(Created page with "= RC Meeting Information = <b> RC Daily Meetings are at 10 am, remote </b> * Bluejeans remote connection information: To join the Meeting: https://bluejeans.com/86143992...")
 
(Current Run Plan)
Line 32: Line 32:
 
# Oct 01 Day/Swing --> Oct 02 Owl/Day/Swing:
 
# Oct 01 Day/Swing --> Oct 02 Owl/Day/Swing:
 
#* Contine data-taking at current PION-LT kinematic setting ( low eps, Q2=6 GeV2, W=3.19, x=0.39 )  
 
#* Contine data-taking at current PION-LT kinematic setting ( low eps, Q2=6 GeV2, W=3.19, x=0.39 )  
#** Data collected as of 08:00 today: ??% of the total PAC approved beam charge accumulated. We --??--- 85 % of beam charge before lowering the beam current  to ~45 uA for the remainder of this kinematic until Sunday Morning.
+
#** Data collected as of 08:00 today: ??% of the total PAC approved beam charge accumulated. We ("have taken" or "still need to take") 85 % of beam charge before lowering the beam current  to ~45 uA for the remainder of this kinematic until Sunday Morning.
 
#**  From Jacob's estimates during Oct 01 Owl shift, we accumulated ~ 5 % / shift @ 60 uA of very stable beam. This would mean that we would reach ~85 % of beam charge by Saturday Oct 02 mid-Owl shift assuming beam keeps steady.  (<span style="color:red"> '''PENDING''' </span>)
 
#**  From Jacob's estimates during Oct 01 Owl shift, we accumulated ~ 5 % / shift @ 60 uA of very stable beam. This would mean that we would reach ~85 % of beam charge by Saturday Oct 02 mid-Owl shift assuming beam keeps steady.  (<span style="color:red"> '''PENDING''' </span>)
 
#** After 85% of beam charge has been accumulated (<span style="color:red">  this is contingent upon beam stability throughout weekend </span>), request to lower beam current to 45 uA to take the remaining data until Sunday Morning --> https://logbooks.jlab.org/entry/3914672  (<span style="color:red"> '''PENDING''' </span>)
 
#** After 85% of beam charge has been accumulated (<span style="color:red">  this is contingent upon beam stability throughout weekend </span>), request to lower beam current to 45 uA to take the remaining data until Sunday Morning --> https://logbooks.jlab.org/entry/3914672  (<span style="color:red"> '''PENDING''' </span>)
# SHMS Rotation to 5.5 deg has been scheduled to Hall C for Sunday Morning at 9:00 am (<span style="color:darkgreen"> '''CLEARED''' </span>)
+
# SHMS Rotation to 5.5 deg has been scheduled for a "Controlled Access" Sunday Morning at 9:00 am (<span style="color:darkgreen"> '''CLEARED''' </span>)
#* Will contact Walter Kellner after RC meeting today to determine availability of techs on weekend to co-ordinate entrance to Hall. Will also need to contact Radcon today to give a specific time range at which rotation will take place on Sunday Morning.  (<span style="color:red"> '''PENDING''' </span>)
+
#* Have contacted Amy Comer/Steve Lassiter and it was concluded that rotation does require 2 techs for beamline spotting during rotation
#** Rotation will require 2 beamline spotters (1 on top of HMS platform and one on the floor in-between HMS/SHMS)
+
#** 1 tech on top of HMS platform + 1 tech on floor (in-between HMS/SHMS spectrometers as closes as possible to the pivot area)  
#** Garth will volunteer to be a beamline spotter in case in case one of the techs cannot come in on a weekend, but an expert spotter (tech) is still required at the pivot
+
#** Garth will volunteer to be a beamline spotter in case in case additional beamline spotters are needed
#** If possible, do rotation in "Controlled Access" (spotter in pivot will have to use ALARA to minimize time near radiation area),  otherwise, will go into "Restricted Access" (takes a bit longer)
+
#* Have contacted Walter and 2 techs can ONLY come in on Sunday
 +
#* Have contacted Radcon, and they will provide support as well
 +
#* Brad will also come to install spare HCCAM03 as the previous one has been fried --> [https://logbooks.jlab.org/entry/3915871 HCCAM03 Broken]
  
 
= Current Issues =
 
= Current Issues =

Revision as of 11:53, 1 October 2021

RC Meeting Information

RC Daily Meetings are at 10 am, remote

  • Bluejeans remote connection information:
 To join the Meeting:
 https://bluejeans.com/861439920
 To join via Room System:
 Video Conferencing System: bjn.vc -or-199.48.152.152
 Meeting ID : 861439920
 To join via phone :
 1)  Dial:
   +1.408.740.7256 (US (San Jose))
   +1.888.240.2560 (US Toll Free))
   +1.408.317.9253 (US (Primary, San Jose))
   (see all numbers - http://bluejeans.com/numbers)
 2)  Enter Conference ID : 861439920

Useful Links

Accelerator Status

  1. --
    • --

Hall C Status

  1. --
    • --

Current Run Plan

  1. Oct 01 Day/Swing --> Oct 02 Owl/Day/Swing:
    • Contine data-taking at current PION-LT kinematic setting ( low eps, Q2=6 GeV2, W=3.19, x=0.39 )
      • Data collected as of 08:00 today: ??% of the total PAC approved beam charge accumulated. We ("have taken" or "still need to take") 85 % of beam charge before lowering the beam current to ~45 uA for the remainder of this kinematic until Sunday Morning.
      • From Jacob's estimates during Oct 01 Owl shift, we accumulated ~ 5 % / shift @ 60 uA of very stable beam. This would mean that we would reach ~85 % of beam charge by Saturday Oct 02 mid-Owl shift assuming beam keeps steady. ( PENDING )
      • After 85% of beam charge has been accumulated ( this is contingent upon beam stability throughout weekend ), request to lower beam current to 45 uA to take the remaining data until Sunday Morning --> https://logbooks.jlab.org/entry/3914672 ( PENDING )
  2. SHMS Rotation to 5.5 deg has been scheduled for a "Controlled Access" Sunday Morning at 9:00 am ( CLEARED )
    • Have contacted Amy Comer/Steve Lassiter and it was concluded that rotation does require 2 techs for beamline spotting during rotation
      • 1 tech on top of HMS platform + 1 tech on floor (in-between HMS/SHMS spectrometers as closes as possible to the pivot area)
      • Garth will volunteer to be a beamline spotter in case in case additional beamline spotters are needed
    • Have contacted Walter and 2 techs can ONLY come in on Sunday
    • Have contacted Radcon, and they will provide support as well
    • Brad will also come to install spare HCCAM03 as the previous one has been fried --> HCCAM03 Broken

Current Issues

  1. Target ladder camera was identified to be bad: Joe Beaufait will purchase a replacement in the next funding cycle ( PENDING )
    • Still need to follow-up with Joe about when the purchase can be done.

Special Requests

  1. Contact Ellen Becker if there is an opportunity to access the hall (longer than 4 hours). This is for diagnosing the SHMS power supply.