(Current Issues)
(Planned Accesses to the Hall)
Line 30: Line 30:
  
 
= Planned Accesses to the Hall =                                                                                                                                                                           
 
= Planned Accesses to the Hall =                                                                                                                                                                           
* During the accelerator full maintenance day (Thursday Jun 23, 2022)                                                                                                                                     
+
* During the accelerator full maintenance day (TODAY)                                                                                                                                     
 
**S. Lassiter needs to put crush washers in LCW filters, so we may see a little bit of water by the HMS boogie for now, until he can put the washers next week, during maintenance period [https://logboo\
 
**S. Lassiter needs to put crush washers in LCW filters, so we may see a little bit of water by the HMS boogie for now, until he can put the washers next week, during maintenance period [https://logboo\
 
ks.jlab.org/entry/4003796 HMS Dipole LCW]  (<span style="color:red"> '''PENDING''' </span>) NOTE: Actually, Heidi and Jack will will need to access Hall C to work on HMS dipole, to get dimensions befor\
 
ks.jlab.org/entry/4003796 HMS Dipole LCW]  (<span style="color:red"> '''PENDING''' </span>) NOTE: Actually, Heidi and Jack will will need to access Hall C to work on HMS dipole, to get dimensions befor\
Line 37: Line 37:
 
color:red"> '''PENDING''' </span>) See HMS DC Card Map: https://hallcweb.jlab.org/wiki/images/1/11/HMS_DriftChamberPlanesLayout.pdf and log-entry: https://logbooks.jlab.org/entry/4005562 describing whi\
 
color:red"> '''PENDING''' </span>) See HMS DC Card Map: https://hallcweb.jlab.org/wiki/images/1/11/HMS_DriftChamberPlanesLayout.pdf and log-entry: https://logbooks.jlab.org/entry/4005562 describing whi\
 
ch wire groups are noisy                                                                                                                                                                                   
 
ch wire groups are noisy                                                                                                                                                                                   
**Xinzhan Bai and Jixie Zhang request to change gas bottle for solid Cherenkov detector: Contact: xbai@jlab.org,  cell: (434) 422-2809  (<span style="color:red"> '''PENDING''' </span>)                
+
**Xinzhan Bai and Jixie Zhang request to change gas bottle for solid Cherenkov detector: Contact: xbai@jlab.org,  cell: (434) 422-2809  (<span style="color:red"> '''PENDING''' </span>)
                                                                                                                                                                                                         
+
 
 
= Planned Accelerator Configuration Changes =                                                                                                                                                             
 
= Planned Accelerator Configuration Changes =                                                                                                                                                             
 
* Full accelerator maintenance day on Thursday, Jun 23. Beam will be taken away at 6:30 am                                                                                                                 
 
* Full accelerator maintenance day on Thursday, Jun 23. Beam will be taken away at 6:30 am                                                                                                                 

Revision as of 07:25, 23 June 2022

Current Status

  • Accelerator status:
    • Beam went away at 6:15 am for planned maintenance day and power shed
    • Restoration should occur late DAY or Early SWING
    • Will try to push to 80 uA (current 45 uA is highest stable available current)
  • Experiment status:
    • pionLT continues to make progress on run plan, though we are still behind schedule, unless Ops is able to deliver 80 uA at >50% efficiency after full maintenance tomorrow.
    • Q1 Interlock at 4:30 am. No production data since. Will address DAY shift
    • On page 33 of run plan. New Setting: Q2=2.45, W=3.20, x=0.21, high ε data taking. Angles are set, awaiting SHMS Q1 to set momentum

Current Run Plan

pionLT Summer 2022 Run Plan
Physics Status

Notices in Effect for Shift Crew

  • Please pro-rate ABU for max current limit in run plan (uA) in beam time accounting. For example, if we receive 15 uA instead of the max_current_limit in the run plan, then the ABU should be: ABU_pro\

rated = 15/(max current limit) * ABU

  • Check the HMS/SHMS rates for when production starts, since for Heep coin. production SHMS saw higher rates. Make sure shift crew takes snapshot of scalers at every setting
  • When analyzing LD2 or Al dummy or LH2, please leave the target_mass_amu in the standard.kinematics as that of the proton, but when analyzing the data with the pionLT script, specify the target used, \

as different targets will have different ranges in the cuts when integrating the missing mass peak. Refer to log entry: https://logbooks.jlab.org/entry/4005387 These instructions are given in the pionL\ T run plan.

Current Issues

24 This issue will have to be addressed during next Hall C access during accelerator maintenance day TODAY

  • Hall C BCMs and Accelerator BCMc (i.e., MPS BCMs) mismatch --> https://logbooks.jlab.org/entry/4005801
    • I would think this is just a scale factor missing between the two measurements? Usually S. Wood did this in the past. I have notified S. Wood in the log-entry

Planned Accesses to the Hall

  • During the accelerator full maintenance day (TODAY)
    • S. Lassiter needs to put crush washers in LCW filters, so we may see a little bit of water by the HMS boogie for now, until he can put the washers next week, during maintenance period [https://logboo\

ks.jlab.org/entry/4003796 HMS Dipole LCW] ( PENDING ) NOTE: Actually, Heidi and Jack will will need to access Hall C to work on HMS dipole, to get dimensions befor\ e ordering the parts needed to install the crush washers.

ch wire groups are noisy

    • Xinzhan Bai and Jixie Zhang request to change gas bottle for solid Cherenkov detector: Contact: xbai@jlab.org, cell: (434) 422-2809 ( PENDING )

Planned Accelerator Configuration Changes

  • Full accelerator maintenance day on Thursday, Jun 23. Beam will be taken away at 6:30 am

Special Requests

  • Mark Jones would like to take HMS optics data with a 4x4 mm^2 raster at some point (when HMS is at a lower momentum, i.e., current setting) for checks. ( DONE </s\

pan>)