Tomorrow (03/04) the hall will go to Controlled access 7:30am-8:00am for the NPS setup change (https://logbooks.jlab.org/entry/4259689).
 
Tomorrow (03/04) the hall will go to Controlled access 7:30am-8:00am for the NPS setup change (https://logbooks.jlab.org/entry/4259689).
  
Bob Michaels and Hanjie would like to do some scaler tests with the DAQ during the downtime (see the comment to https://logbooks.jlab.org/entry/4259689).
+
Bob Michaels and Hanjie would like to do some scaler tests with the DAQ during the downtime on Monday (see the comment to https://logbooks.jlab.org/entry/4259689).
  
 
= Accelerator =
 
= Accelerator =

Revision as of 11:26, 3 March 2024

Back to the calendar

RC Meeting Information

Current RC: Iuliia Skorodumina

No RC meeting today.

Useful Links

Summary

Yesterday (03/02) during Day shift there were 3 hours with no beam due to the issues with Arc 7 Box Supply (https://logbooks.jlab.org/entry/4259708), but apart from that the beam delivery was very stable over the last 24 hours. There wasn't many interruptions on our side, too, so we were just smoothly taking data in KinC_x36_6 kinematics.

We will stay on this kinematic setting for 3 more shifts and on Monday morning we will proceed to the next kinematic setting, which is KinC_x25_4. Yesterday during the RC meeting we discussed background/currents/rates issues and Charles and Peter Bosted came up with the revised plan for NPS setup change on Monday Mar 4 (https://logbooks.jlab.org/entry/4259689). According to the new plan, we will move the calorimeter from 6m to 4 m and will keep the magnet wings on. We will stay on KinC_x25_4 until March 11.

Tomorrow (03/04) the beam will be taken away at 7:30am in the morning and the hall will go to Controlled access for the NPS setup change to be performed.

Day shift summary (https://logbooks.jlab.org/entry/4259614).

Swing shift summary (https://logbooks.jlab.org/entry/4259740).

Owl shift summary (https://logbooks.jlab.org/entry/4259902).

No RC meeting today.

Planned Access to the Hall

Tomorrow (03/04) the hall will go to Controlled access 7:30am-8:00am for the NPS setup change (https://logbooks.jlab.org/entry/4259689).

Bob Michaels and Hanjie would like to do some scaler tests with the DAQ during the downtime on Monday (see the comment to https://logbooks.jlab.org/entry/4259689).

Accelerator

n/a

Current Run Plan

Current Issues

  • Hanjie was concerned that some NPS crates have relatively higher fan temperatures (~95F). We put box fans for those crates. We also asked Facilities if they can lower the AC set point from 68F to 65F (was done on Wed 02/28).
  • On Saturday (03/01) during Swing the heater power for both the loops 1 and 2 dropped to zero and recovered in a few minutes (https://logbooks.jlab.org/entry/4259365).