Difference between revisions of "December 2, 2023"

From HallCWiki
Jump to navigationJump to search
(Created page with "= RC Meeting Information = <b> RC Daily Meetings are at 11:00 (am) via Zoom and in person in the counting house meeting room (2nd floor) </b> * Zoom remote connection informa...")
 
Line 14: Line 14:
  
 
= Current Status =
 
= Current Status =
*  
+
* Moller is ready to take measurement whenever we are https://logbooks.jlab.org/entry/4229528
 +
* Ellen fixed the dipole PLC! https://logbooks.jlab.org/entry/4229581
 +
* ODH alarm went off yesterday in the Hall due to testing (ultimately a non-issue) https://logbooks.jlab.org/entry/4229565
  
 
= Current Run Plan =  
 
= Current Run Plan =  
*  
+
* Calorimeter to be moved back in place 9am, then remove NPS sweeper locks
 +
* Hall will be swept to go to power permit after that
 +
* Setup beam, start run plan
  
 
= Notices in Effect for Shift Crew =
 
= Notices in Effect for Shift Crew =
*  
+
* Don't ramp the HMS dipole until cleared by Heidi (waiting for cry to recover) https://logbooks.jlab.org/entry/4229582
  
 
= Current Issues =
 
= Current Issues =

Revision as of 15:14, 1 December 2023

RC Meeting Information

RC Daily Meetings are at 11:00 (am) via Zoom and in person in the counting house meeting room (2nd floor)

Useful Links

Current Status

Current Run Plan

  • Calorimeter to be moved back in place 9am, then remove NPS sweeper locks
  • Hall will be swept to go to power permit after that
  • Setup beam, start run plan

Notices in Effect for Shift Crew

Current Issues

Planned Accesses to the Hall

Planned Accelerator Configuration Changes

Special Requests