= Table of Commissioning Tasks =
 
= Table of Commissioning Tasks =
 
{| border="1" cellpadding="2" valign="top" style="text-align: center;"
 
{| border="1" cellpadding="2" valign="top" style="text-align: center;"
| Task
+
| '''Task'''
| Person
+
| '''Person'''
| Comment
+
| '''Comment'''
 
|-
 
|-
 
| Harp Scans, BPM and Raster Checkout
 
| Harp Scans, BPM and Raster Checkout

Revision as of 15:17, 11 October 2017

Table of Commissioning Tasks

Task Person Comment
Harp Scans, BPM and Raster Checkout M. Jones
HMS & SHMS Hodoscope Checkout S. Malace
SHMS Quartz Plane S. Malace
HMS & SHMS DC Checkout, Tracking Efficiency and Alignment H. Szumila-Vance, C. Yero
HMS & SHMS Heavy Gas Cherenkov Checkout E. Pooser, R. Ambrose
HMS & SHMS Pre-Shower/Shower Checkout H. Mkrtchyan, A. Asaturyan, V. Berdnikov
SHMS Aerogel Checkout H. Mkrtchyan, A. Asaturyan, V. Berdnikov
HMS & SHMS 3/4 Trigger Efficiency Checkout B. Sawatzky, E. Pooser, C. Yero
HMS & SHMS PID Trigger Efficiency Checkout B. Sawatzky, E. Pooser, C. Yero
Beam Energy M. Jones, D. Mack
BCM Calibration D. Mack, D. Bhetuwal
Target Boiling D. Gaskell
Carbon Elastic with Sieve for Final SHMS Tune Determination M. Jones, H. Szumila-Vance
Carbon Elastic Scan for Delta Matrix Optimization H. Bhatt, D. Dutta
Carbon Inelastics with Sieve for Ytgt, Y’tgt and X’tgt (Need 20 deg for Ytgt) M. Jones, H. Szumila-Vance
Sieve Check After Cycling SHMS Magnets from Positive to Negative and Back M. Jones
Determine SHMS Central Momentum and Angle with Set of Elastic ep Data A. Karki, S. Basnet, D. Dutta
Inelastic Carbon Xn Measurements with Overlapping Momentum Settings for Acceptance Check M. Jones, B. Duran
GEM Front Sieve to Better Understand HB. Do Optics with p+ to Check Optics L. Kabir, D. Dutta
Coincidence Timing Checkout and Optimization B. Sawatzky, E. Pooser, C. Yero
Electronic Dead Time Checkout B. Sawatzky, E. Pooser, C. Yero
Single Kaon Production. Coincidence p and K Production

Fall 2017 Commissioning Plan

  • The plan will be base on the plan of the full SHMS/HMS commissioning.