Difference between revisions of "PolHe3 Punch List For Restart"

From HallCWiki
Jump to navigationJump to search
Line 82: Line 82:
 
** [[Pol_He-3_Target_Information#Production_Target_Cell_Information]]
 
** [[Pol_He-3_Target_Information#Production_Target_Cell_Information]]
  
*; NMR issues
+
*; NMR issues [Junhao]
** Hardware issues?
+
** Transverse NMR not fully working yet
 
** NMR Calibration Constants : Verify that calibration constants and input values associated with NMR and other polarimetry are consistent and will be correct when the software is restarted  
 
** NMR Calibration Constants : Verify that calibration constants and input values associated with NMR and other polarimetry are consistent and will be correct when the software is restarted  
 
***[https://logbooks.jlab.org/entry/3796178] [https://logbooks.jlab.org/entry/3795421] [https://logbooks.jlab.org/entry/3795982] [https://logbooks.jlab.org/entry/3796117] [https://logbooks.jlab.org/entry/3796111] (Bill, Junhao, Arun)
 
***[https://logbooks.jlab.org/entry/3796178] [https://logbooks.jlab.org/entry/3795421] [https://logbooks.jlab.org/entry/3795982] [https://logbooks.jlab.org/entry/3796117] [https://logbooks.jlab.org/entry/3796111] (Bill, Junhao, Arun)
 
*** Add list of calibration runs and what constants apply to what production runs here: [[PolHe3_Polarization_Measurements]]
 
*** Add list of calibration runs and what constants apply to what production runs here: [[PolHe3_Polarization_Measurements]]
  
*; pNMR issues
+
*; pNMR issues [Mingyu]
** Hardware : Check pNMR instruments to make sure they working properly.  Fixes?
+
** Signal present in Transverse mode, but needs to be calibrated/cross checked when NMR works
** pNMR System Check: Follow procedure in [https://logbooks.jlab.org/entry/3797950]
+
** pNMR Online analysis: Using Labview program to analysis pNMR FID signal (see [https://logbooks.jlab.org/entry/3807141])
** pNMR Online analysis: Using Labview program to analysis pNMR FID signal (see [https://logbooks.jlab.org/entry/3807141]); Need to create a archived EPICS variable to record polarization measurement results from pNMR. (might need Brad’s help)
+
*** Need to create a archived EPICS variable to record polarization measurement results from pNMR. [Brad, Chris, Mingyu]
  
 
*; EPR problems : [https://logbooks.jlab.org/entry/3793821] saw some progress on Tuesday [https://logbooks.jlab.org/entry/3796852], but issues remain.
 
*; EPR problems : [https://logbooks.jlab.org/entry/3793821] saw some progress on Tuesday [https://logbooks.jlab.org/entry/3796852], but issues remain.
 
** Tentative plan now is to continue the d2n program by replacing the photo-diode that is placed directly on the pumping chamber (we have many spares).  
 
** Tentative plan now is to continue the d2n program by replacing the photo-diode that is placed directly on the pumping chamber (we have many spares).  
** It would be good to write up a procedure to streamline this replacement procedure for us and RadCon
+
*** It would be good to write up a procedure to streamline this replacement procedure for us and RadCon
 
** Maybe design a new mount for the photodiode replacing the old mount designed for the fiber bundle
 
** Maybe design a new mount for the photodiode replacing the old mount designed for the fiber bundle
  
*; Target Lasers :
+
*; Target work
** Check laser power and wavelength
 
** Check laser alignment
 
** Implement another laser spectrometer for transverse polarization
 
 
 
*; Target work:
 
** NMR checkout/fixes
 
** EPR checkout/fixes
 
 
** Spin up curves for all 4 polarization directions, configurations
 
** Spin up curves for all 4 polarization directions, configurations
  

Revision as of 13:59, 29 June 2020

Onsite Personnel Guidance

NOTE: I'm not 100% sure what restrictions on 'visitor' access may be imposed by the Lab.
** Confirm travel plans in advance to help minimize 2 week quarantine on arrival! **
** Make sure your training and Site Visit status is still current to avoid delays. **

Training / Resumption of Physics Guidance

People

  • Stationed here w/ polhe3 as a priority
    • Brad, JP, Junhao, Mingyu, Bill, Arun
    • David Flay is new staff hire -- did thesis on 6 GeV d2n measurement!
    • Carlos Y (new Hall C postdoc) will be able to help by June
    • Mike Nycz (former Hall A grad student, now Temple post-doc) -- available to help
  • Offsite, but not too far away
    • [W&M] Todd, + 2 grad students (for shifts), post-doc (can RC)
    • [UVa] Xiaochao, Jixie, Gordon?, Chris J
  • Offsite, but plan to return when we know dates
    • Murchhana
    • Melanie

Tasks to complete before we get back on-site

  • These will likely require OSPs to be written up and approved
    • Remove/replace target enclosure panels
    • Laser/optics work on the target platform
    • Laser/optics work in the CH laser room (?)
    • Mounting a new cell (not an immediate task) [RadCon involvement too]
    • Install collimator for 1-pass running
    • EPR photo diode replacement?

Pre-beam Target Work

  • 'Spot check' B-field at target location for SHMS
    • 18 deg, -5.6 GeV/c as a cross check of the TOSCA modelling for production
    • 11 deg, -2.1 GeV/c as a cross check of the TOSCA modelling for elastics
  • We have agreed to rotate the HMS to 20 degrees (kin C) and start running with the HMS at that angle. (The SHMS will remain at its current 11 degree 'Kin X'.) This will allow the SOLID Prototype folks to get their small-angle test completed with minimal impact on our production running. (They will setup at small angle and do all their checkout tests well before beam.)
    • I (Brad) think this sounds OK, but everyone should think through what we need to do and let us know if there is anything that would require moving the HMS in to small angles, even temporarily!, during our pre-beam setup!
  • Purchase another reference cell [JP, Todd]
    • No spares right now
  • Restore items noted in HCLOG 3809218 when site access is restored. [Brad]
  • Spectrum analyzer for transverse configuration ASAP [Junhao]
    • Needs fiber pulled from target to behind
  • Laser Repair [Junhao, JP]
    • Shipped to Raytum; returned on ___________________ ?
  • Laser Control Software Update [Carlin, Brad]
    • Three new lasers require modifications/updates to our existing laser control software.
      • These changes must be integrated with the existing EPICS logging that has been added to the our laser control software.
    • Chris Carlin has agreed to take care of this. He has the software to do the updates in parallel, but will need some testing time on polhe1 later this week. (29 Jun 2020)
  • Test Kepco in current mode (Bill)
    • New power supply is now on-site at JLab
    • New filter (for 180 Hz) to install for current mode operation fix. Can always go to voltage mode if it doesn't work.
    • Establish/verify a known-good production mode
    • Further Details can be found here [1]
  • AnywhereUSB bridge issues
    • Contact with Target readbacks through AnywhereUSB USB bridge still drop out on occasion
    • Description of situation during A1n run:
      • At first, we fixed a network problem raised by Ethan. And this decreased the frequency of the drop out
      • Later, there are two scenarios for the drop out. For the first scenario which happened more frequently, after the device dropped out, we just need to close the individual labview programs with the devices dropped out and wait for the device to come back then reopen the program. If the device do not show up in the first scenario, then we need to close the Labview and restart the computer. (Seems like more of a software issue, not hardware?)
  • Prep a new target cell [Chris J., Todd?, Arun]
    • Chris working on characterizing Tommy and Butterball -- needs to get back in his Lab to wrap things up.
      • Will plan to get things finalized by early June
    • Do we need any hardware at JLab to have a cell ready [Arun, Bert]
      • Double check if we have enough oven seals, seal halves (x6), small dowels (x3), bottom plate (?)
      • Next cell is Tommy -- where is it?
  • NMR issues [Junhao]
    • Transverse NMR not fully working yet
    • NMR Calibration Constants : Verify that calibration constants and input values associated with NMR and other polarimetry are consistent and will be correct when the software is restarted
  • pNMR issues [Mingyu]
    • Signal present in Transverse mode, but needs to be calibrated/cross checked when NMR works
    • pNMR Online analysis: Using Labview program to analysis pNMR FID signal (see [7])
      • Need to create a archived EPICS variable to record polarization measurement results from pNMR. [Brad, Chris, Mingyu]
  • EPR problems
    [8] saw some progress on Tuesday [9], but issues remain.
    • Tentative plan now is to continue the d2n program by replacing the photo-diode that is placed directly on the pumping chamber (we have many spares).
      • It would be good to write up a procedure to streamline this replacement procedure for us and RadCon
    • Maybe design a new mount for the photodiode replacing the old mount designed for the fiber bundle
  • Target work
    • Spin up curves for all 4 polarization directions, configurations

Pending Issues

  • Verify that all other EPICS channels are present and are still being archived [Brad]
    • Correction coil currents channels need to be added to archiver. HLC:He3:FieldCorr*
  • Look at trigger related signals on the scope under high load (reftime extra pules, FADC reftime-shaper pileup?, NGC noise/rate questions) [Brad]
    • investigate FADC 'blocking' artifact (pulse pile-up, undershoot, weirdness?) for SHMS NGC PMT0, reftime shapers
  • Check cabling on NGC PMT3 (12 ns later than other PMTs in TDC spectrum) [Brad]
  • Check cabling on SHMS Shower Layer1, PMT4 timing (25ns difference vs other PMTs) [Brad]
  • Get 3H07B Harp repaired [10] [11]; and a puzzle [12]
    • This is being pursued by Brad, Thia, et al. Still trying to make sure it gets on EES/IC's pre-beam repair list.
    • Repair work is now scheduled (nominal start June 22) [13]
      • Harp removed, and being repaired (June 26)
  • 2mm reference cell offset [Todd, JP, Brad]
    • Is there a way to shift the reference cell position before beam starts?
    • Arun's HCLOG 3807201 about the unfortunate reference cell alignment vs. the rest of the target ladder.
    • NOTE: "Shift Leader must request a beam that is shifted horizontally to the beam left side by 2 mm to prevent scraping."
  • Verify that inputs to 'Scale32'/G0 scalers (ie ROC5) are > 10ns in width. [Brad, Steve]
    • replace the G0 scalers with something newer/better (SIS38xx or similar)
    • Steve is replacing the G0 scalers with SIS38xx units (June 2020)
  • Extended-target optics analysis [Mark]
    • Incorporate into online (and offline) replay code
  • Online analysis software ready to go? [Sylvester?, Brad]
    • Most should be fine, but are we missing any 'physics' plots?
    • Merge and test code updates to hcana / hallc_replay:
      • Better error handling and typo in our SHMS shower PARAM file [14]
  • HMS Q3 LCW leak --supply and return valves were closed [15]
  • Fix the EPICS variable calculation for target field angle [Bill]
    • This is the PV which is calculated from the coils currents that is in the startOfRun entries.
    • It needs a new formula since we changes the coil orientation
  • Target Ladder software must throw an error on a 'voltage' readback mismatch! [16]
    • Ethan reports this is complete and an updated screen is installed
  • iochc10 issues [Gaskell]
    • iochc10 should be removed from OPS monitoring systems -- Hall C monitors it now (5/27 DG)
  • Compton related items in Hall C beam steer-up procedure still cause confusion between MCC and Shift Crew [Gaskell]
    • Procedures need to be updated at MCC (Should be completed 5/27 DG)

Pre-beam punchlist

Copied from pre-beam punchlist done just before MC6 shutdown. Some items should be completed but require verification/confirmation.

Techs w/ RadCon [Todd (or designate) for cooling jets]

  • Turn on turbos for downstream beamline
  • Turn on turbos for SHMS and HMS spectrometer vacuums
  • Remove the guards on the SHMS and HMS entrance windows (verify)
  • Remove the guards on the both upstream and downstream beamline windows (verify)
  • Ensure the beamline window cooling jets are in position and on (verify)
  • Ensure the target window cooling jets are in position and on (verify)
  • ??

Miscellaneous

  • [Gaskell] Moller work and cool-down [17]
  • [RadCon, RC] RadCon checklist
  • [Gaskell] Beamline checklist
  • [Brad] Detector/DAQ checklist
  • [Walter] Hall checklist
  • [OPS, RC] Schedule hot checkout of Hall C arc magnets/power-supplies
  • [OPS, RC] Verify all relevant FSDs that may have been masked for the down are known about and ready to unmasked when appropriate
  • [Lassiter] Enable all spectrometer magnet supplies, restore production settings for Cryo
  • [Brad] Double check that rotation is enabled in the GUIs for both spectrometers
  • [Brad] Ramp all SHMS and HMS magnets to something modest (quick check), or to first kinematic. For example
    • SHMS: 11.0deg, 7.5 GeV/c
    • HMS: 13.5deg, 4.2 GeV/c
    • NOTE: Coordinate with the target group on the appropriate HB setting so we don't interfere with any target pumping.
  • [Techs, Brad?] Do a final check to ensure that there are no potential issues with remote spectrometer rotation
  • Restart main alarm handler (resets masked channels)
  • Restart target alarm handler (if needed)
  • ??