RC Meeting Information
RC Daily Meetings are at 11:00 (am) via Zoom and in person in the counting house meeting room (2nd floor)
- Zoom remote connection information: https://logbooks.jlab.org/entry/4229331
Useful Links
Current Status
- Hall is in Controlled Access.
- TO and SL are cancelled. TO on Tuesday day is on standby.
- Calorimeter work will commence this afternoon.
Current Run Plan
- When we know about beam, we will re-condense the cryogenic target. It will be about 4-6 hours before we can use the cryogenics in beam after that.
- The initial gun injector work is complete. Now they are working on the beam spot and size coming out from the injector beamline.
- Estimate is beam to the Halls on swing shift Tuesday. Will revise this tomorrow at the 9am meeting.
Notices in Effect for Shift Crew
Current Issues
Planned Accesses to the Hall
- Calorimeter work