Difference between revisions of "RC meeting and Run Plan, Monday Nov 5"

From HallCWiki
Jump to: navigation, search
(Created page with "==Status== * Down for Beam studies (~4hrs) today, should be up and running again this afternoon * Finishing up [https://hallcweb.jlab.org/wiki/index.php/5_pass_Run_Plan#Kinema...")
 
Line 3: Line 3:
 
* Finishing up [https://hallcweb.jlab.org/wiki/index.php/5_pass_Run_Plan#Kinematic_Group_18 Kin Group 18]
 
* Finishing up [https://hallcweb.jlab.org/wiki/index.php/5_pass_Run_Plan#Kinematic_Group_18 Kin Group 18]
 
* Hall D TAC run on Wednesday Day should not affect Hall C
 
* Hall D TAC run on Wednesday Day should not affect Hall C
 +
 +
* [https://hallcweb.jlab.org/wiki/index.php/File:McClellan_RC_Report.pdf Slides] for Weekly Meeting
  
 
==Time-Ordered Run Plan==
 
==Time-Ordered Run Plan==

Revision as of 12:37, 5 November 2018

Status

  • Down for Beam studies (~4hrs) today, should be up and running again this afternoon
  • Finishing up Kin Group 18
  • Hall D TAC run on Wednesday Day should not affect Hall C

Time-Ordered Run Plan

SHMS POLARITY CHANGE

  • Kin18.3 current setting
  • Kin18.4 ...
  • Kin14.5

SHMS POLARITY CHANGE (all else same)

  • Kin13.5

Then well start on Kin Groups 15 and 16

Reminders

  • Take one HMS monitoring run each shift
  • For all settings, for each target, split the desired charge between three runs
  • Listed currents are estimates. For runs at less than 60uA, increase current until SHMS singles rates are between 400k-500k.

Issues

Planned access to the hall

  • No Planned Accesses