Difference between revisions of "February 23, 2024"

From HallCWiki
Jump to: navigation, search
m (Current Run Plan)
Line 35: Line 35:
 
** We will start with setting up the corrector coils (Test plan is added to the MCC shift plan: https://ace.jlab.org/apps/pd/shift-plans/38835)
 
** We will start with setting up the corrector coils (Test plan is added to the MCC shift plan: https://ace.jlab.org/apps/pd/shift-plans/38835)
 
** Followed by lumi/background scans and potentially optics
 
** Followed by lumi/background scans and potentially optics
** DO we want another polarization measurement next week? When? HallB will do Moller measurements on Wed.
+
** Do we want another polarization measurement next week? When? HallB will do Moller measurements on Wed.
  
 
= Notices in Effect for Shift Crew =
 
= Notices in Effect for Shift Crew =

Revision as of 10:40, 23 February 2024

RC Meeting Information

RC Daily Meetings are at 11:00 (am) via Zoom and in person in the counting house meeting room (2nd floor)

Useful Links

Hall status

Accelerator status

  • Hall B taking beam
  • Maintenance + Beam study next Wednesday

Current Run Plan

Notices in Effect for Shift Crew

Current Issues

  • NPS crate #2 drops occasionally:
    • Ben had a closer look at the runs with the issue. He thinks that it might be because npsvtp1 clustering was messed up, and this causes a problem for the FADC readout mask logic.
    • Restarting a new run might be sufficient to clear it up.
    • Ben will check if a firmware update could help eliminating some of the problem.

Planned Access to the Hall

Special Requests

  • Guard house work from next Monday. Pay attention to the sign and follow the directions around there when coming to the accelerator site.