Difference between revisions of "March 5, 2023"
From HallCWiki
Jump to navigationJump to search (Created page with " Return to the calendar. = RC Meeting Information = Current RC: Iuliia Skorodumina. No RC meeting today. = Summary = = Accelerator Status = The is...") |
|||
Line 13: | Line 13: | ||
= Accelerator Status = | = Accelerator Status = | ||
− | The issue with Hall A BLM trips still persists. From | + | The issue with Hall A BLM trips still persists. From Friday's studies, the conclusion was made that the 4th pass separator is likely responsible for that (https://logbooks.jlab.org/entry/4142824). Unfortunately, this is not an easy fix and the repair work will realistically take a day and a half. The repair is scheduled for next Tuesday (March 7). For the weekend, it was decided that Halls B, C, and D will be getting beam, while Hall A will wait until Tuesday's repair. |
= Current Run Plan = | = Current Run Plan = | ||
The plan is to continue taking production data for the Pm=800 MeV/c at the highest possible current. | The plan is to continue taking production data for the Pm=800 MeV/c at the highest possible current. |
Revision as of 07:49, 5 March 2023
Return to the calendar.
RC Meeting Information
Current RC: Iuliia Skorodumina.
No RC meeting today.
Summary
Accelerator Status
The issue with Hall A BLM trips still persists. From Friday's studies, the conclusion was made that the 4th pass separator is likely responsible for that (https://logbooks.jlab.org/entry/4142824). Unfortunately, this is not an easy fix and the repair work will realistically take a day and a half. The repair is scheduled for next Tuesday (March 7). For the weekend, it was decided that Halls B, C, and D will be getting beam, while Hall A will wait until Tuesday's repair.
Current Run Plan
The plan is to continue taking production data for the Pm=800 MeV/c at the highest possible current.