RC Meeting Information
RC Daily Meetings are at 11:00 (am) via Zoom and in person in the counting house meeting room (2nd floor)
- Zoom remote connection information: https://logbooks.jlab.org/entry/4229331
Useful Links
Current Status
- Hall is in Controlled Access.
- Calorimeter work will commence this afternoon.
Current Run Plan
- When we know about beam, we will re-condense the cryogenic target. It will be about 4-6 hours before we can use the cryogenics in beam after that.
- The initial gun injector work is complete. Now they are working on the beam spot and size coming out from the injector beamline.
- Estimate is beam to the Halls on swing shift Tuesday. Will revise this tomorrow at the 9am meeting.
Notices in Effect for Shift Crew
- TO and SL are cancelled. TO on Tuesday day is on standby.
Current Issues
Planned Accesses to the Hall
- Calorimeter work