entry/4270630
- HMS Drift Chamber gas flow dropped to 0: https://logbooks.jlab.org/entry/4270782
Plans
- NPS to 3.5 meters
- After last week’s discussion about adding the possibility of moving to an intermediate position of 3.5 meters, RADCON has signed off the proposed plan off drilling a new pinning hole at 3.5 meters.
- Joe Beaufait will lock out the sweep magnet later this morning and the techs will begin working on drill the new hole later this afternoon.