= Summary =  
+
= Summary =
 +
*Yesterday, while attempting to bring us back to production, there was a vacuum issue in the NE spreading.
 +
*have been down since ~11 am yesterday. Prior to the vacuum issue, the calorimeter was moved from 3 to 4 meters. Unfortunately, no data has been taken at this 4 meter setting.
 +
*This morning, will move the calorimeter back to 3 meters in anticipation of the resumption of beam.
 +
*While beam has down, a short access was made into the hall during the SWING shift. Module C3-R3 was replaced.
 +
*A full summary of the activities can be found in Josh's logbook entry: https://logbooks.jlab.org/entry/4270285
 +
*LED runs were taken during OWL shift.
  
 +
*Presently, work continues to address the vacuum issue. They expect to have a clearer idea about the timeline for resuming beam delivery around noon today,
  
 
= Planned Access to the Hall =
 
= Planned Access to the Hall =

Revision as of 08:41, 22 March 2024

RC Meeting Information

Current RC: Michael Nycz (mnycz@jlab.org)

RC Daily Meetings are at 11:00 (am) via Zoom and in person in the counting house meeting room (2nd floor)

Useful Links

Summary

  • Yesterday, while attempting to bring us back to production, there was a vacuum issue in the NE spreading.
  • have been down since ~11 am yesterday. Prior to the vacuum issue, the calorimeter was moved from 3 to 4 meters. Unfortunately, no data has been taken at this 4 meter setting.
  • This morning, will move the calorimeter back to 3 meters in anticipation of the resumption of beam.
  • While beam has down, a short access was made into the hall during the SWING shift. Module C3-R3 was replaced.
  • A full summary of the activities can be found in Josh's logbook entry: https://logbooks.jlab.org/entry/4270285
  • LED runs were taken during OWL shift.
  • Presently, work continues to address the vacuum issue. They expect to have a clearer idea about the timeline for resuming beam delivery around noon today,

Planned Access to the Hall

  • 03/22/2024 - Move NPS to 3 meters: KinC_x50_0 / NPS = 14.40 deg