*Yesterday (12/18)
 
*Yesterday (12/18)
** Shortly after (12/18) Owl shift started, there was another PSS failure and Hall C suddenly dropped to restricted access.  
+
** Shortly after (12/18) Owl shift started, there was another PSS communication failure and Hall C suddenly dropped to restricted access.  
 
*** The tech on-call wasn't able to restore the system.
 
*** The tech on-call wasn't able to restore the system.
 
*** The expert arrived at 8AM and made hardware replacements.  
 
*** The expert arrived at 8AM and made hardware replacements.  
Line 66: Line 66:
 
** I was assured at the 8:00AM meeting today that they are taking the incident seriously and are still investigating.  
 
** I was assured at the 8:00AM meeting today that they are taking the incident seriously and are still investigating.  
 
** Doug mentioned that they are considering reporting it as an "incident" to the DOE in part due to all the equipment damage.  
 
** Doug mentioned that they are considering reporting it as an "incident" to the DOE in part due to all the equipment damage.  
 +
* PSS issues.
 +
** Should be fixed now with the new hardware.
 +
** BUT it seems very wired to me that the failure mode is to drop to restricted access. I'm not sure if safety is taking my criticism about that seriously.
 
* Unser
 
* Unser
 
** Front end electronics suspected to be damaged from the radiation from the beam energy measurement.
 
** Front end electronics suspected to be damaged from the radiation from the beam energy measurement.
Line 72: Line 75:
 
* Radiation Damage in general.
 
* Radiation Damage in general.
 
** We should be on the lookout for other hardware that may have been damaged by radiation.  
 
** We should be on the lookout for other hardware that may have been damaged by radiation.  
 +
  
 
= Planned Accesses to the Hall =
 
= Planned Accesses to the Hall =

Revision as of 10:24, 19 December 2022

RC Meeting Information

RC Daily Meetings are at 11:00 (am) via Zoom and in person in the counting house meeting room (2nd floor)

  • Zoom remote connection information:
 Join ZoomGov Meeting
 https://jlab-org.zoomgov.com/j/1607100885?pwd=ZFBsRTFsYm5Zb0laZ0tyZXNjcEE0QT09
 Meeting ID: 160 710 0885
 Passcode: 595071
 One tap mobile
 +16692545252,,1607100885# US (San Jose)
 +16468287666,,1607100885# US (New York)
 Dial by your location
       +1 669 254 5252 US (San Jose)
       +1 646 828 7666 US (New York)
       +1 669 216 1590 US (San Jose)
       +1 551 285 1373 US
       833 568 8864 US Toll-free
 Meeting ID: 160 710 0885
 Find your local number: https://jlab-org.zoomgov.com/u/ab2CekLXgQ

Useful Links

Current Status

  • Today (12/19)
    • Beam taken away at 7am as scheduled.
    • Hall C in Controlled Access.
    • Beginning of the scheduled accelerator down.
    • SHMS and HMS magnets ramped to zero.
    • SHMS and HMS TVs are off.
    • Dave Meekins arrived at 8:30AM to begin warming up the target.
  • Yesterday (12/18)


Current Run Plan

  • Is there any work that needs to be coordinated by RC today?
    • (I don't think so)
  • No Hall C meeting today.
  • Scan run sheets?

Notices in Effect for Shift Crew

Current Issues

  • Beam Energy Measurement
    • I was assured at the 8:00AM meeting today that they are taking the incident seriously and are still investigating.
    • Doug mentioned that they are considering reporting it as an "incident" to the DOE in part due to all the equipment damage.
  • PSS issues.
    • Should be fixed now with the new hardware.
    • BUT it seems very wired to me that the failure mode is to drop to restricted access. I'm not sure if safety is taking my criticism about that seriously.
  • Unser
  • Radiation Damage in general.
    • We should be on the lookout for other hardware that may have been damaged by radiation.


Planned Accesses to the Hall

Planned Accelerator Configuration Changes

Special Requests

  • Happy Holidays!