Difference between revisions of "December 2, 2023"

From HallCWiki
Jump to navigationJump to search
Line 17: Line 17:
 
* Ellen fixed the dipole PLC! https://logbooks.jlab.org/entry/4229581
 
* Ellen fixed the dipole PLC! https://logbooks.jlab.org/entry/4229581
 
* ODH alarm went off yesterday in the Hall due to testing (ultimately a non-issue) https://logbooks.jlab.org/entry/4229565
 
* ODH alarm went off yesterday in the Hall due to testing (ultimately a non-issue) https://logbooks.jlab.org/entry/4229565
* Summary of calorimeter work
+
* Summary of calorimeter work https://logbooks.jlab.org/entry/4229600
  
 
= Current Run Plan =  
 
= Current Run Plan =  

Revision as of 21:13, 1 December 2023

RC Meeting Information

RC Daily Meetings are at 11:00 (am) via Zoom and in person in the counting house meeting room (2nd floor)

Useful Links

Current Status

Current Run Plan

  • Calorimeter to be moved back in place 9am, then remove NPS sweeper locks
  • Hall will be swept to go to power permit after that
  • Setup beam, start run plan

Notices in Effect for Shift Crew

Current Issues

Planned Accesses to the Hall

Planned Accelerator Configuration Changes

Special Requests