+ | == Pending Issues == | ||
* Fix the epics variable for target field angle. This is the PV which is calculated from the coils currents that is in the startOfRun entries. It needs a new formula since we changes the coil orientation (Bill) | * Fix the epics variable for target field angle. This is the PV which is calculated from the coils currents that is in the startOfRun entries. It needs a new formula since we changes the coil orientation (Bill) | ||
* Test Kepco in current mode (Bill) | * Test Kepco in current mode (Bill) | ||
+ | ** New filter (for 180 Hz) to install for current mode operation fix. Can always go to voltage mode if it doesn't work. | ||
+ | ** Establish/verify a known-good production mode | ||
+ | |||
+ | * Target Ladder software must throw an error on a 'voltage' readback mismatch! [https://logbooks.jlab.org/entry/3808208] -- Ethan working on this | ||
+ | * '''Get 3H07B Harp repaired''' [https://logbooks.jlab.org/entry/3806597] [https://logbooks.jlab.org/entry/3806573]; and a puzzle [https://logbooks.jlab.org/entry/3807995] | ||
+ | * https://logbooks.jlab.org/entry/3807201 Has Arun's note about the unfortunate reference cell alignment. He implies | ||
+ | ** NOTE: '''"Shift Leader must request a beam that is shifted horizontally to the beam left side by 2 mm to prevent scraping."''' | ||
+ | |||
+ | * pNMR issues | ||
+ | ** Software : Software/driver issue needs to be resolved. Checkout during next non-production down time (Moller or SHMS fix) | ||
+ | |||
+ | * EPR problems : [https://logbooks.jlab.org/entry/3793821] saw some progress on Tuesday [https://logbooks.jlab.org/entry/3796852], but issues remain. | ||
+ | ** Tentative plan now is to continue the d2n (and A1n) program by replacing the photo-diode that is placed directly on the pumping chamber (we have many spares). | ||
+ | ** It would be good to write up a procedure to streamline this replacement procedure for us and RadCon | ||
+ | |||
+ | * NMR Calibration Constants : Verify that calibration constants and input values associated with NMR and other polarimetry are consistent and will be correct when the software is restarted | ||
+ | **[https://logbooks.jlab.org/entry/3796178] [https://logbooks.jlab.org/entry/3795421] [https://logbooks.jlab.org/entry/3795982] [https://logbooks.jlab.org/entry/3796117] [https://logbooks.jlab.org/entry/3796111] (Bill, Junhao, Arun) | ||
+ | *** Add list of calibration runs and what constants apply to what production runs here: [[PolHe3_Polarization_Measurements]] | ||
+ | |||
+ | * USB bridge : Contact with Target readbacks through AnywhereUSB USB bridge still drop out on occasion | ||
+ | |||
+ | * iochc10 issues : Green now: Rebooted 3/2/20 with Dave Gaskell assistance. OPs wished to reboot hung iochc10 [https://logbooks.jlab.org/entry/3795636], noted in December as well [https://logbooks.jlab.org/entry/3745818] | ||
+ | ** Confirm relevant procedures have been updated at MCC (Gaskell, Paul V.?) | ||
+ | ** This runs the Moller cryo controls and should not be rebooted without expert oversight (does not impact operations). D. Gaskell is looking into getting this addressed properly with OPs. | ||
+ | |||
+ | * Compton related items in Hall C beam steer-up procedure still cause confusion between MCC and Shift Crew -- Gaskell? | ||
+ | ** Procedures need to be updated at MCC | ||
+ | |||
+ | |||
+ | == Pre-beam punchlist == | ||
+ | Copied from pre-beam punchlist done just before MC6 shutdown. Some items are completed and just need verification (as needed). | ||
+ | |||
+ | === Techs w/ RadCon [Todd (or designate) for cooling jets] === | ||
+ | * Turn on turbos for downstream beamline | ||
+ | * Turn on turbos for SHMS and HMS spectrometer vacuums | ||
+ | * Remove the guards on the SHMS and HMS entrance windows (verify) | ||
+ | * Remove the guards on the both upstream and downstream beamline windows (verify) | ||
+ | * Ensure the beamline window cooling jets are in position and on (verify) | ||
+ | * Ensure the target window cooling jets are in position and on (verify) | ||
+ | * ?? | ||
+ | |||
+ | ===Miscellaneous=== | ||
+ | * [RadCon, RC] RadCon checklist | ||
+ | * [Gaskell] Beamline checklist | ||
+ | * [Brad] Detector/DAQ checklist | ||
+ | * [Walter] Hall checklist | ||
+ | * [OPS, RC] Schedule hot checkout of Hall C arc magnets/power-supplies | ||
+ | * [OPS, RC] Verify all relevant FSDs that may have been masked for the down are known about and ready to unmasked when appropriate | ||
+ | * [Lassiter] Enable all spectrometer magnet supplies, restore production settings for Cryo | ||
+ | * [Gaskell] Moller cooldown | ||
+ | * [Brad] Double check that rotation is enabled in the GUIs for both spectrometers | ||
+ | * [Brad] Ramp all SHMS and HMS magnets to something modest (quick check), or to first kinematic. For example: | ||
+ | ** SHMS: 11.0deg, 7.5 GeV/c | ||
+ | ** HMS: 13.5deg, 4.2 GeV/c | ||
+ | ** NOTE: Coordinate with the target group on the appropriate HB setting so we don't interfere with any target pumping. | ||
+ | * [Techs, Brad?] Do a final check to ensure that there are no potential issues with remote spectrometer rotation | ||
+ | * Restart main alarm handler (resets masked channels) | ||
+ | * Restart target alarm handler (if needed) | ||
+ | * ?? |
Revision as of 13:32, 20 April 2020
Pending Issues
- Fix the epics variable for target field angle. This is the PV which is calculated from the coils currents that is in the startOfRun entries. It needs a new formula since we changes the coil orientation (Bill)
- Test Kepco in current mode (Bill)
- New filter (for 180 Hz) to install for current mode operation fix. Can always go to voltage mode if it doesn't work.
- Establish/verify a known-good production mode
- Target Ladder software must throw an error on a 'voltage' readback mismatch! [1] -- Ethan working on this
- Get 3H07B Harp repaired [2] [3]; and a puzzle [4]
- https://logbooks.jlab.org/entry/3807201 Has Arun's note about the unfortunate reference cell alignment. He implies
- NOTE: "Shift Leader must request a beam that is shifted horizontally to the beam left side by 2 mm to prevent scraping."
- pNMR issues
- Software : Software/driver issue needs to be resolved. Checkout during next non-production down time (Moller or SHMS fix)
- EPR problems : [5] saw some progress on Tuesday [6], but issues remain.
- Tentative plan now is to continue the d2n (and A1n) program by replacing the photo-diode that is placed directly on the pumping chamber (we have many spares).
- It would be good to write up a procedure to streamline this replacement procedure for us and RadCon
- NMR Calibration Constants : Verify that calibration constants and input values associated with NMR and other polarimetry are consistent and will be correct when the software is restarted
- USB bridge : Contact with Target readbacks through AnywhereUSB USB bridge still drop out on occasion
- iochc10 issues : Green now: Rebooted 3/2/20 with Dave Gaskell assistance. OPs wished to reboot hung iochc10 [12], noted in December as well [13]
- Confirm relevant procedures have been updated at MCC (Gaskell, Paul V.?)
- This runs the Moller cryo controls and should not be rebooted without expert oversight (does not impact operations). D. Gaskell is looking into getting this addressed properly with OPs.
- Compton related items in Hall C beam steer-up procedure still cause confusion between MCC and Shift Crew -- Gaskell?
- Procedures need to be updated at MCC
Pre-beam punchlist
Copied from pre-beam punchlist done just before MC6 shutdown. Some items are completed and just need verification (as needed).
Techs w/ RadCon [Todd (or designate) for cooling jets]
- Turn on turbos for downstream beamline
- Turn on turbos for SHMS and HMS spectrometer vacuums
- Remove the guards on the SHMS and HMS entrance windows (verify)
- Remove the guards on the both upstream and downstream beamline windows (verify)
- Ensure the beamline window cooling jets are in position and on (verify)
- Ensure the target window cooling jets are in position and on (verify)
- ??
Miscellaneous
- [RadCon, RC] RadCon checklist
- [Gaskell] Beamline checklist
- [Brad] Detector/DAQ checklist
- [Walter] Hall checklist
- [OPS, RC] Schedule hot checkout of Hall C arc magnets/power-supplies
- [OPS, RC] Verify all relevant FSDs that may have been masked for the down are known about and ready to unmasked when appropriate
- [Lassiter] Enable all spectrometer magnet supplies, restore production settings for Cryo
- [Gaskell] Moller cooldown
- [Brad] Double check that rotation is enabled in the GUIs for both spectrometers
- [Brad] Ramp all SHMS and HMS magnets to something modest (quick check), or to first kinematic. For example:
- SHMS: 11.0deg, 7.5 GeV/c
- HMS: 13.5deg, 4.2 GeV/c
- NOTE: Coordinate with the target group on the appropriate HB setting so we don't interfere with any target pumping.
- [Techs, Brad?] Do a final check to ensure that there are no potential issues with remote spectrometer rotation
- Restart main alarm handler (resets masked channels)
- Restart target alarm handler (if needed)
- ??