Difference between revisions of "RC meeting and Run Plan, Sunday March 10"

From HallCWiki
Jump to: navigation, search
(Created page with "= RC Meeting Information = <b> RC Daily Meetings are at 4:30 PM, 2nd floor Counting House Meeting Room </b> * Bluejeans remote connection information: To join the Meeting:...")
 
(Current Status)
 
Line 25: Line 25:
  
 
= Current Status =
 
= Current Status =
 +
* Completed Q2=5.5, x=0.65, pi- setting
 
* Q2=5.5, x=0.65 (pi+) kinematic setting in progress
 
* Q2=5.5, x=0.65 (pi+) kinematic setting in progress
 
* Beam studies have been canceled for Monday - there is no scheduled break in running next week. RF recovery may be scheduled if needed.
 
* Beam studies have been canceled for Monday - there is no scheduled break in running next week. RF recovery may be scheduled if needed.

Latest revision as of 10:00, 10 March 2019

RC Meeting Information

RC Daily Meetings are at 4:30 PM, 2nd floor Counting House Meeting Room

  • Bluejeans remote connection information:
 To join the Meeting:
 https://bluejeans.com/861439920
 To join via Room System:
 Video Conferencing System: bjn.vc -or-199.48.152.152
 Meeting ID : 861439920
 To join via phone :
 1)  Dial:
   +1.408.740.7256 (US (San Jose))
   +1.888.240.2560 (US Toll Free))
   +1.408.317.9253 (US (Primary, San Jose))
   (see all numbers - http://bluejeans.com/numbers)
 2)  Enter Conference ID : 861439920

Useful Links

Current Status

  • Completed Q2=5.5, x=0.65, pi- setting
  • Q2=5.5, x=0.65 (pi+) kinematic setting in progress
  • Beam studies have been canceled for Monday - there is no scheduled break in running next week. RF recovery may be scheduled if needed.

Current Run Plan

  • Continue Q2=5.5, x=0.65 (pi+) kinematics.
    • For pi+ running, we are trying to match the SHMS 3/4 rates that we saw for pi-
    • For Q2=5.5, x=0.65, this means our target 3/4 rates should be:
      • z=0.7: 100 kHz
      • z=0.6: 180 kHz
      • z=0.5: 365 kHz
      • z=0.4: 500 kHz
  • This setting take us well into Monday.
  • Next, we will proceed to Setting 35: Q2=5.5, x=0.5, (pi-).

Notices in Effect for Shift Crew

  • Monitor SHMS 3/4 rates - maximum rate 500 kHz.
  • HMS polarity cannot be changed remotely - requires hall access. (Note: no polarity changes need for CSV).
  • When setting HMS Q1, always reduce current in steps of 50 A or less.

Current Issues

Planned Accelerator Configuration Changes

Special Requests