Jump to navigationJump to searchLine 39: | Line 39: | ||
= Run Plan = | = Run Plan = | ||
− | * We are in | + | * We are in KinC_x50_0a Production. |
− | * | + | * When beam returns please proceed to KinC_x50_0a step 1.3, LD2 target, and the 5th (of sixteen) 30min runs with 15uA, ps4=0. Please screenshot the relevant CODA, trigger and NPS screens when production starts again. |
+ | * Full details in short-term run plan: https://hallcweb.jlab.org/wiki/index.php/Short_Term_Run-Plan | ||
+ | |||
+ | = Requests for shift crew = | ||
+ | * Please be sure to make screen shots as prompted in the run plan, eg first run of each new target cycle snapshot NPS scalers/anode currents, trigger rates, CODA data rate/livetime/event rate, as prompted in the run plan and of anything else appropriate that happens on shift (e.g. NPS sweeper and corrector settings) |
Revision as of 09:26, 13 March 2024
RC Meeting Information
RC Daily Meetings are at 11:00 (am) via Zoom and in person in the counting house meeting room (2nd floor)
- Zoom connection link: https://jlab-org.zoomgov.com/j/1617015555?pwd=L09IQ216dml6ZmM5ODExVjFsMX
- Meeting ID: 161 701 5555
- Passcode: 288953
Useful Links
- Short term run plan [1]
Summary
RC update 13th March: https://logbooks.jlab.org/entry/4265984
Planned Access to the Hall
Maintenance day today
Hall C is in Controlled access. We plan the following work in the Hall:
- NPS crew (4/5 students. Tasks include checking some noisy channels, replacing temperature sensors electronics, possibly replacing a few bases.
- Work needs to be completed by 3:30pm when the techs will return to move the calorimeter back to 4 m. Plan is to leave the hall by 4pm. Techs are unavailable between 2pm and 3:30pm.
- Techs also doing property inventory.
Accelerator
Maintenance day today with option of beam studies in INJ (https://logbooks.jlab.org/entry/4265990). Expect beam back for halls at ~21:00.
Run Plan
- We are in KinC_x50_0a Production.
- When beam returns please proceed to KinC_x50_0a step 1.3, LD2 target, and the 5th (of sixteen) 30min runs with 15uA, ps4=0. Please screenshot the relevant CODA, trigger and NPS screens when production starts again.
- Full details in short-term run plan: https://hallcweb.jlab.org/wiki/index.php/Short_Term_Run-Plan
Requests for shift crew
- Please be sure to make screen shots as prompted in the run plan, eg first run of each new target cycle snapshot NPS scalers/anode currents, trigger rates, CODA data rate/livetime/event rate, as prompted in the run plan and of anything else appropriate that happens on shift (e.g. NPS sweeper and corrector settings)